Presentation is loading. Please wait.

Presentation is loading. Please wait.

Point of Connection Methodology for Sharing of Transmission Charges.

Similar presentations


Presentation on theme: "Point of Connection Methodology for Sharing of Transmission Charges."— Presentation transcript:

1 Point of Connection Methodology for Sharing of Transmission Charges

2 Methodology adopted for Sharing of ISTS Charges Hybrid Method ----A combination of Tracing and Marginal Participation methods

3 Tracing of Electricity Based on a paper published by Bialek in 1996 Requires base case load flow Uses concept of proportional flows Attempts to identify which generators are supplying which loads

4 Marginal Participation --- changes in line flows due to incremental 1 MW change in generation/load at a node is used to determine the participation of the node on the lines

5 The Procedure Solve Base case LF on basic network….truncated to 400 kv Identification of responding buses-tracing Increment 1 MW Marginal generation/Load at desired bus absorbed/generated by responding buses Calculate line utilization factors Allocate costs to nodes Calculate poc rate/nodal prices

6 The LF studies have been done using Power World Simulator evaluation/student edition

7 P out Records: One MW Marginal drawal at Bus 2, Supplied by Generator at Bus 5 Bus Flows BUS 1 1 400.0 MW GENERATOR 180.00 TO 2 2 1 193.07 0 0.0 TO 3 3 1 60.21 0 0.0 TO 5 5 1 -73.28 0 0.0 BUS 2 2 400.0 MW LOAD 1 261.00 TO 1 1 1 -193.07 0 0.0 TO 4 4 1 -67.93 0 0.0 BUS 3 3 400.0 MW LOAD 1 220.00 TO 1 1 1 -60.21 0 0.0 TO 5 5 1 -159.79 0 0.0 BUS 4 4 400.0 MW LOAD 1 100.00 TO 2 2 1 67.93 0 0.0 TO 5 5 1 -167.93 0 0.0 BUS 5 5 400.0 MW GENERATOR 401.00 TO 1 1 1 73.28 0 0.0 TO 3 3 1 159.79 0 0.0 TO 4 4 1 167.93 0 0.0 Pout Records Base Case Bus Flows BUS 1 1 400.0 MW GENERATOR 180.00 0.0 TO 2 2 1 192.62 0 0.0 TO 3 3 1 60.38 0 0.0 TO 5 5 1 -73.00 0 0.0 BUS 2 2 400.0 MW LOAD 1 260.00 TO 1 1 1 -192.62 0 0.0 TO 4 4 1 -67.38 0 0.0 BUS 3 3 400.0 MW LOAD 1 220.00 TO 1 1 1 -60.38 0 0.0 TO 5 5 1 -159.62 0 0.0 BUS 4 4 400.0 MW LOAD 1 100.00 TO 2 2 1 67.38 0 0.0 TO 5 5 1 -167.38 0 0.0 BUS 5 5 400.0 MW GENERATOR 400.00 0.0 TO 1 1 1 73.00 0 0.0 TO 3 3 1 159.62 0 0.0 TO 4 4 1 167.38 0 0.0

8 60.38 MW 73 MW 192.62 MW Contribution of 180 MW generator on line 4= 60.38*180/(180+73)= 42.96 MW

9 For a large system -----......... It requires the solution of the [A] matrices.

10 P1=253 P2=260 P3=220 P4=167.38 P5=400 1-2=192.62 1-3=60.38 4-2=67.38 5-4=167.38 5-3=159.62 5-1=73.00 Pi = nodal power at node i = sum of injections = sum of withdrawals

11 From “The Tracing of Electricity” J.Bialek, 1996 Contribution of Generator k in line outflow in line i-l emanating from node i= |P i-l |*[A u -1 ] ik *P Gk /P i [A u ] ij = 1 if i=j -|P j-i |/P j if j belongs to set of nodes directly supplying to node i 0otherwise

12 Au Matrix Au Au Inv 1.000000-0.1831.0000000.183 -0.7591.0000-0.40300.7591.00000.4030.307 -0.23901.0000-0.3990.23901.00000.443 0001.000-0.418000.0001.0000.418 00001.0000000

13 From “The Tracing of Electricity” J.Bialek, 1996 Contribution of Generator k to Load at node i= P Li *[A u -1 ] ik *P Gk /P i

14 From “The Tracing of Electricity” J.Bialek, 1996 Contribution of Load k in line inflow in line i-j into node i= |P i-l |*[A d -1 ] ik *P Lk /P i [A d ] ij = 1 if i=j -|P j-i |/P j if j belongs to set of nodes directly supplied from node i 0otherwise

