Presentation is loading. Please wait.

Presentation is loading. Please wait.

Preliminary Design & Steel Deck Alternative Presentation

Similar presentations


Presentation on theme: "Preliminary Design & Steel Deck Alternative Presentation"— Presentation transcript:

1 Preliminary Design & Steel Deck Alternative Presentation
Project : Ministry of Taxation Tower BAKU Office & Residental Tower Preliminary Design & Steel Deck Alternative Presentation

2 General 3D Views

3 Upper 2 Cubes Residental Usage
General Architectural Design Concept Upper 2 Cubes Residental Usage Lower 3 Cubes Office Usage Podium & Auditorium

4 General Overview The site is located on Haydar Aliyev Avenue in Baku.
General Section of MOT Tower

5 General Schematic Designers

6 General Overview of Schematic Structural Design
From WSI Schematic Design Typical PT Slabs by WSI

7 Lower Cube Structural System
Lower Cube System

8 Upper Cube Structural System
Cantilever PT Slabs Central Core Lower Cube System

9 Brief Structural Description of MOT Tower Vertical Load Bearing System

10 Brief Structural Description of MOT Tower Lateral Load Bearing System

11 Design Standards and Codes

12 Structural Materials

13 Structural Materials

14 Loads Vertical Loads on Stories & Podium

15 Loads Wind Loads From the rigid tunnel test results of Wacker Engineering

16 Overall maximum forces and moments for the tower “Ministry of Taxation” –
proximity model

17 Loads Seismic Loads

18 Loads Seismic Loads

19 Loads Seismic Loads

20 Loads Seismic Loads

21 Main Structural Issues
ETABS Model

22 Main Structural Issues
Outer Core Wall Thicknesses with initial stiffnes of tower

23 Main Structural Issues
Extruded View of the Core & Core Thicknesses Inner Core uniform thickness 40 cm Outer core thickness varying thickness 100cm from bottom to 40 cm at top

24 Modal Analysis Results (According to WSI Design )
Main Structural Issues Modal Analysis Results (According to WSI Design )

25 Main Structural Issues
- Main challenging issue may be assumed as Wind Load. In Baku Wind Load effects have very high values. Wacker Engineering Wind Tunnel Rigid Test Results Mean value of Wind Loads

26 Wacker Engineering Wind Tunnel Rigid Test Results Total Story Shears
Main Structural Issues Wacker Engineering Wind Tunnel Rigid Test Results Total Story Shears

27 With the initial stiffness of tower :
Main Structural Issues With the initial stiffness of tower : T = 4.24 s T = 4.24 s f = Hz

28 Main recommendations from the first wind tunnel test (rigid) results :
Main Structural Issues Main recommendations from the first wind tunnel test (rigid) results :

29 Main recommendations from the first wind tunnel test (rigid) results :
Main Structural Issues Main recommendations from the first wind tunnel test (rigid) results :

30 Main Structural Issues
Main recommendations from the first wind tunnel test (rigid) results :

31 Top Story Acceleration
Main Structural Issues Top Story Acceleration Two arising problems after first rigid wind tunnel test result Vortex Resonance Effect of Wind Load

32 Main Structural Issues
Top Story Accelaration Criteria Check with initial tower stiffness

33 Increased Core Wall thicknesses for aeroelastic wind tunnel test
Main Structural Issues Aeroelastic test results with increased stiffness of the tower. Increased Core Wall thicknesses for aeroelastic wind tunnel test

34 Main Structural Issues
Aeroelastic test results conclusions

35 Top Story Acceleration
Main Structural Issues With stiffening the outer core wall of the tower ; NOT OK. Acceleration at Cube 5 is still not acceptable for residential criterias. Top Story Acceleration Vortex Resonance Effect of Wind Load OK, could be excluded for MOT Tower with frequency of 0.29 Hz.

