Elevating the Quality of Life in the District
2
Agenda SITE VIEW SECTIONS CONSTRUCTION STRATEGY TIMELINE – JUNE 2013 TO JULY 2015 TIMELINE – AUGUST 2015 TO APRIL 2016 TIMELINE – EASTER BREAK 2016 TIMELINE – APRIL 2016 TO JULY 2016 ACCESS & FLOW Foundation to Grade Building Permit Building Permit NEXT STEPS 18 th Nov. to 2 nd Dec. Activities two week look ahead. Construction Images in Courtyard Construction Milestone Frequently Asked Questions. Q & A Elevating the Quality of Life in the District
3
RULES OF THE ROAD RESPECT EACH OTHER CELLPHONES OFF OR ON VIBRATE Q&A WILL BE TAKEN AT THE END OF THE PRESENTATION
4
Elevating the Quality of Life in the District
5
AFTER RENOVATION BEFORE RENOVATION
6
Elevating the Quality of Life in the District AFTER RENOVATION BEFORE RENOVATION
7
Elevating the Quality of Life in the District BEFORE RENOVATION AFTER RENOVATION
8
Elevating the Quality of Life in the District AFTER RENOVATION BEFORE RENOVATION
9
Elevating the Quality of Life in the District BEFORE RENOVATION AFTER RENOVATION
10
Elevating the Quality of Life in the District SECTIONS
11
Elevating the Quality of Life in the District
13
CONSTRUCTION STRATEGY TIMELINE – JUNE 2013 TO JULY 2015
14
Elevating the Quality of Life in the District
15
CONSTRUCTION STRATEGY TIMELINE – AUGUST 2015 TO APRIL 2016
16
Elevating the Quality of Life in the District
17
TIMELINE AUGUST 2015 – APRIL 2016 UNDER CONSTRUCTION EGRESS DURING CONSTRUCTION LOGISTICS AND PHASING PLAN ARE CONTINENT UPON OBTAINING PERMITS AND DOEE APPROVALS PER TURNER’S SCHEDULE
18
Elevating the Quality of Life in the District CONSTRUCTION STRATEGY TIMELINE – EASTER BREAK 2016
19
Elevating the Quality of Life in the District TIMELINE EASTER BREAK 2016 UNDER CONSTRUCTION LOGISTICS AND PHASING PLAN ARE CONTINENT UPON OBTAINING PERMITS AND DOEE APPROVALS PER TURNER’S SCHEDULE
20
Elevating the Quality of Life in the District CONSTRUCTION STRATEGY TIMELINE – APRIL 2016 TO JULY 2016
21
Elevating the Quality of Life in the District
22
TIMELINE APRIL 2016 – JULY 2016 UNDER CONSTRUCTION EGRESS DURING CONSTRUCTION LOGISTICS AND PHASING PLAN ARE CONTINENT UPON OBTAINING PERMITS AND DOEE APPROVALS PER TURNER’S SCHEDULE
23
Elevating the Quality of Life in the District TWO CREPE MYRTLE TREES WILL BE RELOCATED 1 2
24
Excavation & Demo in Courtyard
27
Installation of Foundation System & Elevator Pit in Courtyard
28
Erection of Structural Steel in Cafeteria & Roof of 1956 Building
29
Elevating the Quality of Life in the District TWO CREPE MYRTLE TREES WILL BE RELOCATED 1 2
30
Infiltration System Impact Crepe Myrtle Trees in Images
31
Elevating the Quality of Life in the District CONSTRUCTION MILESTONE COMMENCEMENT OF CONCRETE WORK; OCTOBER COMMENCEMENT OF ELEVATOR SHAFT; NOVEMBER COMMENCEMENT OF COURTYARD STRUCTURAL STEEL; DECEMBER
32
Shepherd ES Logo in Courtyard
33
Frequently Asked Questions 1. Will the asphalt area on the playground be repaired or replaced? Answer:- The asphalt will be repaired. 2. The Mural on the concrete wall will not be impacted by the construction Activities.
34
Elevating the Quality of Life in the District NEXT STEPS TWO WEEK LOOK AHEAD EXCAVATION IN COURTYARD FORMING & INSTALLATION OF FOUNDATION SYSTEM IN COURTYARD ERECTION OF STRUCTURAL STEEL IN THE 1956 BUILDING
35
Kenneth Diggs DGS Associate Director DGS Government Affairs & Communications kenneth.diggs@dc.gov (202) 580-9361 Elevating the Quality of Life in the District