Presentation is loading. Please wait.

Presentation is loading. Please wait.

(THIN CONCRETE PAVEMENTS)

Similar presentations


Presentation on theme: "(THIN CONCRETE PAVEMENTS)"— Presentation transcript:

1 (THIN CONCRETE PAVEMENTS)
WORLD BANK TCP Design (THIN CONCRETE PAVEMENTS) Juan Pablo Covarrubias Washington 2008 1

2 Type of Pavement we are Talking About

3 PERFORMANCE OF CONCRETE PAVEMENTS
The basic performance principles of Concrete Pavements In Chile, the slabs are always curled with the edges lifted up, day and night.

4 DEFORMATION OF A SLAB 15 cm thick, 4 m. long

5 EFFECT OF SUBGRADE STIFFNESS
Armaghani 1993

6 EFFECT OF SUBGRADE STIFFNESS
cantilever Granular CBR 40 CTB Not bonded (polyethylene)

7 EFFECT OF SLAB LENGTH cantilever cantilever 1/4 L 1/3 L cantilever
Length 4,5 m. cantilever = 1,13 m cantilever cantilever 1/4 L 1/3 L Length 1,8 m. Cantilever = 0,45 m

8 EFFECT OF SLAB LENGTH ON SHRINKAGE AND CURLING

9 EFFECT OF SLAB LENGTH ON CURLING
450 cm x350 cm Thickness= 18 cm Delta T°=-14 C° Linear Curling = 2.41 mm 140 cm x175 cm Curling = 0.49 mm

10 SLAB LENGTH AND CURLING
3,8 m 4,5 m Holland 2002

11 EFFECT OF TIE BARS ON CRACKING OF SLABS
Hiller and Springenschmid, 2004

12 Development of the Design by TCPavements
Research at the University of Illinois Generate Design Method. Coordinate tests at international level

13 Loads of Trucks on Slabs
Dx L Dx L Minimum Requirement for TCP design: Maximum slab length less than L Maximum slab width less than Dx (1/2 lane)

14 LOADING OF LONG AND SHORT SLABS

15 Efect of Loads and Slab Geometry on Stresses
Top Mpa Bottom MPa Top Mpa Bottom MPa

16 One Axel at the Edge X

17 LOADS AND STRESSES ON A SLAB WHITH ROCKING

18 RELATION: length - thickness - tensile stress

19 EFFECT OF SLAB LENGTH ON CURLING AND OWN WEIGHT STRESSES
450 cm x350 cm Thickness= 18 cm Delta T°=-14 C° Linear Top Tensile stress= 1.40 MPa 140 cm x175 cm Top Tensile stress= 0.18 MPa

20 Project in Guatemala Slabs 4,5 m x 3,5 m x 24 cm
THICKNESS (cm) 24 SIZE 450x360 Thermal Gradient °C -14 Elastic Modulus (kg/cm2) 290000 K (kg/cm3) 3 Dowels YES Load Position I II III IV Tensions (kg/cm2) 21,9 22,5 19,9 10,6 Position III Position IV Position I Position II

21 Project in Guatemala Slabs 1,8 m x 2,1 m x 15 cm
THICKNESS (cm) 15 SIZE 210x180 Thermal Gradient °C -14 Modulus of Elasticity (kg/cm2) 290000 K (kg/cm3) 3 Load Transfer LTE 50% Load Position I II III Tensions (kg/cm2) 14,5 20,0 22,1 Posición III Posición I Posición II

22 Summary Guatemala Project
Slab Length m. Thickness cm Tension Kg/cm2 Traffic mESALS 4,5 24 22,5 50 1,8 15 22,1 Thin slabs with 30 cm widening

23 FINITE ELEMENTS ANALISIS
Equitensional Curves 25 50 75 100 125 150 175 200 225 250 275 300 325 350 375 400 425 450 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 26 Thickness (cm) Length of slab (cm) 20 Kg/cm2 25 Kg/cm2 30 Kg/cm2 35 Kg/cm2 40 Kg/cm2

24 Thicknesses for Same Stresses and Slab Length
Slab length change from 4,5 to 1,75 m y = 0,5431x + 2,0129 R 2 = 0,9954 4 6 8 10 12 14 16 18 20 5 15 25 30 35 Slabs 4,5 m Slabs 1,75 m cm cm