36 Main Structural Issues

37 Alternative Solution of TMD adapted Tower with Composite Steel Deck Slabs;
Advantages : Major decrease in the tower total mass. Seismic shear forces reduction. Seismic base moment reduction. Economy for foundation & pile design Decrease in the period of the building due to the dead mass decrease. This causes increase of the tower’s frequency. Required damper mass will be less than compared to PT RC slab design. Total weight and the total cost of the damper will be less compared to required damper for initial PT RC slab design.

38 Alternative Solution of TMD adapted Tower with Composite Steel Deck Slabs;
Comparison Table : MoT Tower Comparison of 2 Systems ( Freysinet proposed PT System & Steel Composite Deck ) Parameter PT System Composite Steel Deck Decrease ( % ) Dead Mass (kN) 507500 392000 22.76 Seismic Mass (kN) 640000 525000 17.97 Seismic Base Shear (kN) 2840 2350 17.25 Seismic Overturning Moment (mN) 3400 2710 20.29 First period of the structure (s) 4.52 4.01 11.28 Frequency of the structure (Hz) 0.22 0.25 -13.64 Apprx. Required TMD Weight (kN) 5500 4500 18.18

39 Alternative Solution of TMD adapted Tower with Composite Steel Deck Slabs;
Comparison of Core Reinforcement Ratios. Reinforcement Ratios of MOT Tower Inner & Outer Core Materials Concrete C50 Reinforcement fyk = 420 Mpa Inner Core Uniform Coefficient for Final Elevations Wall thickness (cm) Reinforcement Ratio Quantity splices, etc Foundation ~ m 40 0.01 78.5 1.3 102.05 m m m ~ m m ~ m 0.008 62.8 81.64 107.10m ~ m 136.80m ~ m Outer Core -1 100 0.035 274.75 80 50 0.025 196.25 0.02 157 204.1 0.015 117.75 Outer Core -2 Overall Average 180.47

40 Typical Structural Solutions for Lower Cubes
3D View of the Lower 3 Cubes ROTATING FLOOR SLABS CUBE COLUMNS Φ508 mm STEEL TRANSFER TRUSSES

41 Typical Structural Solutions for Lower Cubes
3D View of the Lower 3 Cubes STEEL TRANSFER TRUSSES FOR FIRST 3 CUBES

42 Typical Structural Solutions for Lower Cubes Terrace Floor Plans
PERIMETER BEAMS SECONDARY BEAMS COMPOSITE STEEL DECK

43 Typical Structural Solutions for Lower Cubes Office Floor Plans
PERIMETER BEAMS SECONDARY BEAMS COMPOSITE STEEL DECK

44 DEFLECTION CHECK (G+Q)
OFFICE FLOORS RELATIVE DISPLACEMENT OF CANTILEVER ARM ~ 48 mm LIMIT L/150 = 840 /150 = 5.6 cm

45 DEFLECTION CHECK LOWER 3 CUBES
RELATIVE DISPLACEMENT OF TRANSFER TRUSS ~ 50 mm LIMIT L/150 = 1100 /150 = cm

46 Typical Structural Solutions for 4th Cube 3D View of the 4th Cube
ROTATING FLOOR SLABS CUBE COLUMNS Φ457 mm STEEL TRANSFER TRUSSES

47 Typical Structural Solutions for 4th Cube 3D View of the 4th Cube
STEEL TRANSFER TRUSSES FOR 4th CUBE

48 Typical Structural Solutions for 4th Cube Terrace Floor Plans
PERIMETER BEAMS SECONDARY BEAMS COMPOSITE STEEL DECK

49 Typical Structural Solutions for 4th Cube Office Floor Plans
PERIMETER BEAMS SECONDARY BEAMS COMPOSITE STEEL DECK

50 DEFLECTION CHECK (G+Q)
OFFICE FLOORS RELATIVE DISPLACEMENT OF CANTILEVER ARM ~ 25 mm LIMIT L/150 = 700 /150 = cm

51 DEFLECTION CHECK 4th CUBE
RELATIVE DISPLACEMENT OF TRANSFER TRUSS ~ 51 mm LIMIT L/150 = 780 /150 = 5.2 cm

52 Typical Structural Solutions for 5th Cube 3D View of the 5th Cube
ROTATING FLOOR SLABS CUBE COLUMNS Φ323.9 mm STEEL TRUSSES

