DZero Run IIb Rev Nov 05 ‘03 1 Kotcher Agenda (from Rebaselining Review)  Introduction (Kotcher – 10’)  Trigger & DAQ/Online (Wood – 30’) u AFE II/TriP.

Similar presentations


Presentation on theme: "DZero Run IIb Rev Nov 05 ‘03 1 Kotcher Agenda (from Rebaselining Review)  Introduction (Kotcher – 10’)  Trigger & DAQ/Online (Wood – 30’) u AFE II/TriP."— Presentation transcript:

1 DZero Run IIb Rev Nov 05 ‘03 1 Kotcher Agenda (from Rebaselining Review)  Introduction (Kotcher – 10’)  Trigger & DAQ/Online (Wood – 30’) u AFE II/TriP (Bross – 15’)  BREAK  Silicon Layer 0 (Lipton – 30’)  Baseline Change Proposal, Rebaseline Summary (Kotcher – 30’) Rebaselining Review of the Run IIb DZero Detector Project November 5, 2003 Fermilab Most everything you will see today is in draft form

2 DZero Run IIb Rev Nov 05 ‘03 2 Kotcher AFE II/TriP Upgrade WBS 1.2.8  We are proposing an upgrade to the Central Fiber Tracker (CFT) readout & triggering system u Maintain tracking capability in light of cancellation of silicon upgrade, particularly at increased luminosity s considerably improved noise performance – lower thresholds, enhance triggering, efficiency s z-information from timing u New Analog Front-End Boards (AFE II) and trigger (TriP) chip s First version TriP chip submitted with SVX4 s Designed, tested by Fermilab (PPD, Yarema) s Was major success out of the box s First full AFE II prototype being laid out now, expect back by end CY03 s System represents major simplification, performance upgrade u Exploiting considerable in-house experience – personnel, depth of technical knowledge  TPC = $2.2M (includes 50% total contingency) u M&S cost estimate based on detailed past experience u see talk by Bross

3 DZero Run IIb Rev Nov 05 ‘03 3 Kotcher Run IIb Project Organization Nov ‘03 D0 Run IIb Project J. Kotcher, Project Manager V. O’Dell, Deputy (Trigger/DAQ); R. Lipton, Deputy (Silicon Layer 0) W. Freeman, Associate; M. Johnson, Technical Coordinator D. Knapp, Budget Officer; T. Erickson, Administration WBS 1.2 Trigger P. Padley D. Wood 1.2.3 L1 Track Trigger M. Narain 1.2.1 L1 Cal Upgrade M. Abolins, H. Evans 1.2.4 L2  Upgrade R. Hirosky 1.2.5 Silicon Track Trigger U. Heintz WBS 1.3 DAQ/Online S. Fuess P. Slattery 1.2.2 L1 Cal/Track Match K. Johns 1.2.6 Simulation E. Barberis, M. Hildreth WBS 1.5 Installation R. Smith 1.5.1 Silicon Installation Mechanical: (W. Cooper) Electronics: (L. Bagby) 1.5.2 Trigger Installation D. Edmunds WBS 1.4 Project Administration 1.2.7 Administration (D. Wood) 1.3.3 Control Systems F. Bartlett, G. Savage, V. Sirotenko 1.3.1 Level 3 Systems D. Chapin, G. Watts 1.3.4 DAQ/Online Management (P. Slattery) 1.3.2 Network & Host Systems J. Fitzmaurice, S. Krzywdzinski Installation an integrated part of project plan, but removed from formal Run IIb baselining 1.2.8 AFE II/TriP A. Bross, TBD WBS 1.6 Silicon Layer 0 A. Bean (R. Lipton) 1.6.1 Sensors M. Demarteau, R. McCarthy 1.6.2 Readout Elec A. Nomerotski, R. Sidwell 1.6.3 Mech Des & Fabrication W. Cooper 1.6.4, 1.6.5 Detector Modules & Integ J. Fast, L. Bagby 1.6.6 Administration (A. Bean) Full Run IIb silicon replacement, now cancelled, was WBS 1.1 For initial prototyping phase

4 DZero Run IIb Rev Nov 05 ‘03 4 Kotcher AFE II/TriP Decision Process  Project funding request ($2.2M) includes both salaries and M&S for production only; does not contain either salaries or M&S for R&D u Has been coming from operating funds (e.g., TriP work & testing) u Agreement with Laboratory that this will continue  Before fully supporting the pursuit of this sub- project, we first must convince ourselves that it will provide the experiment with sufficient gains to justify the considerable effort & potential interruptions to data-taking, and that the scheme will work as advertised  Given the time scales (summer ’05 completion), answering these questions must be given sufficient priority during the next few months…and without allowing operations to falter

5 DZero Run IIb Rev Nov 05 ‘03 5 Kotcher AFE II/TriP Decision Process  The following must be completed before production funds will be released: u Continuation/completion of simulations u TriP resubmission s Abder is starting u AFE II prototype layout, fabrication & testing s Arrangements to free John A. up to pursue this for next few months being finalized now s Operations will be covered s Fabrication and testing must immediately follow u DZero Internal Review, followed by a u Laboratory Review, if warranted

6 DZero Run IIb Rev Nov 05 ‘03 6 Kotcher AFE II/TriP Decision Process  The DZero Review will be a critical one  Among the things they will be asked to look over: u Technical gains & feasibility u Physics benefits u Realism of schedule u Long-term commitment of personnel u Credibility of installation and commissioning plan, and its impact on acquisition of physics quality data s A major consideration u Will be asked to provide an overall recommendation, submitted to Spokes, PM  If justification is there, and the DZero Internal Review Committee recommends moving forward, would like to hold the Laboratory Review no later than April ’04  Targeting summer ’05 completion (installation during summer shutdown), which is still tight


Download ppt "DZero Run IIb Rev Nov 05 ‘03 1 Kotcher Agenda (from Rebaselining Review)  Introduction (Kotcher – 10’)  Trigger & DAQ/Online (Wood – 30’) u AFE II/TriP."