1
© 2005 Prentice Hall, Inc. Managing Projects Dr. Mohammad Hamsal
2
© 2005 Prentice Hall, Inc. Task list WBS Constraint by budget and resources limited Time People Machines Materials Money A unique and One-time event Start Stop Definable things to do Has a measurable and quantifiable deliverables Initiated, planned, executed, controlled and close out Initiating Processes Planning Processes Planning Processes Controlling Processes Controlling Processes Closing Processes Closing Processes Executing Processes Executing Processes Has a define start and end dates (temporary) Has a specific objective to be completed within certain specification What is a Project?
3
© 2005 Prentice Hall, Inc. … identifying & achieving specific determined Goals by using Knowledge, Skills, Tools and Techniques … Time Saving Cost Saving Quality Achievement Customer (Stakeholder) Satisfaction Customer (Stakeholder) Satisfaction Process People Tools What is Project Management?
4
© 2005 Prentice Hall, Inc. Develop Marketing Plan Install Operating Control Base Select BankSelect NameFind Location Provide Staffing Provide Physical Facilities Establish Business Structure Work Breakdown Structure Strategic Plan Define Business Opportunity Plan for Action Proceed With Startup Plan Start a New Business
5
© 2005 Prentice Hall, Inc. Project Life Cycle StartFinish Resource requirements Time Definition and organization Planning Execution Close out
6
© 2005 Prentice Hall, Inc. Activity Relationships Activity Relationship S precedes T, which precedes U AOAAON 12 S 3 T 4 U STU
7
© 2005 Prentice Hall, Inc. Activity Relationships Activity Relationship S and T must be completed before U can be started AOAAON S T U 1 2 3 T S 4 U
8
© 2005 Prentice Hall, Inc. Activity Relationships Activity Relationship T and U cannot begin until S has been completed AOAAON T U S 3 4 1 T U 2 S
9
© 2005 Prentice Hall, Inc. Activity Relationships Activity Relationship U and V cannot begin until both S and T have been completed AOAAON 1 2 4 5 U V S T 3 S T U V
10
© 2005 Prentice Hall, Inc. Activity Relationships Activity Relationship U cannot begin until both S and T have been completed; V cannot begin until T has been completed AOAAON S T U V 13 Dummy 5 246 SU TV
11
© 2005 Prentice Hall, Inc. Activity Relationships Activity Relationship T and U cannot begin until S has been completed; V cannot begin until both T and U have been completed AOAAON 124 3 ST 5 V U Dummy STV U
12
© 2005 Prentice Hall, Inc. St. Adolf’s Hospital Immediate ActivityDescriptionPredecessor(s)Responsibility ASelect administrative and medical staff. BSelect site and do site survey. CSelect equipment. DPrepare final construction plans and layout. EBring utilities to the site. FInterview applicants and fill positions in nursing, support staff, maintenance, nursing, support staff, maintenance, and security. and security. GPurchase and take delivery of equipment. HConstruct the hospital. IDevelop an information system. JInstall the equipment. KTrain nurses and support staff.
13
© 2005 Prentice Hall, Inc. St. Adolf’s Hospital Immediate ActivityDescriptionPredecessor(s)Responsibility ASelect administrative and medical staff.—Johnson BSelect site and do site survey.—Taylor CSelect equipment.AAdams DPrepare final construction plans and layout.BTaylor EBring utilities to the site.BBurton FInterview applicants and fill positions inAJohnson nursing, support staff, maintenance, nursing, support staff, maintenance, and security. and security. GPurchase and take delivery of equipment.CAdams HConstruct the hospital.DTaylor IDevelop an information system.ASimmons JInstall the equipment.E,G,HAdams KTrain nurses and support staff.F,I,JJohnson
14
© 2005 Prentice Hall, Inc.Immediate ActivityDescriptionPredecessor(s)Responsibility ASelect administrative and medical staff.—Johnson BSelect site and do site survey.—Taylor CSelect equipment.AAdams DPrepare final construction plans and layout.BTaylor EBring utilities to the site.BBurton FInterview applicants and fill positions inAJohnson nursing, support staff, maintenance, nursing, support staff, maintenance, and security. and security. GPurchase and take delivery of equipment.CAdams HConstruct the hospital.DTaylor IDevelop an information system.ASimmons JInstall the equipment.E,G,HAdams KTrain nurses and support staff.F,I,JJohnson St. Adolf’s Hospital AON Network
