PDP & Construction
2
Construction Reviews Preliminary Engineering – PM Discretion Construction Review Items Construction schedule Access Construction limits Environmental Engineering – PM Discretion Construction Review Items Overall build-ability Bid-ability Final Engineering – Required Review Construction Review Items Specification conformance
3
Preliminary Engineering Don’t underestimate importance of early construction reviews How will the work areas be accessed? Does Contractor have room to perform work? Are additional impacts likely?
4
Has dewatering been considered? Is project constructible without dewatering? Do the construction limits encompass all Work?
5
Culvert projects commonly have additional impacts with Contractor EDA
6
Project was planned assuming dewatering could be performed with a sump… No temporary fill impacts planned Dewatering with this method was unsuccessful
7
Project was planned with no waterway fills in this area Not enough room to perform work Access only from one side of the stream
8
Contractor had no feasible way to perform work with construction limits and permit limits set in planning
9
Construction Reviews Preliminary Engineering – PM Discretion Construction Review Items Construction schedule Access Construction limits Environmental Engineering – PM Discretion Construction Review Items Overall build-ability Bid-ability Final Engineering – Required Review Construction Review Items Specification conformance
10
Questions/Discussion? Hans Gucker, P.E. Office of Construction Administration 614-387-3058