53 Typical Structural Solutions for 5th Cube Terrace Floor Plans
PERIMETER BEAMS SECONDARY BEAMS COMPOSITE STEEL DECK

54 Typical Structural Solutions for 5th Cube Residential Floor Plans
PERIMETER BEAMS SECONDARY BEAMS COMPOSITE STEEL DECK

55 DEFLECTION CHECK (G+Q)
RESIDENTIAL FLOORS RELATIVE DISPLACEMENT OF CANTILEVER ARM ~ 69 mm LIMIT L/150 = 1060 /150 = 7.1 cm

56 DEFLECTION CHECK 5th CUBE RELATIVE DISPLACEMENT OF TRUSS ~ 62 mm
LIMIT L/150 = 1060 /150 = 7.1 cm

57 Typical Details for Composite Steel Deck

58 Typical Details for Composite Steel Deck

59 For connection elements, splices (0.25 coefficient is used)=
Material List for Preliminary Steel Design Cube by Cube MOT TOWER MATERIAL LIST Section NumPieces TotalLength TotalWeight Text Unitless m Tonf TOP CUBE IPE270 41 124.17 4.47 IPE330 33 216.96 10.66 IPE360 48 324.82 18.54 IPE400 88 722.82 47.94 IPE450 8 96.06 7.45 IPE500 16 121.29 11.04 IPE600 101.50 12.43 HE200B 36.35 2.23 HE220B 4 8.92 0.64 HE240B 26.79 HE260B 19.79 1.83 HE280B 24 64.88 6.67 HE300B 10.36 1.21 HE320B 12 74.94 9.47 HE400B 26 71.01 IPE 6.60 0.70 IPE 13.20 1.13 TUBO-D114.3X3.6 100 226.66 PIPE323.9*12 105.82 9.77 The Total Weight of Profiles= 161.68 For connection elements, splices (0.25 coefficient is used)= 40.42 The Total Weight of top Cube= 202.09 The Total Composite Deck Area approximately 1950m², kg/m² 103.64

60 For connection elements, splices (0.25 coefficient is used)=
Material List for Preliminary Steel Design Cube by Cube MOT TOWER MATERIAL LIST Section NumPieces TotalLength TotalWeight Text Unitless m Tonf CUBE 4 IPE200 44 3.9319 IPE220 64 9.7344 IPE240 80 IPE270 40 IPE300 12 3.5874 IPE600 136 HE220B 48 8.1828 HE320B 24 HE360B 47 HE400B 1 0.3079 PIPE457.2*16 The Total Weight of Profiles= 264.34 For connection elements, splices (0.25 coefficient is used)= 66.08 The Total Weight of Cube 4= 330.42 The Total Composite Deck Area approximately 3341m², kg/m² 98.90

61 CUBE 3 Material List for Preliminary Steel Design Cube by Cube
MOT TOWER MATERIAL LIST Section NumPieces TotalLength TotalWeight Text Unitless m Tonf CUBE 3 IPE300 172 51.22 IPE500 8 73.24 6.67 IPE600 72 720.00 88.17 IPE360 44 372.10 21.24 IPE270 326.75 11.75 IPE450 28 263.18 20.41 PIPE 508/10 32 140.89 17.03 HE200A 16 70.40 2.97 35.22 1.49 HE300A 4 17.60 1.56 HE600B 88 240.02 49.75 HE360B 64 250.35 35.57 The Total Weight of Profiles= 307.82 For connection elements, splices (0.25 coefficient is used)= 76.96 The Total Weight of Cube 3= 384.78 The Total Composite Deck Area approximately 3825m², kg/m² 100.60

