Decision Making and Data Management in Geotechnical Engineering
Silas Nichols Principal Bridge Engineer – Geotechnical Federal Highway Administration Office of Bridges and Structures
2
Influencing Trends and Opportunities
Better Informed Decision Making in Project Delivery Effective Management and Communication of Geotechnical Data
3
Log-In Screen
4
Deep Mixing Methods
5
Aggregate Columns Light Weight Fill
6
Column Supported Embankments
7
Technologies Included
Aggregate Columns Beneficial Reuse of Waste Materials Bio-Treatment for Subgrade Stabilization Blast Densification Bulk-Infill Grouting Chemical Grouting/ Injection Systems Chemical Stabilization of Subgrades & Bases Column-Supported Embankments Combined Soil Stabilization with Vertical Columns Compaction Grouting Continuous Flight Auger Piles Deep Dynamic Compaction Deep Mixing Methods Shallow Mass Mixing
8
Technologies Included (cont.)
Intelligent Compaction Jet Grouting Light Weight Fills Mechanical Stabilization of Subgrades & Bases MSE Walls Micro-Piles Onsite Use of Recycled Pavement Materials Partial Encapsulation PVDs & Fill Preloading Rapid Impact Compaction Reinforced Soil Slopes Sand Compaction Piles Screw-In Soil Nailing Shoot-In Soil Nailing Shored MSE Walls Traditional Compaction Vacuum Preloading w/ & w/o PVDs Vibrocompaction Vibro-Concrete Columns
9
Technologies Included (cont.)
Drilled/Grouted & Hollow Bar Soil Nailing Electro-Osmosis Excavation & Replacement Fiber Reinforcement in Pavement Systems Geocell Confinement in Pavement Systems Geosynthetic Reinforced Construction Platforms Geosynthetic Reinforced Embankments Geosynthetic Reinforce-ment in Pavement Systems Geosynthetic Separation in Pavement Systems Geosynthetics in Pavement Drainage Geotextile Encased Columns High-Energy Impact Rollers Hydraulic Fill + Vacuum Consolidation + PVDs Injected Lightweight Foam Fill
10
Technology Fact Sheets
Case Histories Technology Fact Sheets Photographs Design Procedures QC/QA Procedures Specifications Cost Estimating Tools >50 Technologies Technical Bibliography 10
11
Research & Vetting Process
1,000s pages Tech Docs 38 Post-Doc & Grad Students Research & Develop 38 Post-Doc & Grad Students & 12 Principal Investigators & Advisory Board & Peer Reviewers 100s page Summaries 8 Tools – 2 to 40 pages each 11
12
Value Added The system collects, synthesizes, integrates, and organizes a vast amount of critically important information about geotechnical solutions on a readily accessible website 12
13
Did you know… www.GeoTechTools.org
…That up to half of all construction claims in highway works are related to geotechnical issues.
14
Application Areas Construction over Unstable Soils
Construction over Stable/Stabilized Soils Working Platforms Geotechnical Pavement Components (Base, Subbase, and Subgrade)
15
Transition and Closure
Project Management Example Guide Illustration: Manage Change Work the Plan Transition and Closure Initiate and Align Plan the Work Endorse the Plan After:
16
Constraints and Risks Examples Constraint: 3-inch Settlement Limit
Risk: Settlement exceeds 3 inches Constraint: 90% Settlement by 3 months Risk: 90% Settlement takes more than 3 months
17
Typical Constraints General Schedule/Time Cost/Budget ROW Limits
Traffic Flow Weather Environmental Geotech-Related Subsurface Conditions Time of settlement Vibrations Noise Proprietary
18
Implementation Goal Integration of GeoTechTools into Practice – both program delivery and project development
19
Target Audience Public agency personnel at Local, State and Federal levels Geotechnical Engineers Project Planners Project Managers Construction Resident Engineers Maintenance Consultants, Contractors, A/Es Academics/Students 19
20
What About Data Management and Communication?
21
Proposed Geotechnical Asset Taxonomy
Physical Asset Corridor and/or GAM Section ROW Feature Independent Feature Slope Rock Soil Modified Embankment Subgrade Earth Retaining Structure Stabilized Earth Steel or Reinforced Concrete Element of other Structure Bridge Element Tunnel Element Pavement Element Outside-ROW Feature Slopes Water bodies Structures (walls, etc.) Non-Corridor Material Sites Stockpiles or other Non-Physical Asset Data Knowledge Equipment The adjective “Geotechnical” means the asset is comprised of earth, pertains to earth, or its performance is achieved through earth interaction with a structure or inclusion. Inclusions are any and all non-earth modifications: pipes, anchors, grids, fabrics, grouts, etc. Predominant distinction in how feature is managed. Features with inclusions are “modified”. Established management systems for other structures that have (or should have) geotechnical elements. Others, could be added; for example – culverts. High slopes, shorelines, and structures typically owned by others outside the ROW that are sources of risk because they can impact performance Investigation and test results, lab and field equipment, key personnel
22
Physical Assets Along a Corridor
23
What Data?
24
What Data?
25
What Data?
26
What’s the Plan? Development of Guidance for:
Management of Geotechnical Information Communication of Geotechnical Information Research on “Big Data” management Promotion of DiGGS as transfer protocol for communication of geotechnical data
27
Thank You! Silas Nichols, P.E. Principal Geotechnical Engineer
U.S. Federal Highway Administration Washington, DC