Download presentation
Published byJesse Archibald Fitzgerald Modified over 8 years ago
1
On the road to the McKinstry Creek project, a complete stream realignment and constructed floodplain
2
McKinstry Creek, Delevan, NY This was a complete stream and floodway realignment. Constructed June-July The stream had been straightened prior to 1939 (probably to accommodate the construction of Gooseneck Road)
3
McKinstry Creek near Delevan, NY, 5-18-2006, flow left to right
Existing planform (red line)
4
Existing planform (red line)
In the 1939 aerial photos the stream had already been straightened & was parallel with the road. Where had it been?? How long was it?? Existing planform (red line)
5
Green line is toe of hill
The stream needs to be longer and/or rougher but we are hemmed in by the road & the hill. Green line is toe of hill Gooseneck Road McKinstry Road We will have to increase the amplitude of the vertical sine wave (extreme verticality)!
6
Attack Angles, Thalweg Profile, and cross-sections.
Important Note: There is a sine wave for both stream planform, and the vertical thalweg profile!
7
HOW STREAMS NATURALLY DISSIPATE ENERGY !!
Purloined from Brad Humber, The Nature Conservancy Longitudinal Profile Speak about habitat in reference to facet types Cover/Breeding/Food
8
McKinstry Creek near Delevan, NY, 5-18-2006, flow left to right
New channel planform (blue line)
9
Looking US, US of the US bridge, (not in our project area) but typical pre-project conditions, straightened, wide, shallow runs, very few pools.
10
Looking DS at the straightened stretch next to the road (with boilerplate wall), this old channel will be abandoned.
11
Pre-project. The news is not good!
Photo: Deb Freeman, June 29, 2005 Pre-project. The news is not good!
12
Analysis started the year before construction, June 23, 2004
13
LET’S STOP FOR A MOMENT This is a simple “move the stream away from the road” exercise, but we will build as much habitat & energy dissipation into this project as possible!!
14
Looking DS at a pool and the crest stones for the DS rocked riffle
15
Let’s dig a pool (the Locked Log pool), McKinstry Creek, Delevan, NY
Aquatic habitat techniques include Locked Logs, Bed Diversity Stones, Leaner Stones, & appropriate vegetation
16
Looking DS, pilot channel cut for the realigned stream, bottom is at invert elevation. The right bank will be lowered for floodway.
17
Looking DS, pre-dig & overdig those pools
Looking DS, pre-dig & overdig those pools! All pools dug 3 ft deeper than invert of DS rocked riffle June 27, 2005-from derrick
18
Adding Locked Logs June 28, 2005-from derrick
19
Adding appropriate vegetation
June 29, 2005-from derrick
20
Add some stone & more Locked Logs
June 29, 2005 – from Derrick
21
Locked Logs & Bed Diversity Stones on McKinstry Creek
Aug 29, 2005, less than 7 weeks after seeding, Riverbank Wildrye and Creeping Bentgrass mix
22
Pix by derrick Looking the same pool, flowing almost at bankfull stage with Hurricane Katrina’s rain, Sept 1, 2005
23
We need 9 Engineered Rocked Riffle Grade Control structures, so let’s build one. This one is at the DS end of the project.
24
AN ENGINEERED ROCKED RIFFLE
FLOW 4 15 to 20 1 1 Largest stones are placed at crest and on downstream face, upstream face is in compression (due to water flow)
25
AN ENGINEERED ROCKED RIFFLE
Newbury says the backwater should be 1/3 the total height of the structure to dissipate energy and pass sediment through the system. FLOW Largest stones are placed at crest and on downstream face. Upstream face is in compression (due to water flow).
26
Looking DS, setting the crest stones
June 28, 2005
27
Looking DS In a small stream the two center stones are the most critical for low-flow fish passage
28
Stuff in the way!! Looking DS, setting the invert of the GC. Log used when the trackhoe pushes down on the stone
29
Moving a tree out of the way so that we can get the invert elevation shot
30
Flow left to right
31
Adding some “run” stones
32
“Styling” members of the Catt County stream team chinking stones
33
More “glide” gravel
34
Done, June 28, 2005
35
How it looks on March 28, 2006 after 3 bankfull flows & one really big flow
36
The “Shadow Wall” Pool with Locked Logs and a large transplanted multi-trunk Alder for shade
37
Channel dug to invert depth, 5 ft below surrounding land
38
Not as easy to build as it looks
39
“Shadow Wall” stones, A-axis placed perpendicular to flow
40
Half-Dense Riprap with Shadow Wall Toe
The toe stone is designed to cast a shadow into the deepest section of the channel Stone with Vertical face
41
Half-Dense Riprap with Shadow Wall Toe
Stone with Vertical face Shadow area
42
Locked Limbs/Locked Logs
43
Hand rolling a stone to lock down a Locked Limb
44
All aquatic habitat features are designed to be submerged during base flow conditions
45
Looking US at pre-dug pool with Shadow Wall & Locked Logs (everyone’s fav pool)
46
Transplanting a giant multi-trunk alder
BOB Photo: Deb Freeman
48
THIS CONTRACTOR HAD NO STREAM CONSTRUCTION EXPERIENCE!!
