1
Team 23 –RATMAZES Tyler Ferro, PM Andy Thouvenot, APM Adam Watkins Paul Stofko Dominic DiGregor David Coats Client Dr. Eric Jacobs Advisor Dr. Nazeih M. Botros
2
Outline Executive Summary -DC List of Deliverables - PS Principle Responsibilities - PS Discussion Project Description - AT Literature Review Summary -DD Timeline - TF Action Item List - TF Resources Needed - AW Summary - AW
3
Executive Summary Project Background Develop modular chamber Update outdated DOS software More user-friendly Total Dollars Needed: $1055
4
List of Deliverables Control box prototype Test chamber prototype Soundproof box prototype Code developed during the design process Documentation developed during the design process Documentation developed during the test phase
5
Principle Responsibilities
6
Discussion Project Description Client Objectives Additional Objectives Literature Review
7
Timeline Activity 21- Jan 28- Jan4-Feb 11- Feb 18- Feb 25- Feb4-Mar 11- Mar 18- Mar 25- Mar1-Apr8-Apr 15- Apr 22- Apr 29- Apr Verify specs & Design Make parts for chamber and box Build Chamber and soundproof box Testing & Debugging Build subsystems
8
Action Item List ActivityPersonDate AssignedDate DueStatusComments Verify specifications and designTF11/17/20091/21/2010 0% Verify specifications and designAT11/17/20091/21/2010 0% Verify specifications and designDD11/17/20091/21/2010 0% Verify specifications and designAW11/17/20091/21/2010 0% Verify specifications and designPS11/17/20091/21/2010 0% Verify specifications and designDC11/17/20091/21/2010 0% Check progress of ordered partsTF11/17/20091/21/2010 0% Check progress of ordered partsAT11/17/20091/21/2010 0% Check progress of ordered partsDD11/17/20091/21/2010 0% Check progress of ordered partsAW11/17/20091/21/2010 0% Check progress of ordered partsPS11/17/20091/21/2010 0% Check progress of ordered partsDC11/17/20091/21/2010 0% Team Progress MemoPS11/17/20091/28/2010 0% Build chamber manipulation devicesPS11/17/20092/25/2010 0% Build chamberAT11/17/20093/4/2010 0% Build sound proof boxDC11/17/20093/4/2010 0% Review software for controlsTF11/17/20094/1/2010 0% Final quality check Review software for controlsDD11/17/20094/1/2010 0% Final quality check Review software for controlsAW11/17/20094/1/2010 0% Final quality check
9
Resources Needed DescriptionPrice Soundproof Chamber $195 Chamber $181 Manipulanda $53 Control $426 Miscellaneous$200 Total $1055
10
Summary Project Overview Schedule Resources Needed
11
Questions?