1 Upgrade projects and APT update DT-LHCb coordination meeting 28 September 2015

2 APT update Numbers given as agreed with Mar and Andrea Request to increase FTE for O. Jamet has been made

3 APT update

4 Road to the EDR 4 Requirements Safety system Transfer line concept Plant concept design Requirements Evaporator concept and performance Transfer line concept Redundancy concept P&ID FA Engineering Design Review Velo UT Evaporator concept and performance Overview of the main system aspects

5 Components to be reviewed 1.VELO and UT evaporator concept and performance – Important to experimentally validate the assumptions made in the requirements document – Review the suggested evaporator and manifold design – Conceptual design of the connection to the junction box 2.Transfer line concept – Finalize locations for cooling plant and junction box – To be done in close collaboration with the TC team 3.Cooling plant conceptual design – P&I document, only very basic Functional Analysis (FA) – Review of schedule and cost estimate for cooling plant – WP between LHCb and DT for plant construction 5

6 Cooling plant location 6 Preferred Location: Alcove PZ85 (VELO side) – About 25-30m 2 are available and easy to access for objects up to 90cm wide, 1.4m long and 2m + high – Area needs to be equipped with power (EXD, EBD, ESD), network, primary cooling – poor ventilation  Seems to be the best option. – Additional advantage: The transfer line towards the detector would be straight. Passing the shielding wall looks not too complicated.

7 Junction box location Preferred Location: On top of the LHCb magnet Not much space needed Straight forward connection to transfer line running on the top (close to crane gallery) Ideal to distribute from there to UT A-and C-side, and VELO 7

8 2014 – Q34: Requirement document by VELO and UT 2015 – Q12: Development and definition of evaporator systems – Q23: Concept P&ID Preliminary sizing Control philosophy Redundancy approach – Q3: P&ID document & functional analyses – Oct 2015: Cooling EDR – Q4 start of design 2016 – Q123 Detailed 3D design of hardware Evaporator, junction box, transfer line, cooling plants – May 2016: Cooling PRR junction box, transfer line – Oct 2016: Cooling PRR cooling plant. – Q4 Production of transfer line and junction box 2017 – Q1 Transfer line and junction box installation (EYETS, 19 weeks) – Q1234 Production of the cooling hardware 2018 – Q12 cooling system installation in UXA (preferred place: A-side alcove) – Q234 Cooling system over junction box commissioning – Q3 start of LS2 – Q4 Removal of current VELO and TT 2019 – Q2 Upgrade VELO and UT installation – Q34 Detector commissioning with cooling – Q4 end of LS2 Present Schedule Comments: Needs to be updated for the EDR, taking into account: – The updated LHC schedule – The new concept using the LUCASZ unit for UT installation and commissioning – Time for procurement of cooling plant components after the PRR 8

9 Date for Cooling EDR LHCb week: 7 – 11 December 2015 Start of YETS: December 13  Do the EDR before these dates/constraints Suggestion: Thursday, December 3, full day ? Shall we have external reviewers ? 9