15 Ad matrix Ad Ad Inv 1.000-0.741-0.2740.000 1.0000.7410.2740.000 01.0000.000 1.0000.000 001.0000.000 1.0000.000 0-0.2590.0001.0000.000 0.2590.0001.0000.000 -0.2890.000-0.7261.0000.2890.4730.8051.000

16 Line1(1-2)Line2(4-2)Line3(5-1)Line4(1-3)Line5(5-3) Line6(5-4) Generator 1 (MW) 137.040042.9600 %7100 00 Generator 2(MW) 55.58677317.42159.62167.38 %29100 29100 Total192.62677360.38159.62167.38

17 Load line contribution Line1(1- 2)Line2(4-2)Line3(5-1)Line4(1-3)Line5(5-3)Line6(5-4) Load (bus2) 192.667.3855.590067.38 % 100 760040 Load (bus 3) 0017.4160.38159.620 % 0024100 0 load (bus 4) 00000100 % 0000060 192.667.387360.38159.62167.38

18 Load (bus 2) Load (bus 3) Load (bus 4) Gen 1(bus1) 136.6243.020 %53200 Gen 2(bus5) 123.38176.98100 %4780100 Total260220100

19 Increase 1 MW load at Bus 2 ……… and as per result of tracing Generator 1 will respond with 53% that is 0.53 MW and Generator 2 will respond with 47% that is 0.47 MW

20

21 Calculation of Seasonal Index & Marginal Participation Factors

22 Seasonal index (for node i line l): U e,i,l =(|F le i | - |F le |).P ie |F le i | - |F le | must be >0

23 Pout Records: Marginal 1 MW INCR at Bus 2 Bus Flows BUS 1 1 400.0 MW GENERATOR 180.53 0.0 TO 2 2 1 193.33 0 0.0 TO 3 3 1 60.31 0 0.0 TO 5 5 1 -73.11 0 0.0 BUS 2 2 400.0 MW LOAD 1 261.00 TO 1 1 1 -193.33 0 0.0 TO 4 4 1 -67.67 0 0.0 BUS 3 3 400.0 MW LOAD 1 220.00 TO 1 1 1 -60.31 0 0.0 TO 5 5 1 -159.69 0 0.0 BUS 4 4 400.0 MW LOAD 1 100.00 TO 2 2 1 67.67 0 0.0 TO 5 5 1 -167.67 0 0.0 BUS 5 5 400.0 MW GENERATOR 400.47 0.0 TO 1 1 1 73.11 0 0.0 TO 3 3 1 159.69 0 0.0 TO 4 4 1 167.67 0 0.0 Pout Records Base Case Bus Flows BUS 1 1 400.0 MW GENERATOR 180.00 0.0 TO 2 2 1 192.62 0 0.0 TO 3 3 1 60.38 0 0.0 TO 5 5 1 -73.00 0 0.0 BUS 2 2 400.0 MW LOAD 1 260.00 TO 1 1 1 -192.62 0 0.0 TO 4 4 1 -67.38 0 0.0 BUS 3 3 400.0 MW LOAD 1 220.00 TO 1 1 1 -60.38 0 0.0 TO 5 5 1 -159.62 0 0.0 BUS 4 4 400.0 MW LOAD 1 100.00 TO 2 2 1 67.38 0 0.0 TO 5 5 1 -167.38 0 0.0 BUS 5 5 400.0 MW GENERATOR 400.00 0.0 TO 1 1 1 73.00 0 0.0 TO 3 3 1 159.62 0 0.0 TO 4 4 1 167.38 0 0.0

24 LineMarginal case Base case Ue2l 1-2193.33192.62184.6Ue2(1-2) 1-360.3160.380Ue2(1-3) 5-173.1173.0028.6Ue2(5-1) 4-267.6767.3875.4Ue2(4-2) 5-3159.69159.6218.2Ue2(5-3) 5-4167.67167.3875.4Ue2(5-4) Seasonal Index for node 2 Seaslonal index for node 2 on line [1-2] = (193.33-192.62)*260

