Presentation is loading. Please wait.

Presentation is loading. Please wait.

VT 100 over the Mad River Bridge Replacement July 13, 2015.

Similar presentations


Presentation on theme: "VT 100 over the Mad River Bridge Replacement July 13, 2015."— Presentation transcript:

1 VT 100 over the Mad River Bridge Replacement July 13, 2015

2 VT 100 over the Mad River Bridge Replacement Presented By Rob Young, P.E. Project Manager – VTrans Tom Kendrick, P.E. Senior Bridge Engineer – McFarland Johnson Dave Kull, P.E. Bridge Engineer – McFarland Johnson

3 VT 100 over the Mad River Bridge Replacement Agenda Introductions Existing Bridge Condition Proposed Structure Proposed Closure Date & Duration Proposed Detour Route Questions

4 VT 100 over the Mad River Bridge Replacement Existing Bridge Originally constructed in 1938 Bridge is structurally deficient Less than desirable roadway width (22-ft)

5 VT 100 over the Mad River Bridge Replacement Bridge Condition Rating Bridge Deck: 4 (Poor) Bridge Superstructure: 6 (Satisfactory) Bridge Substructure: 5 (Fair) Overall Sufficiency Rating: 54 (Out of 100)

6 VT 100 over the Mad River Bridge Replacement Existing Bridge

7 VT 100 over the Mad River Bridge Replacement Existing Bridge

8 VT 100 over the Mad River Bridge Replacement Existing Site Lareau Farm Country Inn VT 100 Mad River Warren Waitsfield

9 VT 100 over the Mad River Bridge Replacement Proposed Improvements Lareau Farm Country Inn VT 100 Mad River Warren Waitsfield

10 VT 100 over the Mad River Bridge Replacement Proposed Bridge 172’ Span

11 VT 100 over the Mad River Bridge Replacement Proposed Bridge Section 11’ Lanes, 5’ Shoulders 5’ Shldr 11’ Lane Precast Deck Panel Ultra High Performance Concrete Steel Girder

12 VT 100 over the Mad River Bridge Replacement Method of Construction: Accelerated Bridge Construction Building Bridges While Minimizing Traffic Disruptions

13 VT 100 over the Mad River Bridge Replacement Deck Panel Placement 38 Panels to be Placed

14 VT 100 over the Mad River Bridge Replacement Deck Panel Placement

15 VT 100 over the Mad River Bridge Replacement Ultra High Performance Concrete Placement

16 VT 100 over the Mad River Bridge Replacement Pre-Assembly

17 VT 100 over the Mad River Bridge Replacement Rock Removal Mechanical Rock Removal Methods can be Slow and Disruptive

18 VT 100 over the Mad River Bridge Replacement Rock Removal Rock Blasting Will be Used to Reduce Removal Time and Disruptions Approximate Blasting Area

19 VT 100 over the Mad River Bridge Replacement Pier Removal Temporary Stone Causeway Proposed for Construction Access

20 VT 100 over the Mad River Bridge Replacement Future Trail Access

21 VT 100 over the Mad River Bridge Replacement Project Schedule Project Advertised – September 2015 Begin Pre-Closure Activities – April/May, 2016 Bridge Closure – Tuesday, July 5, 2016 Estimated Bridge Opening – August 6, 2016 Project Completion – October 2016 Estimated Bridge Closure Duration – 33 Days

22 VT 100 over the Mad River Bridge Replacement Project Schedule Daily Lane Closures Not Permitted Until 14 days Prior to Bridge Closure – June 21, 2016 Financial Incentives & Disincentives Included in Contract to Encourage Early Completion

23 VT 100 over the Mad River Bridge Replacement Detour Route A B Detour Summary A-B Thru = 3 miles A-B Detour = 7 miles Added = 4 miles End-End = 10 miles VT Rt. 17 German Flats Road Sugarbush Access Rd

24 VT 100 over the Mad River Bridge Replacement Local Road Maintenance Project Specifications Require the Contractor to Coordinate with Local Officials to Monitor and Maintain Local Roads used for Detours. Inspection of German Flats & Sugarbush Access Roads will be Done Pre & Post Closure. $10,000 to be Allocated for Line Striping, Pothole & Other Required Maintenance

25 VT 100 over the Mad River Bridge Replacement Traffic Control

26 VT 100 over the Mad River Bridge Replacement Questions / Comments


Download ppt "VT 100 over the Mad River Bridge Replacement July 13, 2015."

Similar presentations


Ads by Google