15
© 2005 Prentice Hall, Inc.Immediate ActivityDescriptionPredecessor(s)Responsibility ASelect administrative and medical staff.—Johnson BSelect site and do site survey.—Taylor CSelect equipment.AAdams DPrepare final construction plans and layout.BTaylor EBring utilities to the site.BBurton FInterview applicants and fill positions inAJohnson nursing, support staff, maintenance, nursing, support staff, maintenance, and security. and security. GPurchase and take delivery of equipment.CAdams HConstruct the hospital.DTaylor IDevelop an information system.ASimmons JInstall the equipment.E,G,HAdams KTrain nurses and support staff.F,I,JJohnson St. Adolf’s Hospital AON Network Start A
16
© 2005 Prentice Hall, Inc.Immediate ActivityDescriptionPredecessor(s)Responsibility ASelect administrative and medical staff.—Johnson BSelect site and do site survey.—Taylor CSelect equipment.AAdams DPrepare final construction plans and layout.BTaylor EBring utilities to the site.BBurton FInterview applicants and fill positions inAJohnson nursing, support staff, maintenance, nursing, support staff, maintenance, and security. and security. GPurchase and take delivery of equipment.CAdams HConstruct the hospital.DTaylor IDevelop an information system.ASimmons JInstall the equipment.E,G,HAdams KTrain nurses and support staff.F,I,JJohnson St. Adolf’s Hospital AON Network Start A B
17
© 2005 Prentice Hall, Inc.Immediate ActivityDescriptionPredecessor(s)Responsibility ASelect administrative and medical staff.—Johnson BSelect site and do site survey.—Taylor CSelect equipment.AAdams DPrepare final construction plans and layout.BTaylor EBring utilities to the site.BBurton FInterview applicants and fill positions inAJohnson nursing, support staff, maintenance, nursing, support staff, maintenance, and security. and security. GPurchase and take delivery of equipment.CAdams HConstruct the hospital.DTaylor IDevelop an information system.ASimmons JInstall the equipment.E,G,HAdams KTrain nurses and support staff.F,I,JJohnson St. Adolf’s Hospital AON Network Start A B C
18
© 2005 Prentice Hall, Inc.Immediate ActivityDescriptionPredecessor(s)Responsibility ASelect administrative and medical staff.—Johnson BSelect site and do site survey.—Taylor CSelect equipment.AAdams DPrepare final construction plans and layout.BTaylor EBring utilities to the site.BBurton FInterview applicants and fill positions inAJohnson nursing, support staff, maintenance, nursing, support staff, maintenance, and security. and security. GPurchase and take delivery of equipment.CAdams HConstruct the hospital.DTaylor IDevelop an information system.ASimmons JInstall the equipment.E,G,HAdams KTrain nurses and support staff.F,I,JJohnson St. Adolf’s Hospital AON Network Start A B C D
19
© 2005 Prentice Hall, Inc.Immediate ActivityDescriptionPredecessor(s)Responsibility ASelect administrative and medical staff.—Johnson BSelect site and do site survey.—Taylor CSelect equipment.AAdams DPrepare final construction plans and layout.BTaylor EBring utilities to the site.BBurton FInterview applicants and fill positions inAJohnson nursing, support staff, maintenance, nursing, support staff, maintenance, and security. and security. GPurchase and take delivery of equipment.CAdams HConstruct the hospital.DTaylor IDevelop an information system.ASimmons JInstall the equipment.E,G,HAdams KTrain nurses and support staff.F,I,JJohnson St. Adolf’s Hospital AON Network Start A B C D E
20
© 2005 Prentice Hall, Inc.Immediate ActivityDescriptionPredecessor(s)Responsibility ASelect administrative and medical staff.—Johnson BSelect site and do site survey.—Taylor CSelect equipment.AAdams DPrepare final construction plans and layout.BTaylor EBring utilities to the site.BBurton FInterview applicants and fill positions inAJohnson nursing, support staff, maintenance, nursing, support staff, maintenance, and security. and security. GPurchase and take delivery of equipment.CAdams HConstruct the hospital.DTaylor IDevelop an information system.ASimmons JInstall the equipment.E,G,HAdams KTrain nurses and support staff.F,I,JJohnson St. Adolf’s Hospital AON Network Start A B C D E F