25 Increase 1 MW load at Bus 1

26 Pout Records Bus 1 INCR 1 MW Bus Flows BUS 1 1 400.0 MW GENERATOR 181.00 0.0 TO 2 2 1 193.39 0 0.0 TO 3 3 1 60.54 0 0.0 TO 5 5 1 -72.93 0 0.0 BUS 2 2 400.0 MW LOAD 1 260.76 TO 1 1 1 -193.39 0 0.0 TO 4 4 1 -67.37 0 0.0 BUS 3 3 400.0 MW LOAD 1 220.24 TO 1 1 1 -60.54 0 0.0 TO 5 5 1 -159.70 0 0.0 BUS 4 4 400.0 MW LOAD 1 100.00 TO 2 2 1 67.37 0 0.0 TO 5 5 1 -167.37 0 0.0 BUS 5 5 400.0 MW GENERATOR 400.00 0.0 TO 1 1 1 72.93 0 0.0 TO 3 3 1 159.70 0 0.0 TO 4 4 1 167.37 0 0.0 Pout Records Base Case Bus Flows BUS 1 1 400.0 MW GENERATOR 180.00 0.0 TO 2 2 1 192.62 0 0.0 TO 3 3 1 60.38 0 0.0 TO 5 5 1 -73.00 0 0.0 BUS 2 2 400.0 MW LOAD 1 260.00 TO 1 1 1 -192.62 0 0.0 TO 4 4 1 -67.38 0 0.0 BUS 3 3 400.0 MW LOAD 1 220.00 TO 1 1 1 -60.38 0 0.0 TO 5 5 1 -159.62 0 0.0 BUS 4 4 400.0 MW LOAD 1 100.00 TO 2 2 1 67.38 0 0.0 TO 5 5 1 -167.38 0 0.0 BUS 5 5 400.0 MW GENERATOR 400.00 0.0 TO 1 1 1 73.00 0 0.0 TO 3 3 1 159.62 0 0.0 TO 4 4 1 167.38 0 0.0

27 LineMarginal case Base case Ue1l 1-2193.39192.62138.6Ue1(1-2) 1-360.5460.3828.8Ue1(1-3) 5-172.9373.000Ue1(5-1) 4-267.3767.380Ue1(4-2) 5-3159.70159.6214.4Ue1(5-3) 5-4167.37167.380Ue1(5-4) Seasonal Index for node 1

28 Increase 1 MW load at Bus 3

29 Pout Records: 1MW INCR in bus 3 (load) Bus Flows BUS 1 1 400.0 MW GENERATOR 1 180.20 0.0 TO 2 2 1 192.48 0 0.0 TO 3 3 1 60.81 0 0.0 TO 5 5 1 -73.09 0 0.0 BUS 2 2 400.0 MW LOAD 1 260.00 TO 1 1 1 -192.48 0 0.0 TO 4 4 1 -67.52 0 0.0 BUS 3 3 400.0 MW LOAD 1 221.00 TO 1 1 1 -60.81 0 0.0 TO 5 5 1 -160.19 0 0.0 BUS 4 4 400.0 MW LOAD 1 100.00 TO 2 2 1 67.52 0 0.0 TO 5 5 1 -167.52 0 0.0 BUS 5 5 400.0 MW GENERATOR 400.80 0.0 TO 1 1 1 73.09 0 0.0 TO 3 3 1 160.19 0 0.0 TO 4 4 1 167.52 0 0.0 Pout Records Base Case Bus Flows BUS 1 1 400.0 MW GENERATOR 180.00 0.0 TO 2 2 1 192.62 0 0.0 TO 3 3 1 60.38 0 0.0 TO 5 5 1 -73.00 0 0.0 BUS 2 2 400.0 MW LOAD 1 260.00 TO 1 1 1 -192.62 0 0.0 TO 4 4 1 -67.38 0 0.0 BUS 3 3 400.0 MW LOAD 1 220.00 TO 1 1 1 -60.38 0 0.0 TO 5 5 1 -159.62 0 0.0 BUS 4 4 400.0 MW LOAD 1 100.00 TO 2 2 1 67.38 0 0.0 TO 5 5 1 -167.38 0 0.0 BUS 5 5 400.0 MW GENERATOR 400.00 0.0 TO 1 1 1 73.00 0 0.0 TO 3 3 1 159.62 0 0.0 TO 4 4 1 167.38 0 0.0

30 LineMarginal case Base case Ue3l 1-2192.48192.620Ue3(1-2) 1-360.8160.3894.6Ue3(1-3) 5-173.0973.0019.8Ue3(5-1) 4-267.5267.3830.8Ue3(4-2) 5-3160.19159.62125.4Ue3(5-3) 5-4167.52167.3830.8Ue3(5-4) Seasonal Index for node 3

