Presentation is loading. Please wait.

Presentation is loading. Please wait.

EAR2 Beam Line Report on the Status C. Weiss 28.11.2013EAR2 Beam Line - Report on the Status1.

Similar presentations


Presentation on theme: "EAR2 Beam Line Report on the Status C. Weiss 28.11.2013EAR2 Beam Line - Report on the Status1."— Presentation transcript:

1 EAR2 Beam Line Report on the Status C. Weiss 28.11.2013EAR2 Beam Line - Report on the Status1

2 28.11.2013EAR2 Beam Line - Report on the Status2 Beam Dump EAR-2 Exp. Hall 2 nd Collimator Magnet Pit Shielding Target New Area Existing Area 1 st Collimator Filter Box Shielding Service Gallery ISR Tunnel h [m] 0 9.8 18.1 24.4 EAR1

3 Beam Line - Design Considerations 1.Exchangeable components in order to allow new target installation (2018). 2.Minimum background to the experiment. 3.Maximum neutron fluence to the experiment. 4.Acceptable dose rate in working area close to beam line (0.5  Sv/h in ISR). 5.Maximum flexibility for experiment installation (capture & fission setup). 6.Automatic alignment with neutron beam. 7.Feasibility :-)! 28.11.2013EAR2 Beam Line - Report on the Status3

4 VACUUM CHAMBERS 28.11.2013EAR2 Beam Line - Report on the Status4

5 28.11.2013EAR2 Beam Line - Report on the Status5 Special vacuum chamber at the beam dump with inserted shielding material (avoid backscattered neutrons). Target Special vacuum chamber at the 2 nd collimator, to allow the insertion of the collimator and to optimize shielding. Special vacuum chamber to get as close as possible to the target and allow material irradiations close to target. SiMon: carbon fibre vacuum chamber (LNS / INFN).

6 n_TOF Target from the Top 28.11.2013EAR2 Beam Line - Report on the Status6 Opening on top of the spallation target structure  EAR2 TOF tube goes through there

7 Vacuum Chamber 1 8.9 m total length: – ‘Triangular’ shape for the first 1.1 m – Cylindrical shape (d = 317.9 mm) from top of target onwards Window: 1.5 mm Al, concave shape 12 mm gap of air btw. target and window 28.11.2013EAR2 Beam Line - Report on the Status7

8 Production on-going 28.11.2013EAR2 Beam Line - Report on the Status8 Vacuum chamber 1

9 28.11.2013EAR2 Beam Line - Report on the Status9 New guidings for irradiation on target Basket Ø160 Vacuum chamber 1

10 COLLIMATORS 28.11.2013EAR2 Beam Line - Report on the Status10

11 Collimators Decisions on beam parameters:  n_TOF coll. meeting May – capture beam  n_TOF tech. meeting in Sept. – fission beam 2 nd collimator: 2 m Fe + 1 m PE (with B or Li) 1 st collimator: 1 m Fe 28.11.2013EAR2 Beam Line - Report on the Status11 MeasurementCollimator & ShapeInner Diameter [mm] Capture2 nd : conicald 2 = 20 d 1 = 69 1 st : cylindricald 0 = 200 Fission2 nd : conicald 2 = 85.6 d 1 = 124.6

12 1 st Collimator 28.11.2013EAR2 Beam Line - Report on the Status12 Shutter replaced with vacuum chamber Collimator 1: 1 m Fe d inner = 200 mm (will be inserted in vacuum chamber 1) Magnet

13 PE (+B or Li) core 260 kg 1.5 m 2 m 1 m Steel core 2 t Steel vacuum vessel 5 t 28.11.2013EAR2 Beam Line - Report on the Status13 2 nd Collimator

14 28.11.2013EAR2 Beam Line - Report on the Status14 2 nd Collimator Multiple-step design as conical is not machinable!

15 BEAM LINE SHIELDING 28.11.2013EAR2 Beam Line - Report on the Status15

16 →Additional shielding layer on the floor of EAR2 for background reduction. →Steel balls above service gallery. →1.5 m concrete right above service gallery. →Fe collar at the level of 1 st collimator. →Concrete around beam pipe up to service gallery. h [m] 0 9.8 18.1 Target Service Gallery

17 Section 1 Section 2 Section 3 Section 4 Shielded Pit Section 1 Section 2 Centering pins Section 3Section 4 28.11.2013EAR2 Beam Line - Report on the Status17 Target

18 New Concrete Shieldings 28.11.2013EAR2 Beam Line - Report on the Status18

19 Steel forms for concrete taps  Green light for production 28.11.2013EAR2 Beam Line - Report on the Status19 Concrete Tap Blocks

20 1.5 m 2 m 1 m St steel balls 3 t (0.6m³) Concrete 1.1 t 28.11.2013EAR2 Beam Line - Report on the Status20 Shielding above Service Gallery

21 SERVICE GALLERY - MAGNET AND FILTER BOX 28.11.2013EAR2 Beam Line - Report on the Status21

22 Magnet and Filter Box 28.11.2013EAR2 Beam Line - Report on the Status22 Filter Box Permanent Magnet: 0.2 Tm ready by end 2013 1 st collimator in ‘storage position’ Ducts for steel ball removal

23 Filter Box * Proposed by E. Berthoumieux, F. Gunsing and C. Lederer 28.11.2013EAR2 Beam Line - Report on the Status23 FilterEAR1 Available EAR2 Proposed d [mm] Cd * ✗ 0.5 Ag ✔ 0.5 W*W* ✔ 0.8 Mo * ✔ 1 Co * ✔ 0.25 Na * ✗ 10 Al * ✔ / ✔✔ / ✔ 30 / 80 S*S* ✗ 80 C ✔ 60