21
© 2005 Prentice Hall, Inc.Immediate ActivityDescriptionPredecessor(s)Responsibility ASelect administrative and medical staff.—Johnson BSelect site and do site survey.—Taylor CSelect equipment.AAdams DPrepare final construction plans and layout.BTaylor EBring utilities to the site.BBurton FInterview applicants and fill positions inAJohnson nursing, support staff, maintenance, nursing, support staff, maintenance, and security. and security. GPurchase and take delivery of equipment.CAdams HConstruct the hospital.DTaylor IDevelop an information system.ASimmons JInstall the equipment.E,G,HAdams KTrain nurses and support staff.F,I,JJohnson St. Adolf’s Hospital AON Network Start A B C D E F G
22
© 2005 Prentice Hall, Inc.Immediate ActivityDescriptionPredecessor(s)Responsibility ASelect administrative and medical staff.—Johnson BSelect site and do site survey.—Taylor CSelect equipment.AAdams DPrepare final construction plans and layout.BTaylor EBring utilities to the site.BBurton FInterview applicants and fill positions inAJohnson nursing, support staff, maintenance, nursing, support staff, maintenance, and security. and security. GPurchase and take delivery of equipment.CAdams HConstruct the hospital.DTaylor IDevelop an information system.ASimmons JInstall the equipment.E,G,HAdams KTrain nurses and support staff.F,I,JJohnson St. Adolf’s Hospital AON Network Start A B C D E F G H
23
© 2005 Prentice Hall, Inc.Immediate ActivityDescriptionPredecessor(s)Responsibility ASelect administrative and medical staff.—Johnson BSelect site and do site survey.—Taylor CSelect equipment.AAdams DPrepare final construction plans and layout.BTaylor EBring utilities to the site.BBurton FInterview applicants and fill positions inAJohnson nursing, support staff, maintenance, nursing, support staff, maintenance, and security. and security. GPurchase and take delivery of equipment.CAdams HConstruct the hospital.DTaylor IDevelop an information system.ASimmons JInstall the equipment.E,G,HAdams KTrain nurses and support staff.F,I,JJohnson St. Adolf’s Hospital AON Network Start A B C D E F G H I
24
© 2005 Prentice Hall, Inc.Immediate ActivityDescriptionPredecessor(s)Responsibility ASelect administrative and medical staff.—Johnson BSelect site and do site survey.—Taylor CSelect equipment.AAdams DPrepare final construction plans and layout.BTaylor EBring utilities to the site.BBurton FInterview applicants and fill positions inAJohnson nursing, support staff, maintenance, nursing, support staff, maintenance, and security. and security. GPurchase and take delivery of equipment.CAdams HConstruct the hospital.DTaylor IDevelop an information system.ASimmons JInstall the equipment.E,G,HAdams KTrain nurses and support staff.F,I,JJohnson St. Adolf’s Hospital AON Network Start A B C D E F G H I J
25
© 2005 Prentice Hall, Inc.Immediate ActivityDescriptionPredecessor(s)Responsibility ASelect administrative and medical staff.—Johnson BSelect site and do site survey.—Taylor CSelect equipment.AAdams DPrepare final construction plans and layout.BTaylor EBring utilities to the site.BBurton FInterview applicants and fill positions inAJohnson nursing, support staff, maintenance, nursing, support staff, maintenance, and security. and security. GPurchase and take delivery of equipment.CAdams HConstruct the hospital.DTaylor IDevelop an information system.ASimmons JInstall the equipment.E,G,HAdams KTrain nurses and support staff.F,I,JJohnson St. Adolf’s Hospital AON Network Start A B C D E F G H I J K
26
© 2005 Prentice Hall, Inc.Immediate ActivityDescriptionPredecessor(s)Responsibility ASelect administrative and medical staff.—Johnson BSelect site and do site survey.—Taylor CSelect equipment.AAdams DPrepare final construction plans and layout.BTaylor EBring utilities to the site.BBurton FInterview applicants and fill positions inAJohnson nursing, support staff, maintenance, nursing, support staff, maintenance, and security. and security. GPurchase and take delivery of equipment.CAdams HConstruct the hospital.DTaylor IDevelop an information system.ASimmons JInstall the equipment.E,G,HAdams KTrain nurses and support staff.F,I,JJohnson St. Adolf’s Hospital AON Network FinishStart A B C D E F G H I J K