31 Increase 1 MW load at Bus 4

32 Pout Records Base Case Bus Flows BUS 1 1 400.0 MW GENERATOR 180.00 0.0 TO 2 2 1 192.62 0 0.0 TO 3 3 1 60.38 0 0.0 TO 5 5 1 -73.00 0 0.0 BUS 2 2 400.0 MW LOAD 1 260.00 TO 1 1 1 -192.62 0 0.0 TO 4 4 1 -67.38 0 0.0 BUS 3 3 400.0 MW LOAD 1 220.00 TO 1 1 1 -60.38 0 0.0 TO 5 5 1 -159.62 0 0.0 BUS 4 4 400.0 MW LOAD 1 100.00 TO 2 2 1 67.38 0 0.0 TO 5 5 1 -167.38 0 0.0 BUS 5 5 400.0 MW GENERATOR 400.00 0.0 TO 1 1 1 73.00 0 0.0 TO 3 3 1 159.62 0 0.0 TO 4 4 1 167.38 0 0.0 Pout Records: 1MW INCR Bus 4 Bus Flows BUS 1 1 400.0 MW GENERATOR 1 180.00 0.0 TO 2 2 1 193.01 0 0.0 TO 3 3 1 60.23 0 0.0 TO 5 5 1 -73.24 0 0.0 BUS 2 2 400.0 MW LOAD 1 260.00 TO 1 1 1 -193.01 0 0.0 TO 4 4 1 -66.99 0 0.0 BUS 3 3 400.0 MW LOAD 1 220.00 TO 1 1 1 -60.23 0 0.0 TO 5 5 1 -159.77 0 0.0 BUS 4 4 400.0 MW LOAD 1 101.00 TO 2 2 1 66.99 0 0.0 TO 5 5 1 -167.99 0 0.0 BUS 5 5 400.0 MW GENERATOR 1 401.00 0.0 TO 1 1 1 73.24 0 0.0 TO 3 3 1 159.77 0 0.0 TO 4 4 1 167.99 0 0.0

33 LineMarginal case Base case Ue4l 1-2193.01192.6239Ue4(1-2) 1-360.2360.380Ue4(1-3) 5-173.2473.0024Ue4(5-1) 4-266.9967.380Ue4(4-2) 5-3159.77159.6215Ue4(5-3) 5-4167.99167.3861Ue4(5-4) Seasonal Index for node 4

34 Increase 1 MW load at Bus 5

35 Pout Records: bus 5 INCR 1MW Bus Flows BUS 1 1 400.0 MW GENERATOR 180.00 0.0 TO 2 2 1 192.75 0 0.0 TO 3 3 1 60.46 0 0.0 TO 5 5 1 -73.22 0 0.0 BUS 2 2 400.0 MW LOAD 1 260.31 TO 1 1 1 -192.75 0 0.0 TO 4 4 1 -67.56 0 0.0 BUS 3 3 400.0 MW LOAD 1 220.44 TO 1 1 1 -60.46 0 0.0 TO 5 5 1 -159.98 0 0.0 BUS 4 4 400.0 MW 1 LOAD 1 100.25 TO 2 2 1 67.56 0 0.0 TO 5 5 1 -167.81 0 0.0 BUS 5 5 400.0 MW 1 GENERATOR 401.00 0.0 TO 1 1 1 73.22 0 0.0 TO 3 3 1 159.98 0 0.0 TO 4 4 1 167.81 0 0.0 Pout Records Base Case Bus Flows BUS 1 1 400.0 MW GENERATOR 180.00 0.0 TO 2 2 1 192.62 0 0.0 TO 3 3 1 60.38 0 0.0 TO 5 5 1 -73.00 0 0.0 BUS 2 2 400.0 MW LOAD 1 260.00 TO 1 1 1 -192.62 0 0.0 TO 4 4 1 -67.38 0 0.0 BUS 3 3 400.0 MW LOAD 1 220.00 TO 1 1 1 -60.38 0 0.0 TO 5 5 1 -159.62 0 0.0 BUS 4 4 400.0 MW LOAD 1 100.00 TO 2 2 1 67.38 0 0.0 TO 5 5 1 -167.38 0 0.0 BUS 5 5 400.0 MW GENERATOR 400.00 0.0 TO 1 1 1 73.00 0 0.0 TO 3 3 1 159.62 0 0.0 TO 4 4 1 167.38 0 0.0

36 LineMarginal case Base case Ue4l 1-2192.75192.6252Ue5(1-2) 1-360.4660.3832Ue5(1-3) 5-173.2273.0088Ue5(5-1) 4-267.5667.3872Ue5(4-2) 5-3159.98159.62144Ue5(5-3) 5-4167.81167.38172Ue5(5-4) Seasonal Index for node 5

37 Marginal Participation Factor( of node i in line l): U eil / ∑ i U eil

38 Node/b us 1 Bus 2Bus 3Bus 4Bus 5 Line 1-2 0.33460.44570.09410.1255 1-30.185300.608800.2059 1-500.17830.12340.14960.5486 2-400.42310.172800.4040 3-50.04540.05740.39560.04730.4543 4-500.22230.09080.17980.5071

39 Zone A

40 Line Cost Information Linefrom busto buslength in KMCost of line (in Crs) 112160 224112 315200 41380 535152 64599 Total=803 Cr Line cost considered as 1 crore/km for indicative purposes only

