PACS SVR 22/23 June 2006 Test Campaigns1 Overview of PACS Test Campaigns Helmut Feuchtgruber MPE
2
PACS SVR 22/23 June 2006 Test Campaigns2 AVM Warm Electronics Tests AVM WE Tests from Sep-2002 to Jul-2004 Purpose: - OBSW development - Initial warm electronics communication verification - Development of basic instrument operational procedures (switch-on/off, memory load, 1355 link initialization etc.) - Development of EGSE software and operational procedures (memory load, packet recording, bus list switching etc.) Hardware: DPU AVM1, SPU EM, BOLC sim., DMC AVM
3
PACS SVR 22/23 June 2006 Test Campaigns3 CQM ILT Two cryogenic test phases: 19-23 Jul 2004 and 6-Sep to 6-Nov 2004 (EMC: 4/6-Nov 2004) Instrument Hardware: - DPU AVM1, SPU AVM, BOLC AVM, DMC EM, WIH AVM - CQM FPU Instrument OBSW: - DPU V7.10, several updates during the tests until V7.68 - SPU V11.1, short trial of V11.3, but roll back to V11.1 - DMC V5.006, several updates during the tests until V5.023
4
PACS SVR 22/23 June 2006 Test Campaigns4 EQM IMT July/August 2005 3 x Short Functional Tests warm 19-Sep to 4-Nov in 2 periods (with and without He-leak) 7/9-Nov-2005 PACS/SPIRE parallel mode testing 21/25-Nov-2005 EMC Testing 7/9-Dec-2005 Straylight Testing 15-Dec-2005 SFT at ~HeI conditions Hardware: Refurbished DMC EM, otherwise same as during ILT OBSW:DMC OBSW V5.025, SPU V11.7, DPU V7.68
5
PACS SVR 22/23 June 2006 Test Campaigns5 FM Pre-ILT Since 22-Mar-2006 in several time periods Purpose: - Development and testing of CUS-based ILT test procedures and operational procedures - Verification of new DPU Boot SW - Dry-run and validation of IST test procedures - OBSW and MIB testing - SPU HLSW development - Support to PCSS development and testing Hardware: DPU AVM2 & CFM2, DMC EQM, BOLC sim., SPU EM, WIH EQM, FPU simulator (part time) OBSW:DMC V6.000-V6.005, SPU V12.2, DPU V8.31
6
PACS SVR 22/23 June 2006 Test Campaigns6 Future Test Phases (1) ILT without FPU: Continuation of Pre-ILT and integration of PACS FM warm units into test setup as they become available prior to the cold ILT ILT with FPU: SFT warm (before evacuation) Nominal ILT program (incl. SFT HeI, SFT HeII, entire IST test procedure and parallel mode test verification) ILT EMC phase Hardware: FM warm electronics and FM FPU OBSW: Flight versions
7
PACS SVR 22/23 June 2006 Test Campaigns7 Future Test Phases (2) AVM IST Purpose: - Verification of IST test procedures - Test of system related aspects (TBC) Hardware:DPU AVM1 (with new boot software), SPU AVM, BOLC AVM, DMC EM, WIH AVM Software:DPU OBSW V8.xx (TBD during ILT), SPU V12.x (TBD during ILT), DMC V6.xxx (TBD during ILT and due to DMC EM hardware constraints)
8
PACS SVR 22/23 June 2006 Test Campaigns8 Future Test Phases (3) Instrument Delivery FM IST Purpose: - Verify that PACS instrument function and performance is preserved at satellite level, before, during and after environmental testing. This includes TV/TB and EMC tests. SVT 1&2 (content TBD by ESA/MOC) Hardware:FM warm electronics and FM FPU Software:Flight software, evtl. bugs/SPRs detected during ILT corrected