24 Filter Box EAR2: 276 mm available length, each filter: 350 x 350 mm 2 28.11.2013EAR2 Beam Line - Report on the Status24 FilterEAR1 Available EAR2 Proposed d [mm] Cd * ✗ ?0.5 Ag ✔✔ 0.5 W*W* ✔✔ 0.8 Mo * ✔✔ 1 Co * ✔✔ 0.25 Na * ✗✔ 10 Al * ✔ / ✔✔ / ✔✔ / ✗ 30 / 80 S*S* ✗✔ 80 C ✔ ?60

25 Filters: Transmission Probabilities 28.11.2013EAR2 Beam Line - Report on the Status25

26 BEAM DUMP 28.11.2013EAR2 Beam Line - Report on the Status26

27 Beam Dump 28.11.2013EAR2 Beam Line - Report on the Status27 Design constraints:  Background situation in EAR2 (n_TOF)  Dose rate outside (Radioprotection)  Maximum weight (Civil Engineering) Outer dimensions (to be confirmed by RP): 1.Concrete: 3.2 x 3.2 x 2.4 m 3 2.Iron: 1.6 x 1.6 x 1.6 m 3

28 Beam Dump Entrance 28.11.2013EAR2 Beam Line - Report on the Status28 Vacuum chamber Ø200 Borated polyethylene Concrete block Gap 60mm Alignment accuracy to be defined! Al window (300  m)

29 EXPERIMENTAL AREA 28.11.2013EAR2 Beam Line - Report on the Status29

30 Additional Shielding in EAR2 28.11.2013EAR2 Beam Line - Report on the Status30 Additional shielding below beam dump. Additional shielding above 2 nd collimator = false floor (20 cm). C6D6 detectors in FLUKA.

31 Capture Setup 28.11.2013EAR2 Beam Line - Report on the Status31 -SiMon and sample exchanger (INFN) included in model. -Support for sample exchanger to be modified (less material, detector closer to sample). -Beam-line reductions before and after sample not included yet. -Small Kapton windows planned before and after sample (like in EAR1). -Valve below SiMon (vacuum + safety). -Additional shielding not included yet (false floor + below beam dump).

32 Capture Setup 28.11.2013EAR2 Beam Line - Report on the Status32 Vacuum Valve 1 m from beam centre to pillars

33 Capture + Fission Setup 28.11.2013EAR2 Beam Line - Report on the Status33 -Top part of the beam line will have to be dismantled before the crane can be used. -Vacuum chamber with inserted shielding different for capture and fission => also needs to be removed when changing the collimators.

34 From Capture to Fission (and reverse!) 28.11.2013EAR2 Beam Line - Report on the Status34 Vac. chamber + shielding in roof To be dismantled and remounted: Beam Line + Detectors 2 nd Collimator False Floor = Shielding 1 st Collimator in Service Gallery! 4-5 days!

35 6 LI OR 10 B 28.11.2013EAR2 Beam Line - Report on the Status35

36 Investigations Use 6 Li(n,  ) 3 H instead of 10 B(n,  ) 7 Li for 2 nd collimator and all shielding material in EAR2. Cross-section of 6 Li(n,  ) 3 H is 4 times smaller than 10 B(n,  ) 7 Li – higher neutron background expected. See presentation of Silvia for details about the simulations. Available material: 7.5% nat Lithium-Polyethylene. Material properties: machinable like normal PE, no safety issues reported. Budget: Approximately 10 000 Euros for 1 m 3. 28.11.2013EAR2 Beam Line - Report on the Status36

37 CONCLUSIONS 28.11.2013EAR2 Beam Line - Report on the Status37

38 Conclusions Production started for various elements: Vacuum chamber 1 All needed bellows Magnet (almost ready) To be decided: ?Filters (proposed: Ag, W, Mo, Co, Na, Al, S) ? 10 B or 6 Li ?Monitoring system (capture) ?Error margins for beam dump alignment ?Safety margins for vacuum chambers inside EAR2 To Do: Supports (detectors, sample exchanger, etc.) Equipment in EAR2 (tools, sources, etc.) 28.11.2013EAR2 Beam Line - Report on the Status38

39 Master Mind Sylvain Girod 28.11.2013EAR2 Beam Line - Report on the Status39

40 WHAT HAVE WE FORGOTTEN? Thank you for your attention! 28.11.2013EAR2 Beam Line - Report on the Status40

41 BACKUP 28.11.2013EAR2 Beam Line - Report on the Status41

42 1.5 m 2 m 1 m 28.11.2013EAR2 Beam Line - Report on the Status42 Collimator 2 Material Thickness 20 mm Gap 60 mm Minimum aperture Ø320 mm Pit Ø800 mm 175 mm available for chicanes on radius. (Here 3x58mm) Maximum gap: 2mm

43 →Additional shielding layer at the floor of EAR2 for background reduction →Steel balls above service gallery →1 m Concrete right above service gallery →Fe + Concrete wall in ISR tunnel →Fe collar at the level of 1 st collimator →Concrete around beam pipe up to service gallery

44 1 st Collimator: Removal 1.The green shielding is brought above the collimator with a trolley on the rails 2.The collimator is lifted inside the green shielding with a hoist 3.The rails guide the trolley to the storage position 4.The collimator is lowered in the storage pit 28.11.2013EAR2 Beam Line - Report on the Status44 Hoist 0.5t


Download ppt "EAR2 Beam Line Report on the Status C. Weiss 28.11.2013EAR2 Beam Line - Report on the Status1."

Similar presentations


Ads by Google