41 Calculation of Uniform Charges = Total Transmission Charges/(Sum of approved Injection+Sum of approved Withdrawal) =803/(400+180+220+260+100) =69.22 lakhs/MW For bus 1 =(69.22*180)=125 Cr For bus 2=(69.22*260) =180 Cr For bus 3=(69.22*220) =152 Cr For bus 4=(69.22*100) = 69 Cr For bus 5=(69.22*400) =277 Cr

42 Cost allocation to nodes based on marginal participation NodesMarginal Participation case (Cost in Rs Cr) Uniform Charges (Cost in Rs Cr) 50 % Marginal Participation 50% Uniform Charges PoC rates Rs Lakh /MW/mont h Node/Bus 1 751251004.62 Node/Bus 2 185180182.55.85 Node/Bus 3 1621521575.95 Node/Bus 4 706969.55.79 Node/Bus 5 3112772946.13 Total803

43 Generator shares Generator Loads Generator Node 1 % share Generator Node 5 % share Load bus 21050 Load bus 330 Load bus 46020

44 Node s MP- Trace UC50 % MP & 50% UC PoC rates Rs Lakh /MW /month Monthly Charges to be paid Rs Lakhs/mont h based on share Monthly Charges to be paid Rs Lakhs/month based on trace Node/ Bus 1 751251004.62 (3.47) Generator node Node/ Bus 2 185180182.55.85 (5.93) 2830 2905 Node/ Bus 3 1621521575.95 (6.14) 2294 2596 Node/ Bus 4 706969.55.79 (5.83) 1568 1192 Node/ Bus 5 3112772946.13 (6.48) Generator node Total803 Charges to be paid = own drawal*drawal PoC of node+share*generator capacity*injection PoC of generator bus (Figures in brackets are based on MP-Trace only)

45 Present Issues

46 There is no internationally adopted best common method for allocation of transmission costs….. All methods have their pros & cons Worldwide a combination of methods is used for allocation such as postage stamp, marginal/nodal pricing, marginal participation, average participation, MW- Mile, peak based, game theory etc Requires not only technical expertise but also Econimics concepts such as marginal price, social welfare, etc

47 While postage stamp method is the most easiest to understand, it does not capture the congestion costs. While marginal participation has some degree of technical backing it is complex to understand and implement Selection of slack bus/responding nodes in marginal participation is a contentious issue.

48 While we are rightly concerned with congestion. What if there is over capacity/stranded assets in a corridor? What if the constructed lines remain lightly loaded for most part of the year due to error in planning or change in load generation scenario over time? What is the limit of reliability costs?

49 In Flow based methods the base case load generation is very important….. More so when the tariff of assets vary widely 50 % Uniform charges distort the locational signals Slabbing further distorts the results of marginal participation

50 Whether a generator/supplier or Load/Consumer is to be penalized for its geographical location? -----generation zones are predetermined based on availability of resources ----load zones/industrial belts are also result of historical development, resource availability Whether generator or Consumer be penalized due to asymmetries in transmission network created during historical development of ISTS ?

51 Future Concerns Integration of Renewables in the Grid ---run of the river hydro, wind and solar run on very low PLF. However, transmission must be developed for entire capacity. ---higher transmission cost/unit due to low PLF which is not under the control of generator may result in disincentive for growth of renewables

52 The issue of integration of renewables is being debated worldwide now Can such transmission projects be funded by Government under NAPCC?

53 Changes in Sharing Regulations contemplated in the third amendment regulations

54 Transmission charges to be calculated based on peak scenario rather than average scenario ---In selecting those operating scenarios it is important to recognise that the operating conditions that impose most stress on particular network elements may occur at times other than for system peak demand.

55 Discontinuation of uniform charges Discontinuation of slabbing Computation based on full basic network rather than truncated network Proportional compensation for use of state lines carrying interstate power

56 PoC charges under peak conditions

57

58 Pout Records: NEW BASE CASE::150% peak drawal at node/bus-2---supplied by generator node 5 Bus Flows BUS 1 1 400.0 MW GENERATOR 180.00 0.0 TO 2 2 1 251.79 0 0.0 TO 3 3 1 37.27 0 0.0 TO 5 5 1 -109.06 0 0.0 BUS 2 2 400.0 MW LOAD 1 390.00 TO 1 1 1 -251.79 0 0.0 TO 4 4 1 -138.21 0 0.0 BUS 3 3 400.0 MW LOAD 1 220.00 TO 1 1 1 -37.27 0 0.0 TO 5 5 1 -182.73 0 0.0 BUS 4 4 400.0 MW LOAD 1 100.00 TO 2 2 1 138.21 0 0.0 TO 5 5 1 -238.21 0 0.0 BUS 5 5 400.0 MW GENERATOR 530.00 0.0 TO 1 1 1 109.06 0 0.0 TO 3 3 1 182.73 0 0.0 TO 4 4 1 238.21 0 0.0