62 For connection elements, splices (0.25 coefficient is used)=
Material List for Preliminary Steel Design Cube by Cube MOT TOWER MATERIAL LIST Section NumPieces TotalLength TotalWeight Text Unitless m Tonf CUBE 2 IPE300 172 58.47 IPE500 8 83.62 7.61 IPE600 72 822.02 100.66 IPE360 44 424.83 24.25 IPE270 373.05 13.42 IPE450 28 300.47 23.30 PIPE 508/10 32 160.86 19.44 HE200A 16 80.38 3.39 40.21 1.70 HE300A 4 20.09 1.78 HE600B 88 274.04 56.80 HE360B 64 285.82 40.61 The Total Weight of Profiles= 351.44 For connection elements, splices (0.25 coefficient is used)= 87.86 The Total Weight of Cube 2= 439.30 The Total Composite Deck Area approximately 4367m², kg/m² 100.60

63 For connection elements, splices (0.25 coefficient is used)=
Material List for Preliminary Steel Design Cube by Cube MOT TOWER MATERIAL LIST Section NumPieces TotalLength TotalWeight Text Unitless m Tonf CUBE 1 IPE300 172 64.91 IPE500 8 92.82 8.45 IPE600 72 912.45 111.74 IPE360 44 471.56 26.91 IPE270 414.08 14.89 IPE450 28 333.52 25.87 PIPE 508/10 32 178.55 21.58 HE200A 16 89.22 3.77 44.64 1.89 HE300A 4 22.30 1.98 HE600B 88 304.18 63.04 HE360B 64 317.26 45.08 The Total Weight of Profiles= 390.10 For connection elements, splices (0.25 coefficient is used)= 96.32 The Total Weight of Cube 1= 481.61 The Total Composite Deck Area approximately 4841m², kg/m² 99.50

64 Total weight of the steel =
Material List for Preliminary Steel Design Total Weight Total weight of the steel = 1840 t For connection elements, splices (0.25 coefficient is used) Steel deck weight is not included in the total weight.

65 Primary Details & Critical Points for Composite Steel Deck System ;
Vibration Check for Composite Slabs

66 Primary Details & Critical Points for Composite Steel Deck System ;
- Vibration Check for Composite Slabs Damping ratio is accepted as 0.03 To take the effect of walls into account.

67 Primary Details & Critical Points for Composite Steel Deck System ;
- Vibration Check for Composite Slabs Acceptance Criteria for Human Walking Excitation

68 Primary Details & Critical Points for Composite Steel Deck System ;
- Vibration Check for Composite Slabs SLAB CHECK 1 SLAB CHECK 2

69 Primary Details & Critical Points for Composite Steel Deck System ;
- Slab Check 1 Vibration Check Joist / Beam Mode Maximum moment at beam due to dead loads M = 115 kNm Linear Load from dead loads wjb = kN/m Additional deflections Deflection due to dead loads Support Deflection 15 mm Column Deflection 56 Δjb = m Frequency of the composite slab fjb Total weight of the composite slab wj

70 Primary Details & Critical Points for Composite Steel Deck System ;
- Slab Check 1 Floor occupancy Office Acceleration limit 0.005 g Constant Force 0.29 kN Damping Ratio 0.03 Panel acceleration value Ap m/s^2 OK Target

71 Primary Details & Critical Points for Composite Steel Deck System ;
- Slab Check 1 Vibration Check Combined Mode wg = kN/m Support Deflection 49 mm Column Deflection Girder Length 15 m Wg kN ( with effective panel weight ) Δgb = 30 fgb Hz fgb (combined) W

72 Primary Details & Critical Points for Composite Steel Deck System ;
- Slab Check 1 Floor occupancy Office Acceleration limit 0.005 g Constant Force 0.29 kN Damping Ratio 0.03 Panel acceleration value Ap m/s^2 Target