27
© 2005 Prentice Hall, Inc.Immediate ActivityDescriptionPredecessor(s)Responsibility ASelect administrative and medical staff.—Johnson BSelect site and do site survey.—Taylor CSelect equipment.AAdams DPrepare final construction plans and layout.BTaylor EBring utilities to the site.BBurton FInterview applicants and fill positions inAJohnson nursing, support staff, maintenance, nursing, support staff, maintenance, and security. and security. GPurchase and take delivery of equipment.CAdams HConstruct the hospital.DTaylor IDevelop an information system.ASimmons JInstall the equipment.E,G,HAdams KTrain nurses and support staff.F,I,JJohnson St. Adolf’s Hospital AOA Network
28
© 2005 Prentice Hall, Inc.Immediate ActivityDescriptionPredecessor(s)Responsibility ASelect administrative and medical staff.—Johnson BSelect site and do site survey.—Taylor CSelect equipment.AAdams DPrepare final construction plans and layout.BTaylor EBring utilities to the site.BBurton FInterview applicants and fill positions inAJohnson nursing, support staff, maintenance, nursing, support staff, maintenance, and security. and security. GPurchase and take delivery of equipment.CAdams HConstruct the hospital.DTaylor IDevelop an information system.ASimmons JInstall the equipment.E,G,HAdams KTrain nurses and support staff.F,I,JJohnson St. Adolf’s Hospital AOA Network A Start 1 2
29
© 2005 Prentice Hall, Inc.Immediate ActivityDescriptionPredecessor(s)Responsibility ASelect administrative and medical staff.—Johnson BSelect site and do site survey.—Taylor CSelect equipment.AAdams DPrepare final construction plans and layout.BTaylor EBring utilities to the site.BBurton FInterview applicants and fill positions inAJohnson nursing, support staff, maintenance, nursing, support staff, maintenance, and security. and security. GPurchase and take delivery of equipment.CAdams HConstruct the hospital.DTaylor IDevelop an information system.ASimmons JInstall the equipment.E,G,HAdams KTrain nurses and support staff.F,I,JJohnson St. Adolf’s Hospital AOA Network A B Start 1 2 4
30
© 2005 Prentice Hall, Inc.Immediate ActivityDescriptionPredecessor(s)Responsibility ASelect administrative and medical staff.—Johnson BSelect site and do site survey.—Taylor CSelect equipment.AAdams DPrepare final construction plans and layout.BTaylor EBring utilities to the site.BBurton FInterview applicants and fill positions inAJohnson nursing, support staff, maintenance, nursing, support staff, maintenance, and security. and security. GPurchase and take delivery of equipment.CAdams HConstruct the hospital.DTaylor IDevelop an information system.ASimmons JInstall the equipment.E,G,HAdams KTrain nurses and support staff.F,I,JJohnson St. Adolf’s Hospital AOA Network A B C D Start 1 2 3 5 4
31
© 2005 Prentice Hall, Inc.Immediate ActivityDescriptionPredecessor(s)Responsibility ASelect administrative and medical staff.—Johnson BSelect site and do site survey.—Taylor CSelect equipment.AAdams DPrepare final construction plans and layout.BTaylor EBring utilities to the site.BBurton FInterview applicants and fill positions inAJohnson nursing, support staff, maintenance, nursing, support staff, maintenance, and security. and security. GPurchase and take delivery of equipment.CAdams HConstruct the hospital.DTaylor IDevelop an information system.ASimmons JInstall the equipment.E,G,HAdams KTrain nurses and support staff.F,I,JJohnson St. Adolf’s Hospital AOA Network F A B C D H E G I Start 1 8 2 3 7 65 4
32
© 2005 Prentice Hall, Inc.Immediate ActivityDescriptionPredecessor(s)Responsibility ASelect administrative and medical staff.—Johnson BSelect site and do site survey.—Taylor CSelect equipment.AAdams DPrepare final construction plans and layout.BTaylor EBring utilities to the site.BBurton FInterview applicants and fill positions inAJohnson nursing, support staff, maintenance, nursing, support staff, maintenance, and security. and security. GPurchase and take delivery of equipment.CAdams HConstruct the hospital.DTaylor IDevelop an information system.ASimmons JInstall the equipment.E,G,HAdams KTrain nurses and support staff.F,I,JJohnson St. Adolf’s Hospital AOA Network F A B C D H E G J I Start 1 8 2 3 7 65 4