59 Load (bus 2) Load (bus 3) Load (bus 4) Gen 1(bus1) 156.7823.220 %40110 Gen 2(bus5) 232.74197.26100 %6089100 Total390220100

60 Pout Records: NEW BASE CASE::150% peak drawal at node/bus-2 Bus Flows BUS 1 1 400.0 MW GENERATOR 180.00 0.0 TO 2 2 1 251.79 0 0.0 TO 3 3 1 37.27 0 0.0 TO 5 5 1 -109.06 0 0.0 BUS 2 2 400.0 MW LOAD 1 390.00 TO 1 1 1 -251.79 0 0.0 TO 4 4 1 -138.21 0 0.0 BUS 3 3 400.0 MW LOAD 1 220.00 TO 1 1 1 -37.27 0 0.0 TO 5 5 1 -182.73 0 0.0 BUS 4 4 400.0 MW LOAD 1 100.00 TO 2 2 1 138.21 0 0.0 TO 5 5 1 -238.21 0 0.0 BUS 5 5 400.0 MW GENERATOR 530.00 0.0 TO 1 1 1 109.06 0 0.0 TO 3 3 1 182.73 0 0.0 TO 4 4 1 238.21 0 0.0 Pout Records:: INCR 1 MW at bus 1 Bus Flows BUS 1 1 400.0 MW GENERATOR 181.00 0.0 TO 2 2 1 252.64 0 0.0 TO 3 3 1 37.37 0 0.0 TO 5 5 1 -109.01 0 0.0 BUS 2 2 400.0 MW LOAD 1 390.87 TO 1 1 1 -252.64 0 0.0 TO 4 4 1 -138.23 0 0.0 BUS 3 3 400.0 MW LOAD 1 220.13 TO 1 1 1 -37.37 0 0.0 TO 5 5 1 -182.76 0 0.0 BUS 4 4 400.0 MW LOAD 1 100.00 TO 2 2 1 138.23 0 0.0 TO 5 5 1 -238.23 0 0.0 BUS 5 5 400.0 MW GENERATOR 530.00 0.0 TO 1 1 1 109.01 0 0.0 TO 3 3 1 182.76 0 0.0 TO 4 4 1 238.23 0 0.0

61 Pout Records: NEW BASE CASE::150% peak drawal at node/bus-2 Bus Flows BUS 1 1 400.0 MW GENERATOR 180.00 0.0 TO 2 2 1 251.79 0 0.0 TO 3 3 1 37.27 0 0.0 TO 5 5 1 -109.06 0 0.0 BUS 2 2 400.0 MW LOAD 1 390.00 TO 1 1 1 -251.79 0 0.0 TO 4 4 1 -138.21 0 0.0 BUS 3 3 400.0 MW LOAD 1 220.00 TO 1 1 1 -37.27 0 0.0 TO 5 5 1 -182.73 0 0.0 BUS 4 4 400.0 MW LOAD 1 100.00 TO 2 2 1 138.21 0 0.0 TO 5 5 1 -238.21 0 0.0 BUS 5 5 400.0 MW GENERATOR 530.00 0.0 TO 1 1 1 109.06 0 0.0 TO 3 3 1 182.73 0 0.0 TO 4 4 1 238.21 0 0.0 Pout Records:: INCR 1 MW at bus 2 Bus Flows BUS 1 1 400.0 GENERATOR 180.40 0.0 TO 2 2 1 252.44 0 0.0 TO 3 3 1 37.17 0 0.0 TO 5 5 1 -109.21 0 0.0 BUS 2 2 400.0 MW LOAD 1 391.00 TO 1 1 1 -252.44 0 0.0 TO 4 4 1 -138.56 0 0.0 BUS 3 3 400.0 MW LOAD 1 220.00 TO 1 1 1 -37.17 0 0.0 TO 5 5 1 -182.83 0 0.0 BUS 4 4 400.0 MW LOAD 1 100.00 TO 2 2 1 138.56 0 0.0 TO 5 5 1 -238.56 0 0.0 BUS 5 5 400.0 MW GENERATOR 530.60 0.0 TO 1 1 1 109.21 0 0.0 TO 3 3 1 182.83 0 0.0 TO 4 4 1 238.56 0 0.0

