Chapter 16 & 9 Scheduling Work & Employees
2
Scheduling Outline What needs to be scheduled? –doctor’s office, restaurant, mfg. plant, hospital –employees vs. products Gantt charts Dispatching (sequencing) rules for scheduling work Scheduling employees
3
Shop floor control includes: 1.assigning a priority to each order 2.issuing dispatching lists to each work center (what and when to produce) 3.keeping WIP inventory updated 4.providing input-output control for all work centers 5.monitoring efficiency, utilization, and productivity of workers and machines
4
Scheduling (Dispatching/Sequencing) Rules FCFS – First Come, First Served SPT – Shortest Processing Time EDD – Earliest Due Date Least Slack (LS) slack = (time until due date) – (remaining lead time) process job with smallest slack first Critical Ratio (CR) CR = (time until due date) / (remaining lead time) process job with smallest CR first
5
Scheduling Rules Example Job #Due Date Remaining Lead Time Time Until Due Date SlackCR 768584 7756512 751617 758568 7636914 currently day 50; 5 jobs at a machine
6
Gantt Chart weeks of processing time work order # mach. A mach. B mach. C total 34 4 2 1 35 1 3 1 36 2 2 2 37 1 1 2
7
Gantt Chart FCFS: 34, 35, 36, 37 34 35 3637 34 35 36 37 C B A 15 weeks
8
Gantt Chart SPT: 37, 35, 36, 34 34 35 3637 34 35 36 37 C B A 11 weeks
9
Work-Shift Scheduling Rule ( work 5 days, 2 consecutive days off) SunMonTueWedThuFriSat 2534245 Minimum # of employees needed
10
Work-Shift Scheduling Rule ( work 5 days, any 2 days off) SunMonTueWedThuFriSat 2534245 Minimum # of employees needed
11
Work-Shift Scheduling Rule ( work 4 days, 3 consecutive days off) SunMonTueWedThuFriSat 2534245 Minimum # of employees needed