73 Primary Details & Critical Points for Composite Steel Deck System ;
- Slab Check 2 Vibration Check Maximum moment at beam due to dead loads M = 80 kNm Linear Load from dead loads wjb = kN/m Deflection due to dead loads Support Deflection 84 mm Column Deflection Δjb = m Frequency of the composite slab fjb Total weight of the composite slab wj

74 Primary Details & Critical Points for Composite Steel Deck System ;
- Slab Check 2 Floor occupancy Office Acceleration limit 0.005 g Should be filled manually Constant Force 0.29 kN Damping Ratio 0.04 Panel acceleration value Ap m/s^2 OK Target

75 Primary Details & Critical Points for Composite Steel Deck System ;
- Vibration Check for Composite Slabs SLAB CHECK 3

76 Primary Details & Critical Points for Composite Steel Deck System ;
- Slab Check 3 Vibration Check Joist / Beam Mode Maximum moment at beam due to dead loads M = 137 kNm Linear Load from dead loads wjb = 7.0144 kN/m Additional deflections Deflection due to dead loads Support Deflection 51 mm Column Deflection Δjb = m Frequency of the composite slab fjb Total weight of the composite slab wj 87.68

77 Primary Details & Critical Points for Composite Steel Deck System ;
- Slab Check 3 Floor occupancy Office Acceleration limit 0.005 g Constant Force 0.29 kN Damping Ratio 0.03 Panel acceleration value Ap m/s^2 Target

78 Office & Residental Tower Upper&Lower Cubes – Truss & Core Connection
Project : Ministry of Taxation Tower BAKU Office & Residental Tower Upper&Lower Cubes – Truss & Core Connection Typical Details

79 Typical Structural Solutions for 5th Cube 3D View of the 5th Cube
Transfer Truss

80 3d View of The 4th Cube Transfer Truss

81 3d View of The 3th Cube ( Similar to 1st and 2nd Cube )
Transfer Truss

82 Plan View of The Transfer Story at the 5th Cube
Transfer Trusses

83 Plan View of The Transfer Story at the 4th Cube
Transfer Trusses

84 Plan View of The Transfer Story at the 3rd Cube
Transfer Trusses

85 3d View of The 3th Cube Truss (Similar to 1st and 2nd Cube)

86 3d View of The 3th Cube Truss (Similar to 1st and 2nd Cube)

87 3D View of the Transfer Truss at 4th Cube

88 3D View of the Transfer Truss at 5th Cube

89 Axial Load Diagram of Truss Elements (Most Unfavorable Combination)
P(tension) = 1670 kN P(compression) = 3410 kN

90 Punching Check of The Core Wall 5th Cube (Governing action at bottom chord connection)

91 Punching Check of The Core Wall P1 = 1670 kN P2 = - 2380 kN
Equivalent Horizontal Force : Phor = P3*cos7+P2*sin47= 5150 kN Vd = 5150 kN Vrc = ϒ . Up. fctd . d ϒ = 0.90 fctd = 1650 kN/m2 (C50) Up = ( ) x 2 + ( ) x 2 = 4.7m d = 0.45 m Vrc = 0.90 x 4.7 x 1650 x 0.45 = 3140 kN

92 Vr = Vrc + Vrs Vrs = 5150 – 3140 = 2010 kN 8 x φ 20 / 150 selected transverse reinforcement Asw / sw = cm2 /m Rsw = 30 kN/cm2 Vrs = Asw / sw x d x Rsw = 2261 kN > Vrs = 2010 kN OK. Concrete Bearing Check σ = ( Phor / Aplate ) = 5150 / ( 1.20 * 0.70 ) = 6130 kN/cm2 σlim = fcd*/2 = kN/cm2 > 6130 kN/cm OK. Uniform Core Wall Thickness t = 500 mm Plate dimensions 0.70 m * 1.20 m