33
© 2005 Prentice Hall, Inc.Immediate ActivityDescriptionPredecessor(s)Responsibility ASelect administrative and medical staff.—Johnson BSelect site and do site survey.—Taylor CSelect equipment.AAdams DPrepare final construction plans and layout.BTaylor EBring utilities to the site.BBurton FInterview applicants and fill positions inAJohnson nursing, support staff, maintenance, nursing, support staff, maintenance, and security. and security. GPurchase and take delivery of equipment.CAdams HConstruct the hospital.DTaylor IDevelop an information system.ASimmons JInstall the equipment.E,G,HAdams KTrain nurses and support staff.F,I,JJohnson St. Adolf’s Hospital AOA Network F A B C D H E G J I Dummy Start 1 8 2 3 7 65 4
34
© 2005 Prentice Hall, Inc.Immediate ActivityDescriptionPredecessor(s)Responsibility ASelect administrative and medical staff.—Johnson BSelect site and do site survey.—Taylor CSelect equipment.AAdams DPrepare final construction plans and layout.BTaylor EBring utilities to the site.BBurton FInterview applicants and fill positions inAJohnson nursing, support staff, maintenance, nursing, support staff, maintenance, and security. and security. GPurchase and take delivery of equipment.CAdams HConstruct the hospital.DTaylor IDevelop an information system.ASimmons JInstall the equipment.E,G,HAdams KTrain nurses and support staff.F,I,JJohnson St. Adolf’s Hospital AOA Network F A B C D H E G K J I Finish 9 Dummy Start 1 8 2 3 7 65 4
35
© 2005 Prentice Hall, Inc.Immediate ActivityDescriptionPredecessor(s)Responsibility ASelect administrative and medical staff.—Johnson BSelect site and do site survey.—Taylor CSelect equipment.AAdams DPrepare final construction plans and layout.BTaylor EBring utilities to the site.BBurton FInterview applicants and fill positions inAJohnson nursing, support staff, maintenance, nursing, support staff, maintenance, and security. and security. GPurchase and take delivery of equipment.CAdams HConstruct the hospital.DTaylor IDevelop an information system.ASimmons JInstall the equipment.E,G,HAdams KTrain nurses and support staff.F,I,JJohnson St. Adolf’s Hospital Completion Time FinishStart K6K6 I 15 F 10 C 10 D 10 E 24 G 35 H 40 J4J4 A 12 B9B9
36
© 2005 Prentice Hall, Inc.Immediate ActivityDescriptionPredecessor(s)Responsibility ASelect administrative and medical staff.—Johnson BSelect site and do site survey.—Taylor CSelect equipment.AAdams DPrepare final construction plans and layout.BTaylor EBring utilities to the site.BBurton FInterview applicants and fill positions inAJohnson nursing, support staff, maintenance, nursing, support staff, maintenance, and security. and security. GPurchase and take delivery of equipment.CAdams HConstruct the hospital.DTaylor IDevelop an information system.ASimmons JInstall the equipment.E,G,HAdams KTrain nurses and support staff.F,I,JJohnson St. Adolf’s Hospital Completion Time FinishStart K6K6 I 15 F 10 C 10 D 10 E 24 G 35 H 40 J4J4 A 12 B9B9
37
© 2005 Prentice Hall, Inc.Immediate ActivityDescriptionPredecessor(s)Responsibility ASelect administrative and medical staff.—Johnson BSelect site and do site survey.—Taylor CSelect equipment.AAdams DPrepare final construction plans and layout.BTaylor EBring utilities to the site.BBurton FInterview applicants and fill positions inAJohnson nursing, support staff, maintenance, nursing, support staff, maintenance, and security. and security. GPurchase and take delivery of equipment.CAdams HConstruct the hospital.DTaylor IDevelop an information system.ASimmons JInstall the equipment.E,G,HAdams KTrain nurses and support staff.F,I,JJohnson St. Adolf’s Hospital Completion Time FinishStart K6K6 I 15 F 10 C 10 D 10 E 24 G 35 H 40 J4J4 A 12 B9B9
38
