Pine Mountain Lake Dredging Project Moffatt & Nichol Project Engineers Cooper Crane & Rigging, Inc. Contractor The Right Contractor Adaptability Communication
2
Project Need: Improve Channel Flow & Water Quality Project Need: Restore Navigable Depth
3
Disposal Area Project Layout
4
REGULATORY Required Studies, Reports and Testing Standard Requirements $ Sediment Quality & Sources Biological Water Quality Vegetation/ Habitat CH 3 Hg +
5
Hydraulic Disposal REGULATORY Construction Conditions Thin Layer Placement to aid benthic recovery Construction Windows: Nov 1 – Mar 31 Placement within 10’ of lake bottom Diffuser at end of discharge pipe Silt Curtain (if needed)
6
CONSTRUCTION CHALLENGES Mobilization New Priest Grade
7
Toyo Portable Barge Toyo Pump CONSTRUCTION CHALLENGES Toyo Portable Barge
8
Excavator Portable Barge Material Handling Portable Barge CONSTRUCTION CHALLENGES Excavator Portable Barge
9
“Mechanical-Hydraulic” Disposal Hydraulic Disposal CONSTRUCTION CHALLENGES Material Disposal Portable Barge
10
CONSTRUCTION CHALLENGES Varying Material
11
CONSTRUCTION CHALLENGES Weather
12
THE CREW