93 Vertical Shear Force will be transferred by bolts
Equivalent Vertical Force : Pver = P3.sin7+P2*cos47 = 2040 kN

94 Vertical Shear Force will be transferred by bolts
1 bolt shear strength (8.8) M36 Vrs = 0.75*0.45*Fu = 0.45*8 * =27.45t n = 204 / 27.45= 8 bolts for connection

95 Top Chord Brace Connection to Core
Check of Anchor Bolts at tension Ptmax = kN

96 Top Chord Connection to Truss
Check of Anchor Bolts (M36 – 8.8) Pr = 0.75 * 0.75 * 8 * * 12 = 548 t > Pd = 200 t

97 Top Chord Connection to Truss
Punching Shear at Top Chord 12 M36 8.8

98 Uniform Core Wall Thickness t = 500 mm Plate dimension 600 mm* 600 mm
Vd = 2000 kN Vrc = ϒ . Up. fctd . d ϒ = 0.90 fctd = 1650 kN/m2 (C50) Up = ( 4*1.08) = 4.32 m d = 0.45 m Vrc = 0.90 x x 1650 x 0.45 = 2880 kN > Vd = 2000 kN Concrete Bearing Check σ = ( Phor / Aplate ) = 2000 / ( 0.6*0.6 ) = 5555 kN/cm2 σlim = fcd*/2 = kN/cm2 > 5555kN/cm OK. Uniform Core Wall Thickness t = 500 mm Plate dimension 600 mm* 600 mm

99 Punching Check of The Core Wall 4th Cube (Governing action at bottom chord connection)

100 Punching Check of The Core Wall P1 = 2000 kN P2 = -2380 kN
Equivalent Horizontal Force : Phor =P3 = 3000 kN Vd = 3000 kN Vrc = ϒ . Up. fctd . d ϒ = 0.90 fctd = 1650 kN/m2 (C50) Up = ( ) x 2 + ( ) x 2 = 3.3 m d = 0.45 m Vrc = 0.90 x 3.3 x 1650 x 0.45 = 2205 kN

101 Vr = Vrc + Vrs Vrs = 3000 – 2205 = 795 kN 5 x φ 16 / 150 selected transverse reinforcement Asw / sw = cm2 /m Rsw = 30 kN/cm2 Vrs = Asw / sw x d x Rsw = 904 kN > Vrs = = 795 kN OK. Concrete Bearing Check σ = ( Phor / Aplate ) = 3000 / ( 0.60 * 0.60 ) = 8333 kN/cm2 σlim = fcd*/2 = kN/cm2 > 8333 kN/cm OK. Uniform Core Wall Thickness t = 500 mm Plate dimensions m * 0.60 m

102 Top Chord Connection to Core
Check of Anchor Bolts at tension Ptmax = kN kN * cos45 = 3697 kN

103 Top Chord Connection to Truss
Check of Anchor Bolts (M36 – 8.8) Pr = 0.75 * 075 * 8 * * 12 = 549 t > Pd = 369 t

104 Top Chord Connection to Truss
Punching Shear at Top Chord

105 Uniform Core Wall Thickness t = 500 mm Plate dimension 600 mm* 600 mm
Vd = 3697 kN Vrc = ϒ . Up. fctd . d ϒ = 0.90 fctd = 1650 kN/m2 (C50) Up = ( 0.82*4) = 3.28m d = 0.45 m Vrc = 0.90 x 3.28 x 1650 x 0.45 = 2191 kN > Vd = 2000 kN Concrete Bearing Check σ = ( Phor / Aplate ) = 3697 / ( 0.60 * 4) = 1540 kN/cm2 σlim = fcd*/2 = kN/cm2 > 1127kN/cm OK. Uniform Core Wall Thickness t = 500 mm Plate dimension 600 mm* 600 mm

106 Vertical Shear Force will be transferred by bolts
Equivalent Vertical Force : Pver = P3.sin7 + P2.sin50 = 2240 kN

107 Vertical Shear Force will be transferred by bolts
1 bolt shear strength (8.8) M36 Vrs = 0.75*0.45*Fu = 80 * 0.45 * = kN n = 2240 / = 9 bolts for connection 12 M36 Vr = 3300 kN > 2240 kN

