Presentation is loading. Please wait.

Presentation is loading. Please wait.

Place your chosen image here. The four corners must just cover the arrow tips. For covers, the three pictures should be the same size and in a straight.

Similar presentations


Presentation on theme: "Place your chosen image here. The four corners must just cover the arrow tips. For covers, the three pictures should be the same size and in a straight."— Presentation transcript:

1 Place your chosen image here. The four corners must just cover the arrow tips. For covers, the three pictures should be the same size and in a straight line. Developing capacity & connection processes Long term non-firm capacity: Draft business principles 6 th September 2012

2 2 Long Term Non-Firm: Recap  Allow new connections and existing site expansions access to the NTS ahead of timescales for firm incremental capacity delivery, but only where NTS reinforcement is needed  Would provide greater certainty for customers  Where customer has significantly progressed their project and NTS connection is ready, but firm capacity delivery is beyond the first potential gas flow date  Where customer project is ready ahead of schedule  Where customer project doesn’t need planning consent so timescales are potentially misaligned  ‘In flight’ projects  Aimed at covering the gap between firm capacity delivery and first gas flow date Option A: Long term off-peak exit / interruptible entry capacity Introduces new capacity product, sold through auctions (adhoc or fixed) Option B: Non-obligated firm capacity, with buyback option Released via non-obligated capacity mechanism with a buyback option contract attached

3 3 Draft Business principles  High level principles  First draft only  Industry discussion needed to ensure ideas are developed into a workable solution for industry, consider:  Are these options workable?  Are these viable alternatives?

4 4 Process trigger No Yes Customer signals incremental capacity requirement NG NTS analyse & determine how requirement could be met In the case that NTS build is required, does customer require early access to NTS? Unsold firm? Substitution? NTS build? Customer bids/applies for firm incremental capacity from the agreed delivery date Long term non-firm capacity release would be considered for the ‘early capacity period’

5 5 Long Term Non-Firm: Release criteria  Applies to both Option A & B  Only released where:  An incremental signal has been provided and  Earlier access to the NTS is required and  NTS reinforcement required  Staged capacity release (annually), conditional upon:  Demonstration requirements being satisfied (where a bilateral agreement is in place); and  There being insufficient unsold firm capacity available to fulfil the customer’s capacity requirement for the year ahead (customer must purchase any unsold firm capacity where available)

6 6 Option A: Draft business principles Capacity Product  Longer term release of Interruptible Entry and Off-Peak Exit Capacity  Release via an annual adhoc process  Subject to curtailment  Likelihood of curtailment provided to the relevant user for the release period Pricing  ‘Pay as Bid’ pricing, with a reserve price Duration  Capacity released throughout entire ‘early capacity period’  Held once a year for (up to) a 12 month period  Up to 12 Monthly blocks

7 7 Option B: Draft business principles Capacity Product  Non-obligated firm capacity  Release via an annual adhoc process  Buyback option contract for all days on which capacity is held  Likelihood of buyback provided to the relevant user for the release period Pricing  ‘Pay as Bid’ capacity pricing  Zero option price + exercise price capped at price paid for capacity Duration  Capacity released throughout entire early capacity period (annually)  Held once a year for (up to) a 12 month period  Up to 12 Monthly blocks

8 Long Term Non-Firm Capacity Scenarios: How might it work in practice?

9 9 Scenario 1 – Status quo arrangements Buyback Period Sold/Obligated Level Request level Firm capacity delivery date Achievable firm capacity delivery date LTNF = Long term non-firm capacity Time Capacity Quantity Incremental Capacity Situation: NG NTS unable to meet firm capacity delivery date and no permits to use

10 10 Scenarios 2&3 – Status quo arrangements LTNF Sold/Obligated Level Request level Scenario 2: NG NTS can meet firm capacity delivery date but customer requests early access Scenario 3: NG NTS unable to meet firm capacity delivery date, extend with permits First gas date Firm capacity delivery date extended by permits Firm capacity delivery date LTNF = Long term non-firm capacity Time Capacity Quantity Incremental Capacity

11 11 Scenario 4 – ‘PARCA’/Split Auctions & PCA LTNF Period Sold/Obligated Level Request level First gas date Firm capacity delivery date Demo Dates passed  All Planning Consents Obtained  Situation: Demonstration information satisfied and all planning consents obtained Time Capacity Quantity LTNF = Long term non-firm capacity Incremental Capacity

12 12 Initial LTNF period Sold/Obligated Level Request level LTNF to replace delayed incremental Original firm capacity delivery date Revised firm capacity delivery date due to planning consent delay NG NTS Planning consent obtained  Situation: Delay in obtaining NG NTS planning consent Scenario 5 – ‘PARCA’/Split Auctions & PCA First gas date Time Capacity Quantity LTNF = Long term non-firm capacity Incremental Capacity Customer Planning consent obtained 

13 13 Proposed first LTNF period Sold/Obligated Level Request level LTNF to replace delayed incremental Original firm capacity delivery date & revised first gas date Revised firm capacity delivery date due to planning consent delay Customer Planning consent obtained  Situation: Delay in obtaining customer planning consent Scenario 6 – ‘PARCA’/Split Auctions & PCA Original First gas date Time Capacity Quantity LTNF = Long term non-firm capacity Incremental Capacity NG NTS Planning consent obtained 

14 14 Sold/Obligated level Request level Final Demo Date failed Proposed LTNF period – year 1 Firm capacity delivery date First gas date Incremental capacity build & release cancelled Date LTNF would have been renewed for new gas year Proposed LTNF period – year 2 Situation: Failure to provide demonstration information Scenario 7 – ‘PARCA’/Split Auctions & PCA Time Capacity Quantity LTNF = Long term non-firm capacity Planned Incremental Capacity (no longer to be released at this stage)


Download ppt "Place your chosen image here. The four corners must just cover the arrow tips. For covers, the three pictures should be the same size and in a straight."

Similar presentations


Ads by Google