MSD II Week 7 Update P13265: Motorcycle Safety Lighting and Portable Electronics Charging System
2
Mike: Action Items Status Lens Covers o Incomplete: Still waiting on shell XBee's tested in lab o Complete Replicated signals from bike, functionality confirmed Tech Paper o Delayed, due to poster pull-forward Poster rough draft o Complete o Met with Killian to make layout o Created draft of content
3
Mike: Action Items Status cont. Misc. EE work: o Assisted Eric with testing board functionality and revisions to new board layout o Completed CEMA lab training, received swipe access
4
Mike: Next Steps for Week 8 Finalize poster- 4 hours Light channels? Populate boards upon arrival ~ 12 hours Assist with misc. wiring
5
Tyler: Action Items Status Shell Rework/Remake o Complete o Finally was able to get a g. Assembly Plan o In Progress; No new updates since last week. Poster o Incomplete, met with Killian to figure out some layouts.
6
Tyler: Next Steps for Week 8 Shell Assembly ~15 hrs o With shell complete, assembly should go smoothly. Majority to be completed this weekend. Poster Work w/Killian ~5-10 hrs Assembly Plan (Final details will be completed alongside the actual assembly of thr backpack) EDGE update ~3 hrs
7
Ben: Action Items Status Finish electronics housing box o COMPLETE Other: o I worked with Tyler to help with the shell o My section of the Tech Paper is mostly complete
8
Ben: Next Steps for Week 8 Finish my Tech Paper section Assist with Shell creation and assembly
9
Eric: Action Item Status Continue MSP430 Development o In Progress/Incomplete o Framework is incomplete, primary focus was placed on board debug, proof of functionality and layout revision. Board error identification o Complete o All errors located, documented. Board Functionality Testing o Battery Monitor - Complete o Push Buttons/Flags - Complete o Battery Isolation - Complete o Wireless System - Complete o Light Strip Drivers - Complete Final Board Layout with Revisions o Complete
10
Eric: Next Steps for Week 8 MSP430 Development - Finish Functionality Development Assist with Final Board Population
11
TJ: Action Items Status Continue Tech Paper o Complete o Added more paragraphs to revise with Mike Populate PCBs o In Progress o Determined adapters will not work, ordered new boards Test XBee Units and Document Tests o Complete o Recreated bike signals in the lab and tested with XBee units
12
TJ: Next Steps for Week 8 90% Finished with Tech Paper ~ 5 Hours Populate PCBs ~ 10 Hours
13
Killian: Action Items Status Complete Photoshop and Illustrator Renderings: In Progress o Spent a lot more time than expected working on the mold and the shell, also had surprise co-op interview Form shell and Control Panel: Complete o After quite a few attempts we finally got the shell to work. o HUGE THANK YOU to Vince for helping us get the control panel printed. It looks great and the components fit through the holes perfectly Draw up Outlines of Poster, begin inserting text and graphics: In Progress o Grid layouts formed, want to edit text/content
14
Killian: Next Steps for Week 8 Finish Renderings: 2 in Illustrator, 2 in Photoshop ~10 hours Assist Tyler in backpack assembly ~8 hours Finish Poster ~6 hours
15
Major Week 8 Action Items Mike- Lens Covers (hopefully) TJ - Populate PCBs Tyler- Finalize shell Eric- MSP430 Code All- Finish tech paper sections
16
Lessons Learned Mike o A backup plan will be necessary to complete our final assembly by Imagine RIT. Tyler o A good fallback plan for the mold was not in place which has pushed it's completion time back even more. Ben o Vacuum forming is trickier than I originally thought.
17
Lessons Learned cont. Eric TJ o Adapters were a good idea, but not feasible option because of in-house manufacturing limitation Killian