Download presentation
Presentation is loading. Please wait.
Published byBarnaby Evans Modified over 9 years ago
1
Secondary beam production facility layout discussions SBLNF meeting 5 th Dec. 2012 M. Calviani, A. Ferrari, R. Losito (EN/STI) H. Vincke (DGS/RP)
2
Outline 2 Update on the conceptual functional layout Neutrino production area Annex services (“morgue”, hot handling area, etc.) Building sizes and requirements Comparison with similar installations in USA/Japan 5th December 2012MC - Updates on SBLNF secondary beam facility layout
3
Updates on the neutrino production area 3 Present solution adopts the “trench/chase” approach: ~20/25 meters long, for an internal size of ~3 meters New proposition: Machine (cooling systems) rooms on the lateral/size to the target area Depends on the size of the trench that can be excavated Impact on costs but reduced pipings Morgue and local shielding storage lateral to the target area Hot handling cell located downstream the target vault Personnel access to the target building from upstream Shielding thickness adapted to radiation levels at 240 kW (MC, link)link Disclaimer: this proposition reflects requirements – it’s not integrated with services groups (CV, EL, etc.)! 5th December 2012MC - Updates on SBLNF secondary beam facility layout
4
Access conditions and H*(10) levels 4 No routine access to the target hall during operation Shielding should be designed to respect an H*(10) of < 15 Sv/h on the target vault during operation at 240 kW Levels outside the building will have to be <0.5 Sv/h (non designated) 5th December 2012MC - Updates on SBLNF secondary beam facility layout Decay pipe: 250 cm thick concrete shielding 5 Sv/h at 10 m from beam axis – DP possibly fenced on the surface Concrete/soil interface at ~30 mSv/h 5 mSv/h would require ~400 cm thick concrete 5 Sv/h level H*(10) (mSv/h) Z averaged middle DP Vertical direction
5
Neutrino production area proposition 5th December 2012MC - Updates on SBLNF secondary beam facility layout5
6
Neutrino production area proposition 65th December 2012MC - Updates on SBLNF secondary beam facility layout Shielding: There are margins to reduce the H*(10) on the vault floor by adding concrete blocks Chase size matched with a 3 m diameter DP < 15 Sv/h < 1 mSv/h< 10 mSv/h Present configuration assume: Machine rooms & morgue excavated lateral to chase
7
Possible configuration of the “morgue” 7 Two possibilities could be envisaged for the radioactive material disposal area Ground level lateral from the main target vault Less underground works Need significant shielding + complex transport? Located in a separate trench lateral to the target chase Easier shielding in case of very hot objects (objects could reach ~Sv/h) Can be used also to temporary store shielding blocks More complex CE works to excavate the trench Could be used to prepare the shielded transport cask Size will depend on assumptions on hot objects exchange rates & transport requirements – temporary storage? 5th December 2012MC - Updates on SBLNF secondary beam facility layout
8
Neutrino production area 5th December 2012MC - Updates on SBLNF secondary beam facility layout8
9
Hot handling work cell possible configuration 9 Potential use of a “radioactive working cell”: Horn mechanical connection to the shielding module, remote strip line clamp, waterline connection to horn, electrical connection to horn, target inspection 5th December 2012MC - Updates on SBLNF secondary beam facility layout Location? On the target vault floor, downstream the chase shielding Easier manipulation and access Concrete enclosure, w/ internal cameras for local inspection No lead glass window Front side
10
He-vessel conceptual 10 He-vessel enclosure, 1 atm He-gas: Pros: Reduce pion absorption Suppress 3 H by ~25% wrt air Suppress NO x production and corrosion (factor of ~100x) Suppress 7 Be, 41 Ar, 32 P, etc. sure benefits for global releases See H. Vincke, linklink Cons: Quite complicated to build – huge He volume to handle – need to guarantee leak tightness for feedthroughs Expensive solution Target station & decay volume – unique volume No beam window required between TS and DP 5th December 2012MC - Updates on SBLNF secondary beam facility layout