25 LOAD POSITION AND SLAB SIZE

26 Top and Bottom Stresses for Length and Thickness

27

28 CHARACTERISTICS of TCP Design
Small slabs (1,8 by 2.4 meters) Granular base (fines < 6%) 15 cm thick Impermeable layer between the sub grade and sub base, if needed Thin joint cut (2 mm thick) No joints sealing No dowel bars or tie bars Lateral confinement with curb, shoulder or vertical steel pins Widened outer lane (30 cm)

29 Design Design method being used:
Design with AASHTO with normal slab size (4.5 m long) Determine by finite elements the stresses within the concrete of the slab for the AASHTO design Calculate slab thickness by iteration with ISLAB2000 with the new configuration of slab size and wheel positions (one set of wheels on each slab) to obtain the same stresses than the AASHTO design. The result, by using this new design approach, is a thinner concrete pavement with the same stresses as AASHTO design

30 Construccion Cost TCP H° Tradicional Asfalto EE Diseño Espesor
TCP H° Tradicional Asfalto EE Diseño Espesor Costo Km-Pista H°-TCP % Ahorro Asf-TCP 50,000 8cm $ ,041 - 5cm $ ,808 $ 2,767 4% 100,000 $ ,000 7cm $ ,000 $ 11,000 13% 1,250,000 10cm $ ,715 15cm $ ,400 $ 31,685 28% 9cm $ ,803 $ 20,089 20% 3,000,000 12cm $ ,389 18cm $ ,411 $ 38,022 29% $ ,165 $ 21,776 19% 15,000,000 22cm $ ,000 $ 46,600 13cm $ ,389 $ 23,989 17% 68,000,000 28 cm $ ,782 $ 63,371 32% $ ,889 $ 54,478 160,000,000 22 cm $ ,759 30 cm $ ,456 $ 50,696 24% $ ,885 $ 59,126 27% *Prices from Chile

31 Long Term Costs: 15 20 TCP NPV (%) Asphalt Traditional Concrete
Time (years) 15 20 Asphalt Traditional Concrete TCP

32 Research at U. de Illinois

33 Sub Grade CBR 3%

34 Geotextile and Granular Base

35 Granular Base less 6% Fines

36 Concrete Slabs finished

37 ATLAS Machine

38 ATLAS Machine

39 Experiences

40 Constructed Projects

41 Guatemala BM3 Acceso CA9 Sur (Puente Villalobos) Description
Start Year: end 2005 Length: 1.68km Esals 15 years design Ciudad de Guatemala, Guatemala Highway Pavement structure 21 cm thick Granular base and asphalt base 14.40m to 21.60m Witdh

42

43

44

45 Guatemala Ruta CA-01 Occidente Ciudad San Cristobal - San Lucas (Road to Antigua) Description Year 2006 Length: 11.07km Esals Ciudad de Guatemala – Sacatepéquez, Guatemala Highway Pavement Structure 17cm thick Granular base and asphalt base 14.40m Witdh

46

47

48

49

50 Configuration of Sugar Cane Vehícle (VCMEM)

51 Tensions with Sugar Cane Vehicle (VCMEM)
THICKNESS (cm) 18 Slab size 180x210 Thermal Gradient °C -21 -14 Position of Load I II III IV Tensions (kg/cm2) - K = 3 kg/cm3 25,1 25,4 21,9 21,7 24,4 24,7 21,3 21 23,1 23,4 20,1 19,8 Tensions (kg/cm2) - K = 9 kg/cm3 25,7 26,2 22,6 22,2 24,1 24,5 21,1 20,8 20,6 17,9 17,5 THICKNESS (cm) 22 Slab size 180x210 Thermal gradient °C -21 -14 Position of load I II III IV Tensions (kg/cm2) - K = 3 kg/cm3 16,9 17,1 14,8 14,7 16,5 16,7 14,5 14,3 15,8 16,0 13,8 13,7 Tensions (kg/cm2) - K = 9 kg/cm3 17,9 18,2 15,7 15,5 17,2 14,6 15,1 13,0 12,7

52 Conclution TCP design allows for:
Reduction in thickness, reducing construction costs and keeping the normal performance as traditional design Increase of axel loads, reducing transportation costs, congestion and contamination.

53 THANK YOU


Download ppt "(THIN CONCRETE PAVEMENTS)"

Similar presentations


Ads by Google