© 2005 Prentice Hall, Inc.Immediate ActivityDescriptionPredecessor(s)Responsibility ASelect administrative and medical staff.—Johnson BSelect site and do site survey.—Taylor CSelect equipment.AAdams DPrepare final construction plans and layout.BTaylor EBring utilities to the site.BBurton FInterview applicants and fill positions inAJohnson nursing, support staff, maintenance, nursing, support staff, maintenance, and security. and security. GPurchase and take delivery of equipment.CAdams HConstruct the hospital.DTaylor IDevelop an information system.ASimmons JInstall the equipment.E,G,HAdams KTrain nurses and support staff.F,I,JJohnson St. Adolf’s Hospital Completion Time FinishStart K6K6 I 15 F 10 C 10 D 10 E 24 G 35 H 40 J4J4 A 12 B9B9
39
© 2005 Prentice Hall, Inc.Immediate ActivityDescriptionPredecessor(s)Responsibility ASelect administrative and medical staff.—Johnson BSelect site and do site survey.—Taylor CSelect equipment.AAdams DPrepare final construction plans and layout.BTaylor EBring utilities to the site.BBurton FInterview applicants and fill positions inAJohnson nursing, support staff, maintenance, nursing, support staff, maintenance, and security. and security. GPurchase and take delivery of equipment.CAdams HConstruct the hospital.DTaylor IDevelop an information system.ASimmons JInstall the equipment.E,G,HAdams KTrain nurses and support staff.F,I,JJohnson St. Adolf’s Hospital Completion Time FinishStart K6K6 I 15 F 10 C 10 D 10 E 24 G 35 H 40 J4J4 A 12 B9B9
40
© 2005 Prentice Hall, Inc.Immediate ActivityDescriptionPredecessor(s)Responsibility ASelect administrative and medical staff.—Johnson BSelect site and do site survey.—Taylor CSelect equipment.AAdams DPrepare final construction plans and layout.BTaylor EBring utilities to the site.BBurton FInterview applicants and fill positions inAJohnson nursing, support staff, maintenance, nursing, support staff, maintenance, and security. and security. GPurchase and take delivery of equipment.CAdams HConstruct the hospital.DTaylor IDevelop an information system.ASimmons JInstall the equipment.E,G,HAdams KTrain nurses and support staff.F,I,JJohnson St. Adolf’s Hospital Completion Time FinishStart K6K6 I 15 F 10 C 10 D 10 E 24 G 35 H 40 J4J4 A 12 B9B9
41
© 2005 Prentice Hall, Inc.Immediate ActivityDescriptionPredecessor(s)Responsibility ASelect administrative and medical staff.—Johnson BSelect site and do site survey.—Taylor CSelect equipment.AAdams DPrepare final construction plans and layout.BTaylor EBring utilities to the site.BBurton FInterview applicants and fill positions inAJohnson nursing, support staff, maintenance, nursing, support staff, maintenance, and security. and security. GPurchase and take delivery of equipment.CAdams HConstruct the hospital.DTaylor IDevelop an information system.ASimmons JInstall the equipment.E,G,HAdams KTrain nurses and support staff.F,I,JJohnson St. Adolf’s Hospital Completion Time FinishStart K6K6 I 15 F 10 C 10 D 10 E 24 G 35 H 40 J4J4 A 12 B9B9 Path Expected Time (wks) A-F-K28 A-I-K33 A-C-G-J-K67 B-D-H-J-K69 B-E-J-K43
42
© 2005 Prentice Hall, Inc.Immediate ActivityDescriptionPredecessor(s)Responsibility ASelect administrative and medical staff.—Johnson BSelect site and do site survey.—Taylor CSelect equipment.AAdams DPrepare final construction plans and layout.BTaylor EBring utilities to the site.BBurton FInterview applicants and fill positions inAJohnson nursing, support staff, maintenance, nursing, support staff, maintenance, and security. and security. GPurchase and take delivery of equipment.CAdams HConstruct the hospital.DTaylor IDevelop an information system.ASimmons JInstall the equipment.E,G,HAdams KTrain nurses and support staff.F,I,JJohnson St. Adolf’s Hospital Completion Time FinishStart K6K6 I 15 F 10 C 10 D 10 E 24 G 35 H 40 J4J4 A 12 B9B9 Path Expected Time (wks) A-F-K28 A-I-K33 A-C-G-J-K67 B-D-H-J-K69 B-E-J-K43
43
© 2005 Prentice Hall, Inc.Immediate ActivityDescriptionPredecessor(s)Responsibility ASelect administrative and medical staff.—Johnson BSelect site and do site survey.—Taylor CSelect equipment.AAdams DPrepare final construction plans and layout.BTaylor EBring utilities to the site.BBurton FInterview applicants and fill positions inAJohnson nursing, support staff, maintenance, nursing, support staff, maintenance, and security. and security. GPurchase and take delivery of equipment.CAdams HConstruct the hospital.DTaylor IDevelop an information system.ASimmons JInstall the equipment.E,G,HAdams KTrain nurses and support staff.F,I,JJohnson St. Adolf’s Hospital Completion Time FinishStart K6K6 I 15 F 10 C 10 D 10 E 24 G 35 H 40 J4J4 A 12 B9B9