108 Punching Check of The Core Wall 3th Cube ( Governing action at bottom plate connection )
P1= Total tensile force P2= Total compressive force

109 Punching Check of The Core Wall P1 = 12400 kN P2 = -12060 kN
Vd = kN Vrc = ϒ . Up. fctd . d ϒ = 0.90 fctd = 1650 kN/m2 (C50) Up = ( ) x 2 + ( ) x 2 = m d = 0.45 m Vrc = 0.90 x x 1650 x 0.45 = 9034 kN

110 Vr = Vrc + Vrs Vrs = –9034 = 3366 kN Asw / sw = 250 cm2 /m OK. Concrete Bearing Check σ = ( Phor / Aplate ) = / ( 5.25 * 1.06 ) = 2228 kN/cm2 σlim = fcd*/2 = kN/cm2 > 2228 kN/cm OK. Uniform Core Wall Thickness t = 500 mm Plate dimensions m * 1.06 m

111 Top Chord Connection to Core
Check of Anchor Bolts at tension Ptmax = kN 42 M36 (8.8)

112 Top Chord Connection to Truss
Check of Anchor Bolts (M36 – 8.8) Pr = 0.75 * 075 * 8 * * 42 = 1922 t > Pd = 1240 t

113 Vertical Shear Force will be transferred by bolts
Equivalent Vertical Force : Pver= 5650kN

114 Vertical Shear Force will be transferred by bolts
1 bolt shear strength (8.8) M36 Vrs = 0.75*0.45*Fu = 80 * 0.45 * = kN n = 5650 / 275 = 21 bolts for connection 42 M36 Vr = kN > 5650 kN

115 Out of Plane Bending Moments of Core Wall at Transfer Truss Surface
M22 ( Vertical direction ) -250 kN.m 350 kN m

116 Out of Plane Bending Moments at Core Wall at Transfer Truss Surface
SECTION/ СЕЧЕНИЯ b h h' M am e z As Арматура A Asmin 1 2 (mm) ( kN.m ) (mm2) 1000 700 50 250.0 0.039 0.980 902.0 Ø 16 / 200 + > 901.97 320.0 0.050 0.051 0.975 1161.2 20 150 Additionally φ20/200 reinforcement will be added vertically to resist the out of plane moment at core wall.

117 Out of Plane Bending Moments of Core Wall at Transfer Truss Surface
M11 ( Horizontal direction ) -300 kN.m 600 kN m

118 Out of Plane Bending Moments at Core Wall at Transfer Truss Surface
SECTION/ СЕЧЕНИЯ b h h' M am e z As Арматура A Asmin 1 2 (mm) ( kN.m ) (mm2) 1000 700 50 300.0 0.046 0.048 0.976 1086.8 Ø 20 / 200 + > 600.0 0.093 0.098 0.951 2230.9 25 150 Additionally φ20/200 outer surface reinforcement will be added horizontally to resist the out of plane moment at core wall. Additionally φ25/200 inner surface reinforcement will be added horizontally to resist the out of plane moment at core wall.

119 TYPICAL DETAILS FOR TRANSFER TRUSS & CORE CONNECTION
4th & 5th Cube

120 TYPICAL DETAILS FOR TRANSFER TRUSS & CORE CONNECTION
Lower 3 Cubes

121 TYPICAL DETAILS FOR TRANSFER TRUSS & CORE CONNECTION
Lower 3 Cubes

122 TYPICAL DETAILS FOR TRANSFER TRUSS & CORE CONNECTION
Lower 3 Cubes

123 TYPICAL DETAILS FOR TRANSFER TRUSS & CORE CONNECTION
Lower 3 Cubes


Download ppt "Preliminary Design & Steel Deck Alternative Presentation"

Similar presentations


Ads by Google