B EWARE THE G OLDEN G OOSE C ELLULAR A NTENNA I NSTALLATIONS ON E LEVATED W ATER T ANKS November 17, 2015 James Michel, PE, Water Resources Engineer II.

Similar presentations


Presentation on theme: "B EWARE THE G OLDEN G OOSE C ELLULAR A NTENNA I NSTALLATIONS ON E LEVATED W ATER T ANKS November 17, 2015 James Michel, PE, Water Resources Engineer II."— Presentation transcript:

1 B EWARE THE G OLDEN G OOSE C ELLULAR A NTENNA I NSTALLATIONS ON E LEVATED W ATER T ANKS November 17, 2015 James Michel, PE, Water Resources Engineer II Fayetteville Public Works Commission (NC)

2 Introduction 2 Background - Fayetteville PWC What are the Benefits? Issues created by antenna installation Solutions found by Fayetteville PWC

3 3 Since 1997 leasing on water tanks to cellular carriers: AT&TSprintCrown Castle VerizonT-MobileNextel (now Sprint) Agreements for seven water tanks Five-year term Three automatic five-year renewals Termination with six months notice Background

4 4 Agreements for up to a specific number of antennas 147 Antennas currently installed (171 counting radio units) Commitments for 250 antennas Capacity for 135 antennas Background

5 5 Benefits

6 6 Issues Structural Maintenance Conflicts Site Access Contracts Capacity vs. Obligation

7 7 Issues - Structural

8 8

9 9 TANK

10 10 Issues – Maintenance Conflicts

11 11 Issues – Site Access Requires Multiple Locks Requires On-Call Staff Contractors Provide Little Notice

12 12 Issues – Contracts Short Review Times Limited requirements for access Are Fees Reasonable Are Monthly Billings needed

13 13 Solutions - Structural

14 14 Antenna installation now required on corrals Engaged in design of new/upgraded corrals Fleming & Associates (F&A) for third party Structural review of proposed installations F&A to perform post construction review and verification Solutions - Structural

15 15 Solutions - Maintenance Antenna installation now required on corrals Maintenance considered when looking at cable routings

16 16 Solutions – Site Access Require 48 hours notice for access Gang locks only allow site access, PWC Staff needed to access tanks Third party access control/security

17 17 Solutions – Contracts Access notice written into contract Reasonable review times Pro-rata share of corral upgrades Annual fees instead of monthly

18 QUESTIONS? Presented by: James Michel, PE, Water Resources Engineer II Fayetteville Public Works Commission (NC)