Lecture Objectives: Finish with common HVAC system configurations
Discuss control systems Discuss the life cycle cost analysis Learn about empirical modeling
4
HVAC systems in eQUEST
5
Basic purpose of HVAC control
Daily, weekly, and seasonal swings make HVAC control challenging Highly unsteady-state environment Provide balance of reasonable comfort at minimum cost and energy Two distinct actions: 1) Switching/Enabling: Manage availability of plant according to schedule using timers. 2) Regulation: Match plant capacity to demand
6
Basic Control loop Example: Heat exchanger control
Modulating (Analog) control air water Cooling coil x (set point temperature)
7
Cooling coil control valve
Electric (pneumatic) motor Position (x) fluid Volume flow rate Vfluid = f(x) linear or exponential function
8
The control in HVAC system – only PI
Proportional Integral value Set point Proportional affect the slope Set point Integral affect the shape after the first “bump”
9
Detail control system simulation
MatLAB - Simulink Control system simulation - take into account HVAC component behavior but focus more on control devices and stability of control scheme
10
Models integrated in HVAC System simulation
Example: Economizer (fresh air volume flow rate control) Controlled device is damper - Damper for the air - Valve for the liquids fresh air damper mixing recirc. air T & RH sensors
11
HVAC Control Economizer (fresh air volume flow rate control)
Controlled device is damper - Damper for the air - Valve for the liquids fresh air damper mixing recirc. air % fresh air T & RH sensors 100% Minimum for ventilation
12
Economizer – cooling regime
How to control the fresh air volume flow rate? If TOA < Tset-point → Supply more fresh air than the minimum required The question is how much? Open the damper for the fresh air and compare the Troom with the Tset-point . Open till you get the Troom = Tset-point If you have 100% fresh air and your still need cooling use cooling coil. What are the priorities: - Control the dampers and then the cooling coils or - Control the valves of cooling coil and then the dampers ? Defend by SEQUENCE OF OERATION the set of operation which HVAC designer provides to the automatic control engineer % fresh air 100% Minimum for ventilation
13
Economizer – cooling regime
Example of SEQUENCE OF OERATIONS: If TOA < Tset-point open the fresh air damper the maximum position Then, if Tindoor air < Tset-point start closing the cooling coil valve If cooling coil valve is closed and T indoor air < Tset-point start closing the damper till you get T indoor air = T set-point Other variations are possible Sequence of calculation in energy simulation modeling is different than sequence of operation ! We often assume perfect aromatic control
14
What are the reasons for energy simulations?
System Development (research) Building design (evaluate different design solutions) Economic benefits Budget planning
15
Life Cycle Cost Analysis
Engineering economics
16
Parameters in life cycle cost analysis
Beside energy benefits expressed in $, you should consider: First cost Maintenance Operation life Change of the energy cost Interest (inflation) Taxes, Discounts, Rebates, other Government measures
17
Example Using eQUEST analyze the benefits (energy saving and pay back period) of installing - low-e double glazed window - variable frequency drive in the school building in NYC
19
What are the reasons for energy simulations?
System Development (research) Building design (evaluate different design solutions) Economic benefits Budget planning
20
For budget planning Empirical model For average year use TMY2