Download presentation
Published byHilary Ferguson Modified over 8 years ago
1
OPIM 5894 Advanced Project management ARIBA IMPLEMENTATION IN MED-X case
SURESH NAIR, Ph.D. Professor, School of Business University of Connecticut, Storrs, USA
2
ARIBA IMPLEMENTATION IN MED-X case
Issues Raised Importance of Earned Value in Project Management Prof. Suresh Nair, University of Connecticut
3
ARIBA IMPLEMENTATION IN MED-X case
Calculating Earned Value - Spreadsheet Prof. Suresh Nair, University of Connecticut
4
ARIBA IMPLEMENTATION IN MED-X case
Control limits for CR Prof. Suresh Nair, University of Connecticut
5
ARIBA IMPLEMENTATION IN MED-X case
Team Assignments – Team 1, Team 2, Team 3 Which of the two components (software, technical) are underperforming according to the plan? How do you know this? (Draw graphs, as necessary to make your point) Are the components of the project within budget? How do you know? What can you conclude by looking at the combined earned value data for the project? Why did Terry Baker think that the project was going according to plan the entire time? Prof. Suresh Nair, University of Connecticut
6
ARIBA IMPLEMENTATION IN MED-X case
Team Assignments (contd.) – Team 1, Team 2, Team 3 How much longer will the project take? (it is September now) What should Martin have done earlier in the project timeline to prevent delays? What should Martin do when managing future projects to prevent similar problems from developing? Prof. Suresh Nair, University of Connecticut