44
© 2005 Prentice Hall, Inc. St. Adolf’s Hospital Earliest Start and Earliest Finish Times
45
© 2005 Prentice Hall, Inc. St. Adolf’s Hospital Earliest Start and Earliest Finish Times
46
© 2005 Prentice Hall, Inc. St. Adolf’s Hospital Earliest Start and Earliest Finish Times
47
© 2005 Prentice Hall, Inc. St. Adolf’s Hospital Earliest Start and Earliest Finish Times
48
© 2005 Prentice Hall, Inc. St. Adolf’s Hospital Earliest Start and Earliest Finish Times
49
© 2005 Prentice Hall, Inc. St. Adolf’s Hospital Earliest Start and Earliest Finish Times
50
© 2005 Prentice Hall, Inc. St. Adolf’s Hospital Earliest Start and Earliest Finish Times A 12 K6K6 C 10 G 35 J4J4 H 40 B9B9 D 10 E 24 0 12 I 15 F 10 12 27 12 22 19 59 9 33 0 9 9 19 12 22 Finish Start
51
© 2005 Prentice Hall, Inc. St. Adolf’s Hospital Earliest Start and Earliest Finish Times A 12 K6K6 C 10 G 35 J4J4 H 40 B9B9 D 10 E 24 0 12 I 15 F 10 12 27 12 22 22 57 19 59 9 33 0 9 9 19 12 22 Finish Start
52
© 2005 Prentice Hall, Inc. St. Adolf’s Hospital Earliest Start and Earliest Finish Times A 12 K6K6 C 10 G 35 J4J4 H 40 B9B9 D 10 E 24 0 12 I 15 F 10 12 27 12 22 22 57 59 6319 59 9 33 0 9 9 19 12 22 Finish Start
53
© 2005 Prentice Hall, Inc. St. Adolf’s Hospital Earliest Start and Earliest Finish Times
54
© 2005 Prentice Hall, Inc. St. Adolf’s Hospital A 12 K6K6 C 10 G 35 J4J4 H 40 B9B9 D 10 E 24 0 12 I 15 F 10 12 27 12 22 63 69 22 57 59 6319 59 9 33 0 9 9 19 12 22 Latest Start and Latest Finish Times Finish Start
55
© 2005 Prentice Hall, Inc. St. Adolf’s Hospital Latest Start and Latest Finish Times A 12 K6K6 C 10 G 35 J4J4 H 40 B9B9 D 10 E 24 0 12 I 15 F 10 12 27 12 22 63 69 22 57 59 6319 59 9 33 0 9 9 19 12 22 63 69 Latest finish time Finish Start
56
© 2005 Prentice Hall, Inc. St. Adolf’s Hospital Latest Start and Latest Finish Times A 12 K6K6 C 10 G 35 J4J4 H 40 B9B9 D 10 E 24 0 12 I 15 F 10 12 27 12 22 63 69 22 57 59 6319 59 9 33 0 9 9 19 12 22 63 69 Latest start time Latest finish time Finish Start
57
© 2005 Prentice Hall, Inc. St. Adolf’s Hospital A 12 K6K6 C 10 G 35 J4J4 H 40 B9B9 D 10 E 24 0 12 I 15 F 10 12 27 12 22 63 69 22 57 59 6319 59 9 33 0 9 9 19 12 22 48 63 53 63 63 69 59 63 Latest Start and Latest Finish Times Finish Start
58
© 2005 Prentice Hall, Inc. St. Adolf’s Hospital A 12 K6K6 C 10 G 35 J4J4 H 40 B9B9 D 10 E 24 0 12 I 15 F 10 12 27 12 22 63 69 22 57 59 6319 59 9 33 0 9 9 19 12 22 48 63 53 63 63 69 24 59 19 59 35 59 59 63 Latest Start and Latest Finish Times Finish Start
59
© 2005 Prentice Hall, Inc. St. Adolf’s Hospital A 12 K6K6 C 10 G 35 J4J4 H 40 B9B9 D 10 E 24 0 12 I 15 F 10 12 27 12 22 63 69 22 57 59 6319 59 9 33 0 9 9 19 12 22 48 63 53 63 63 69 14 24 24 59 9 19 19 59 35 59 59 63 Latest Start and Latest Finish Times Finish Start
60
© 2005 Prentice Hall, Inc. St. Adolf’s Hospital Latest Start and Latest Finish Times
61
© 2005 Prentice Hall, Inc. St. Adolf’s Hospital Gantt Charts
62
© 2005 Prentice Hall, Inc. St. Adolf’s Hospital Gantt Charts
63
© 2005 Prentice Hall, Inc. St. Adolf’s Hospital Activity Slack
64
© 2005 Prentice Hall, Inc. St. Adolf’s Hospital Activity Slack Analysis A 12 K6K6 C 10 G 35 J4J4 H 40 B9B9 D 10 E 24 0 12 I 15 F 10 12 27 12 22 63 69 22 57 59 6319 59 9 33 0 9 9 19 12 22 48 63 2 14 53 63 63 69 14 24 24 59 0 9 9 19 19 59 35 59 59 63 Finish Start
65
© 2005 Prentice Hall, Inc. St. Adolf’s Hospital Start A 12 K6K6 C 10 G 35 J4J4 H 40 B9B9 D 10 E 24 0 12 I 15 F 10 12 27 12 22 63 69 22 57 59 6319 59 9 33 0 9 9 19 12 22 48 63 2 14 53 63 63 69 14 24 24 59 0 9 9 19 19 59 35 59 59 63 Finish Activity Slack Analysis Activity Slack
66
© 2005 Prentice Hall, Inc. St. Adolf’s Hospital Start A 12 K6K6 C 10 G 35 J4J4 H 40 B9B9 D 10 E 24 0 12 I 15 F 10 12 27 12 22 63 69 22 57 59 6319 59 9 33 0 9 9 19 12 22 48 63 2 14 53 63 63 69 14 24 24 59 0 9 9 19 19 59 35 59 59 63 Finish Activity Slack Analysis Activity Slack Slack = LS – ES or Slack = LF – EF
67