62 Pout Records: NEW BASE CASE::150% peak drawal at node/bus-2 Bus Flows BUS 1 1 400.0 MW GENERATOR 180.00 0.0 TO 2 2 1 251.79 0 0.0 TO 3 3 1 37.27 0 0.0 TO 5 5 1 -109.06 0 0.0 BUS 2 2 400.0 MW LOAD 1 390.00 TO 1 1 1 -251.79 0 0.0 TO 4 4 1 -138.21 0 0.0 BUS 3 3 400.0 MW LOAD 1 220.00 TO 1 1 1 -37.27 0 0.0 TO 5 5 1 -182.73 0 0.0 BUS 4 4 400.0 MW LOAD 1 100.00 TO 2 2 1 138.21 0 0.0 TO 5 5 1 -238.21 0 0.0 BUS 5 5 400.0 MW GENERATOR 530.00 0.0 TO 1 1 1 109.06 0 0.0 TO 3 3 1 182.73 0 0.0 TO 4 4 1 238.21 0 0.0 Pout Records:: 1 MW INCR at Bus 3 Bus Flows BUS 1 1 400.0 MW GENERATOR 1 180.11 0.0 TO 2 2 1 251.61 0 0.0 TO 3 3 1 37.68 0 0.0 TO 5 5 1 -109.18 0 0.0 BUS 2 2 400.0 MW LOAD 1 390.00 TO 1 1 1 -251.61 0 0.0 TO 4 4 1 -138.39 0 0.0 BUS 3 3 400.0 MW LOAD 1 221.00 TO 1 1 1 -37.68 0 0.0 TO 5 5 1 -183.32 0 0.0 BUS 4 4 400.0 MW LOAD 1 100.00 TO 2 2 1 138.39 0 0.0 TO 5 5 1 -238.39 0 0.0 BUS 5 5 400.0 MW GENERATOR 1 530.89 0.0 TO 1 1 1 109.18 0 0.0 TO 3 3 1 183.32 0 0.0 TO 4 4 1 238.39 0 0.0

63 Pout Records: NEW BASE CASE::150% peak drawal at node/bus-2 Bus Flows BUS 1 1 400.0 MW GENERATOR 180.00 0.0 TO 2 2 1 251.79 0 0.0 TO 3 3 1 37.27 0 0.0 TO 5 5 1 -109.06 0 0.0 BUS 2 2 400.0 MW LOAD 1 390.00 TO 1 1 1 -251.79 0 0.0 TO 4 4 1 -138.21 0 0.0 BUS 3 3 400.0 MW LOAD 1 220.00 TO 1 1 1 -37.27 0 0.0 TO 5 5 1 -182.73 0 0.0 BUS 4 4 400.0 MW LOAD 1 100.00 TO 2 2 1 138.21 0 0.0 TO 5 5 1 -238.21 0 0.0 BUS 5 5 400.0 MW GENERATOR 530.00 0.0 TO 1 1 1 109.06 0 0.0 TO 3 3 1 182.73 0 0.0 TO 4 4 1 238.21 0 0.0 Pout Records Bus Flows BUS 1 1 400.0 MW GENERATOR 1 180.00 0.0 TO 2 2 1 252.19 0 0.0 TO 3 3 1 37.11 0 0.0 TO 5 5 1 -109.30 0 0.0 BUS 2 2 400.0 MW LOAD 1 390.00 TO 1 1 1 -252.19 0 0.0 TO 4 4 1 -137.81 0 0.0 BUS 3 3 400.0 MW LOAD 1 220.00 TO 1 1 1 -37.11 0 0.0 TO 5 5 1 -182.89 0 0.0 BUS 4 4 400.0 MW LOAD 1 101.00 TO 2 2 1 137.81 0 0.0 TO 5 5 1 -238.81 0 0.0 BUS 5 5 400.0 MW GENERATOR 531.00 0.0 TO 1 1 1 109.30 0 0.0 TO 3 3 1 182.89 0 0.0 TO 4 4 1 238.81 0 0.0

64 Pout Records: NEW BASE CASE::150% peak drawal at node/bus-2 Bus Flows BUS 1 1 400.0 MW GENERATOR 180.00 0.0 TO 2 2 1 251.79 0 0.0 TO 3 3 1 37.27 0 0.0 TO 5 5 1 -109.06 0 0.0 BUS 2 2 400.0 MW LOAD 1 390.00 TO 1 1 1 -251.79 0 0.0 TO 4 4 1 -138.21 0 0.0 BUS 3 3 400.0 MW LOAD 1 220.00 TO 1 1 1 -37.27 0 0.0 TO 5 5 1 -182.73 0 0.0 BUS 4 4 400.0 MW LOAD 1 100.00 TO 2 2 1 138.21 0 0.0 TO 5 5 1 -238.21 0 0.0 BUS 5 5 400.0 MW GENERATOR 530.00 0.0 TO 1 1 1 109.06 0 0.0 TO 3 3 1 182.73 0 0.0 TO 4 4 1 238.21 0 0.0 Pout Records Bus Flows BUS 1 1 400.0 MW GENERATOR 1 180.00 0.0 TO 2 2 1 251.98 0 0.0 TO 3 3 1 37.30 0 0.0 TO 5 5 1 -109.29 0 0.0 BUS 2 2 400.0 MW LOAD 1 390.44 TO 1 1 1 -251.98 0 0.0 TO 4 4 1 -138.46 0 0.0 BUS 3 3 400.0 MW LOAD 1 220.37 TO 1 1 1 -37.30 0 0.0 TO 5 5 1 -183.07 0 0.0 BUS 4 4 400.0 MW LOAD 1 100.19 TO 2 2 1 138.46 0 0.0 TO 5 5 1 -238.65 0 0.0 BUS 5 5 400.0 MW GENERATOR 531.00 0.0 TO 1 1 1 109.29 0 0.0 TO 3 3 1 183.07 0 0.0 TO 4 4 1 238.65 0 0.0