49
Katrina’s rains, Sept 1, 2005
50
Transplanted alder Looking DS at pool & Alder during Katrina’s rains, Sept 1, 2005
51
Looking DS, Aug 29, 2005
52
Looking DS, Sept 1, 2005
53
Looking US, Nov 2, 2005
54
Looking US, Sept 1, 2005
55
Looking US at a properly functioning pool, note roostertail dies out at DS end of pool during bankfull event, Sept 1, 2005 McKinstry Creek,
56
Looking US at a properly functioning pool, note rooster tail dies out at DS end of pool during bankfull event, McKinstry Creek, Delevan, NY
57
Looking DS at the last bend (Bend #9), Aug 29, 2005
58
Looking DS at the last bend, Sept 1, 2005
Looking DS at the last bend, Sept 1, Pool is not functioning well, fast water through length of pool. Needs to have more volume in pool (greater depth) McKinstry Creek, Delevan, NY
59
Looking US at the last bend (Bend #9) 5 weeks after construction
Photo: Deb Freeman, Aug 10, 2005
60
A BIG FLOW. MARCH 12-13, 2006 2 TO 3 FT OUT OF BANK
61
The remains of the rocked riffle, good habitat though. March 28, 2006
Mar 28, 2006-from Derrick
62
Looking US after large storm in early March 2006 destroyed the US rocked riffle
Mar 28, 2006-from Derrick
63
4 YEARS AFTER -MCKINSTRY CR FOR CATT COUNTY-DERRICK 6-12-2009
Looking US toward the failed ERR. Channel has narrowed & stabilized while banks have naturally revegetated. 4 YEARS AFTER -MCKINSTRY CR FOR CATT COUNTY-DERRICK
64
Some Contributing Factors to the Rocked Riffle Failure
DS (run) slope of rocked riffle too steep (approx. 7 to 1) Stone used was not well-graded (did not adjust very well, large stones with few medium-sized stones) Stones not in compression or keyed DS toe
65
AN ENGINEERED ROCKED RIFFLE WITH WEIGHTED TOE
Stones on crest, the downstream face, & toe all set in compression FLOW Weighted toe can designed to help stop the headward migration of a knickpoint {headcut}
66
AN ENGINEERED ROCKED RIFFLE WITH INTEGRATED FISH LADDER
At least two layers of stones are set in compression to form pools on the DS face of the ERR Flow Water surface elevation
67
Fish Sampling McKinstry Creek- Catt County Realignment (Improved) Reach
THE BOTTOM LINE: trout moved trout counted, times as many More trout per unit effort than any stream shocked in Western New York in 2007!!!
68
4 YEARS AFTER PROJECT COMPLETION Photos by Derrick JUNE 12, 2009
69
Sloughing & erosion is still occurring at the cliff.
4 YEARS AFTER -MCKINSTRY CR FOR CATT COUNTY-DERRICK
70
4 YEARS AFTER -MCKINSTRY CR FOR CATT COUNTY-DERRICK 6-12-2009
Constructed floodplain bench is still catching sediment from the cliff before it reaches the stream. This area will vegetate & collect more cliff colluvium. 4 YEARS AFTER -MCKINSTRY CR FOR CATT COUNTY-DERRICK
71
4 YEARS AFTER -MCKINSTRY CR FOR CATT COUNTY-DERRICK 6-12-2009
Looking 3 pools & two riffles that are still functioning properly. The riparian area is maturing very well. Project sponsor did not want a lot of streamside will so that this stretch would remain “fishable”. 4 YEARS AFTER -MCKINSTRY CR FOR CATT COUNTY-DERRICK
72
Looking US @ downed veg providing shade, cover, and carbon.
4 YEARS AFTER -MCKINSTRY CR FOR CATT COUNTY-DERRICK
73
Looking US @ functioning channel & downed vegetation.
4 YEARS AFTER -MCKINSTRY CR FOR CATT COUNTY-DERRICK
74
Looking US @ veg providing shade over the functioning pool.
4 YEARS AFTER -MCKINSTRY CR FOR CATT COUNTY-DERRICK
75
Looking DS @ undercut bank & leaning tree. Excellent aquatic habitat.
4 YEARS AFTER -MCKINSTRY CR FOR CATT COUNTY-DERRICK
76
4 YEARS AFTER -MCKINSTRY CR FOR CATT COUNTY-DERRICK 6-12-2009
Looking pool & riffle with maturing riparian vegetation & downed wood. 4 YEARS AFTER -MCKINSTRY CR FOR CATT COUNTY-DERRICK
77
Tenacious 1 year old Catskill Sand Cherry spreading around stones.
4 YEARS AFTER -MCKINSTRY CR FOR CATT COUNTY-DERRICK
78
Looking DS @ DS riffle with some stone displaced downstream.
4 YEARS AFTER -MCKINSTRY CR FOR CATT COUNTY-DERRICK
79
Looking DS at the next section of stream we will work on.
80
Looking DS of the project on 6/24/2004
Looking DS of the project on 6/24/ We tackle 49 bends in this section next.
81
Headcut in the beaver meadow, 6/24/2004
82
This is a trout stream? 6/24/2004
83
the end
Similar presentations
© 2024 SlidePlayer.com. Inc.
All rights reserved.