© 2005 Prentice Hall, Inc. St. Adolf’s Hospital Start A 12 K6K6 C 10 G 35 J4J4 H 40 B9B9 D 10 E 24 0 12 I 15 F 10 12 27 12 22 63 69 22 57 59 6319 59 9 33 0 9 9 19 12 22 48 63 2 14 53 63 63 69 14 24 24 59 0 9 9 19 19 59 35 59 59 63 Finish Activity Slack Analysis Activity Slack Slack K = 63 – 63 or Slack K = 69 – 69
68
© 2005 Prentice Hall, Inc. St. Adolf’s Hospital Start A 12 K6K6 C 10 G 35 J4J4 H 40 B9B9 D 10 E 24 0 12 I 15 F 10 12 27 12 22 63 69 22 57 59 6319 59 9 33 0 9 9 19 12 22 48 63 2 14 53 63 63 69 14 24 24 59 0 9 9 19 19 59 35 59 59 63 Finish Activity Slack Analysis Activity Slack Slack K = 0 or Slack K = 0
69
© 2005 Prentice Hall, Inc. St. Adolf’s Hospital Start A 12 K6K6 C 10 G 35 J4J4 H 40 B9B9 D 10 E 24 0 12 I 15 F 10 12 27 12 22 63 69 22 57 59 6319 59 9 33 0 9 9 19 12 22 48 63 2 14 53 63 63 69 14 24 24 59 0 9 9 19 19 59 35 59 59 63 Finish Activity Slack Analysis
70
© 2005 Prentice Hall, Inc. St. Adolf’s Hospital Start A 12 K6K6 C 10 G 35 J4J4 H 40 B9B9 D 10 E 24 0 12 I 15 F 10 12 27 12 22 63 69 22 57 59 6319 59 9 33 0 9 9 19 12 22 48 63 2 14 53 63 63 69 14 24 24 59 0 9 9 19 19 59 35 59 59 63 Finish Activity Slack Analysis Node DurationESLS Slack
71
© 2005 Prentice Hall, Inc. St. Adolf’s Hospital Start A 12 K6K6 C 10 G 35 J4J4 H 40 B9B9 D 10 E 24 0 12 I 15 F 10 12 27 12 22 63 69 22 57 59 6319 59 9 33 0 9 9 19 12 22 48 63 2 14 53 63 63 69 14 24 24 59 0 9 9 19 19 59 35 59 59 63 Finish Activity Slack Analysis Node DurationESLS Slack A12022 B9000 C1012142 D10990 E2493526 F10125341 G3522242 H4019190 I15124836 J459590 K663630
72
© 2005 Prentice Hall, Inc. St. Adolf’s Hospital C 10 G 35 E 24 I 15 F 10 12 27 12 22 22 57 9 33 12 22 48 63 53 63 14 24 24 59 35 59 B9B9 0 9 D 10 9 19 H 40 19 59 J4J4 59 63 K6K6 63 69 Finish Critical Path Node DurationESLS Slack A12022 B9000 C1012142 D10990 E2493526 F10125341 G3522242 H4019190 I15124836 J459590 K663630
73
© 2005 Prentice Hall, Inc. St. Adolf’s Hospital C 10 G 35 E 24 I 15 F 10 12 27 12 22 22 57 9 33 12 22 48 63 53 63 14 24 24 59 35 59 B9B9 0 9 D 10 9 19 H 40 19 59 J4J4 59 63 K6K6 63 69 A 12 0 12 2 14 Finish Start Critical Path
74
© 2005 Prentice Hall, Inc. Probabilistic Time Estimates Beta Distribution Mean mab Time Probability
75
© 2005 Prentice Hall, Inc. Probabilistic Time Estimates Time Probability Normal Distribution Mean abm 3333 3333 Area under curve between a and b is 99.74%
76
© 2005 Prentice Hall, Inc. St. Adolf’s Hospital Probabilistic Time Estimates AF I CG Finish D E HBJ K Start te =te =te =te = a + 4m + b 6Mean 2 =2 =2 =2 = ( ) b – ab – a66b – ab – a666 2Variance
77
© 2005 Prentice Hall, Inc. St. Adolf’s Hospital Activity B Most OptimisticLikelyPessimistic (a)(m)(b) 7815 Probabilistic Time Estimates AF I CG Finish D E HBJ K Start
78
© 2005 Prentice Hall, Inc. St. Adolf’s Hospital Activity B Most OptimisticLikelyPessimistic (a)(m)(b) 7815 Probabilistic Time Estimates t e = = 9 weeks 7 + 4(8) + 15 6 2 = = 1.78 ( ) 15 - 7 6 2 AF I CG Finish D E HBJ K Start
79
© 2005 Prentice Hall, Inc. St. Adolf’s Hospital OptimisticLikelyPessimisticExpectedVariance Activity(a)(m)(b)Time (t e )( 2 ) Time Estimates (wk)Activity Statistics A111213120.11 B781591.78 C51015102.78 D8916101.78 E142530247.11 F6918104.00 G253641357.11 H354045402.78 I101328159.00 J121545.44 K56760.11
80
© 2005 Prentice Hall, Inc. St. Adolf’s Hospital 2 = (variances of activities) z = T – T E 2 2 = 1.78 + 1.78 + 2.78 + 5.44 + 0.11 = 11.89 z = 72 – 69 11.89 Probabilities Critical Path = B - D - H - J - K T = 72 days T E = 69 days
81
© 2005 Prentice Hall, Inc. St. Adolf’s Hospital 2 = (variances of activities) z = T – T E 2 2 = 1.78 + 1.78 + 2.78 + 5.44 + 0.11 = 11.89 z = = 0.87 72 – 69 11.89 Probabilities Critical Path = B - D - H - J - K T = 72 days T E = 69 days From Table Normal Dist. P z =.8078 .81
82
© 2005 Prentice Hall, Inc. St. Adolf’s Hospital 2 = (variances of activities) z = T – T E 2 2 = 1.78 + 1.78 + 2.78 + 5.44 + 0.11 = 11.89 z = = 0.87 72 – 69 11.89 Probabilities Critical Path = B - D - H - J - K T = 72 days T E = 69 days From Appendix 2 P z =.8078 .81 Project duration (weeks) 6972 Probability of meeting the schedule is 0.8078 Length of critical path Normal distribution: Mean = 69 weeks; = 3.45 weeks Probability of exceeding 72 weeks is 0.1922