11
He-vessel conceptual 11 Configuration: Thick steel layer – ~20 m (L), 3 m (W), 8 m (H) Evacuation of the He-vessel required to remove air and avoid condensation (i.e. corrosion) during operation Cooling channels might be needed to cool down the vessel (~20/30 kW deposited) Air/water cooled? Is a shutter separating the TS from the DP during access required? In order to recuperate He during evacuation, need of external compartments Total volume ~1100 m 3 (480 TS + 620 DP) It’s urgent to study the viability of this option vs. an open air circulation system 5th December 2012MC - Updates on SBLNF secondary beam facility layout
12
What needs to be cooled in the chase? 12 Target – possibly an He cooling system Horn/reflector – water cooling He-vessel circulation (*) – He cooling system He-vessel plates (*) – water (or air?) cooling DP collimator (?) – water cooling Hadron Absorber – water cooling Upstream collimator/baffle – cooling not needed? 5th December 2012MC - Updates on SBLNF secondary beam facility layout (*) with an open air atmosphere these would be probably exchanged for a forced air cooling loop
13
Decay pipe 13 3 or 3.5 m Ø ~90 meters long volume (~110 m from target) Shape cylindrical or parallelepiped (a-la-T2K) What’s the level of the moraine/molasse interface? 1974 bore: close to TCC2, waterbed in moraine at 20 m below ground level (431 m) Molasse ~429 m (22 m from surface) 5th December 2012MC - Updates on SBLNF secondary beam facility layout Courtesy: J. Osborne
14
DP - geomembrane DP: high level of prompt dose rate over a large distance risks of soil and water activation Geosynthetic barrier system: protect the surrounding groundwater from any possible tritiated water escaping the decay region 5th December 2012MC - Updates on SBLNF secondary beam facility layout14 Separate barriers (LBNE approach): Geomembrane Geosynthetic clay liner barrier Geonet leak detection layer http://lbne2- docdb.fnal.gov:8080/0046/004623/006/C DR_Vol_5_MI-10CF_20120313.pdf
15
Hadron absorber area 155th December 2012MC - Updates on SBLNF secondary beam facility layout
16
Hadron absorber area 165th December 2012MC - Updates on SBLNF secondary beam facility layout Pit1/HS Absorber cooling mandatory – cooling station will be certainly quite hot (~50 kW power to dissipate) Access limited for maintenance Pit1 access requires local bunker due to material activation Crane required Pit2: Could potentially be even a barrack – no RP issues foreseen (H. Vincke, link)link No fixed crane required Pit1/HSPit2
17
FNAL NuMI configuration NuMI target station deep underground (beam level ~50 meters below ground); target hall is ~40 meters deep Facility adapted to handle 400 kW beam power Surface target service building to access the deeper vault 5th December 2012MC - Updates on SBLNF secondary beam facility layout17 Target hall = 53 m length, ~8 m wide
18
FNAL NuMI configuration 185th December 2012MC - Updates on SBLNF secondary beam facility layout
19
JPARC/T2K configuration JPARC has a surface target vault, with a beam axis located ~20 meters below ground level Facility adapted to handle 750 kW (1.6 MW) beam power Several annex buildings are located on the surface 5th December 2012MC - Updates on SBLNF secondary beam facility layout19
20
JPARC/T2K configuration 205th December 2012MC - Updates on SBLNF secondary beam facility layout
21
Conclusions 21 Updated secondary beam line functional specifications Location of the morgue to be confirmed in collaboration with DGS/RP Cooling station/hot service rooms location to be confirmed/discussed with DGS/RP and GS/SE, as the target vault/chase size depends on this as well He-vessel certainly an advantage, but costs and technical complexity worth? 5th December 2012MC - Updates on SBLNF secondary beam facility layout
Similar presentations
© 2024 SlidePlayer.com. Inc.
All rights reserved.