65 Node/b us 1 Bus 2Bus 3Bus 4Bus 5 Line 1-2 0.2800.4630.0000.0730.184 1-3 0.1450.0000.7270.0000.128 1-5 0.0000.2530.1140.1040.528 2-4 0.0120.4370.1270.0000.424 3-5 0.0150.1050.3500.0430.487 4-5 0.0080.2890.0840.1270.493

66 Marginal Line Participation Factors peak case and earlier/average case for line 1--2

67 Total charges allocated to nodes peak case earlier case

68 Tabulated data for earlier case and peak case NodeEarlier cost allocated to node Peak scenario cost % change Earlier cost/ Lakh/MW /month MP Earlier cost/ Lakh/MW/ month MP+UC Peak Scenario cost/ Lakh/MW/mo nth 1756118.663.474.622.82 218521817.835.935.854.66 31621573.086.145.955.94 4705127.145.835.794.25 53113161.616.486.134.97 While the load at bus 2 had increased 1.5 times the total cost allocated to the node has increased only 1.18 times( 1.19 for MP+UC) cost/MW/Month will go down (as MW increased). New entrants/ST customers incentivized Charges allocated to a node will change only if due to it flow in different lines change. Otherwise the charge may remain same under peak scenario also. May also reduce.

69 From CERC sharing of ISTS charges (third amendment) draft

70 TABLE 2 DICWithdrawal/Load PoC Charges Scaled PoC Charges X45,79,42,69750,45,52,461 Y18,96,39,55420,89,41215

71 TABLE 3 ZoneUniform Charges (UC)\(Rs./Month)=Unifo rm Rate*LTA Scaled PoC Charges Rs/Month 50% UC and 50% PoC Rs./Month LTA (MW)Withdrawal Charges (Rs/MW/Month) X 25,22,12,08750,45,52,46137,83,82,2742,6681,41,822 Y 16,44,90,08820,89,41,21518,66,46,8471,7411,07,280 50.46/20.89= 2.42 ; 37.84/18.66 = 2.07

72 TABLE- 4 DIC Drawal (MW) LTA (MW) Slab Rate (Rs/MW/Month) Actual Usage (Rs/ Month) Payment (Rs/ Month)Variation X498926681,09,54445,79,42,69729,22,63,392(-) 36.2% Y141417411,09,54418,96,39,55419,07,16,1040.56% 50.46/20.89= 2.42 ; 37.84/18.66 = 2.07 ; 29.23/19.07 = 1.53 ??

73 TABLE-5 Zone Generation (MW) Load (MW) Generation Charges (Rs.) Load Charges (MW) LTA (Generation) (MW) LTA (Demand) (MW) Generation PoC (Rs./MW/ Month) Load PoC (Rs./MW /Month) (1)(2)(3)(4)(5)(6)(7)(8)(9) Z194 29 29160 16,64,6382,160,51,3862804784594545166

74 TABLE-6 Zone Generation PoC (Rs./MW/ Month) Load PoC (Rs./MW /Month) Generation PoC (Rs./MW/ Month) Load PoC (Rs./MW /Month) Generation PoC (Rs./MW/ Month) Load PoC (Rs./MW/ Month) Generation PoC (Rs./MW/ Month) Load PoC (Rs./M W/Mo nth) Software ComputedLTA Based After 50% Uniform charge and 50% PoC application After Slabs Z8,59474,2295,94545,16650,54772,15479,544

75 TABLE-7 Sl.No.State /DIC% Allocation 1BIHAR42.89% 2JHARKHAND8.13% 3DVC0.31% 4ODISHA31.8% plus temp allocation 5WEST BENGAL9.1% plus temp allocation 6SIKKIM2.4 7TAMIL NADU0.85% 8NER3.22%

76 TABLE-8 Sl.No.State /DIC% as per participation factor 1ODISHA82.97 3DVC12.1 5WEST BENGAL4.93

77 Thank you


Download ppt "Point of Connection Methodology for Sharing of Transmission Charges."

Similar presentations


Ads by Google