Download presentation
Presentation is loading. Please wait.
Published byFranklin Copeland Modified over 9 years ago
1
Lecture 20 Production Activity Control (Revision)
Books Introduction to Materials Management, Sixth Edition, J. R. Tony Arnold, P.E., CFPIM, CIRM, Fleming College, Emeritus, Stephen N. Chapman, Ph.D., CFPIM, North Carolina State University, Lloyd M. Clive, P.E., CFPIM, Fleming College Operations Management for Competitive Advantage, 11th Edition, by Chase, Jacobs, and Aquilano, 2005, N.Y.: McGraw-Hill/Irwin. Operations Management, 11/E, Jay Heizer, Texas Lutheran University, Barry Render, Graduate School of Business, Rollins College, Prentice Hall
2
Objectives Production activity control Gantt chart
Critical ratio scheduling Finite loading Scheduling Assignment method Sequencing Slack Johnson's Rule Monitoring Advance planning and scheduling Scheduling procedure Employee Scheduling
3
Production Activity Control
PAC in the MPC System Shop Floor Control Vendor Scheduling Production Activity Control Techniques Basic Data Gantt Charts Priority Scheduling Finite Loading Process Design Impact on Scheduling Batch Manufacturing – Work Orders Repetitive Manufacturing – JIT
4
Production Activity Control in the MPC System
5
Basic Data
6
Routing Data and Operation Setback Chart
7
Gantt Charts _____________________________________________________
The incoming orders at Tom's Sailboard follow different routes through the shop but all orders must stop at each of the three work centers in the plant. The table below shows all tasks for four jobs that arrive over 5 days and need to be scheduled at the company. It is currently November 10 and Tom works a seven-day week. _____________________________________________________ Arrival Job/WC Processing time (days) Order date routing WC 1 WC 2 WC 3 (B)iff Nov (G)riffin Nov (H)erbie Nov (K)errie Nov Assume that the new material for all orders is in stock and that a first-come/first-served sequencing rule is used at all work centers. All three work centers are idle as work begins on orders B and G on November 10.
8
Tom’s Sailboard Construct a Gantt chart depicting the processing and idle times for the three work centers for these four jobs. Arrival Job/WC Processing time (days) Order date routing WC 1 WC 2 WC 3 (B)iff Nov (G)riffin Nov (H)erbie Nov (K)errie Nov
9
Tom’s Sailboard How many days does each job wait in queue for processing at work center 2? The determination of how long jobs wait at work center 2 is as follows: B and G are processed immediately at work center 2, order K must wait 1 day (11/14) and order H waits 4 days (11/12, 11/13 at WC3) and (11/16 and 11/17 at WC2).
10
Priority Sequencing Rules
First Come, First Served Shortest Operation Next Earliest Due Date Order Slack: (Time Remaining until Due Date – Sum of Remaining Setup and Run Time) Slack per Operation Critical Ratio: (Due Date-Now)/(Lead Time Remaining) ________________________________________ Lead Time Remaining includes setup, run, move and queue time for all remaining operations.
11
__________________________
Knox Machine The jobs below are waiting to be processed at the P&W Grinder at the Knox Machine Company. (There are no other jobs and the machine is empty.) __________________________ Machine processing Date job arrived Job due Job time (in days)*__ at this machine date__ A B C D *Note: This is the final operation for each of these jobs. ___________________________________________________________
12
Knox Machine: Solution
The production manager has heard about three dispatching rules: the Shortest Operation Next Rule, the First-Come/First-Served Rule, and the Earliest Due Date Rule. In what sequence would these jobs be processed at the P&W grinder if each rule was applied? The shortest operation next rule: B-D-A-C The first-come, first-served rule: D-A-B-C The earliest due date rule: C-A-D-B Machine processing Date job arrived Job due Job time (in days)*__ at this machine date__ A B C D *Note: This is the final operation for each of these jobs.
13
Knox Machine: Solution
If it's now the morning of July 10 and the Shortest Operation Next Rule is used, when would each of the four jobs start and be completed on the P&W grinder? (Express your schedule in terms of the calendar dates involved, assuming that there are 7 working days each week.) P & W Grinder Job B D A C Date 7/10 7/11 7/12 7/13 7/14 7/15 7/16 7/17 7/18 7/19 7/20 7/21
14
Critical Ratio Scheduling
Eight weeks remain for constructing the a 50foot yacht. Assume that each week consists of 5 work days, for a total lead time of 40 days. The work required to complete the yacht comprises 10 operations, 4 days for each.
15
Yacht Project Example On Tuesday morning of week 3, 3 of the 10 operations had been completed and the yacht was waiting for the fourth operation. What's the critical ratio priority?
16
Yacht Project Example What's the critical ratio priority if only 2 of the 10 operations are completed by Tuesday morning of week 3?
17
Finite Loading
18
The Bundy Company The Bundy Company produces for three products (A, K, and P). Each order goes through the same three machine centers, but not necessarily in the same sequence. Each order must be finished at a machine center before another can be started. Orders cannot be split. The shop works a single eight-hour shift five days per week. Assume that the time to move between machines is negligible. each machine center is operated eight hours per day. All three machines are currently available for scheduling, and no further orders will arrive.
19
The Bundy Company Processing time Machine at machine center
center ___(in days)____ Order Order routing due date A K P Note: Order due dates are fixed based on the shop calendar. It is now 8:00 A.M. Monday (day 1), Monday of next week is day 6, etc.
20
The Bundy Company Using the horizontal loading procedure with earliest-due-date priority sequencing rule, prepare a Gantt chart showing the production schedule for the three orders above.
21
The Bundy Company Using the vertical loading procedure and the shortest-operation-next priority sequencing rule, prepare a Gantt chart showing the production schedule for the three orders above.
22
Scheduling
23
What is Scheduling? Last stage of planning before production occurs
Specifies when labor, equipment, and facilities are needed to produce a product or provide a service
24
Scheduled Operations Batch Production Process Industry
Aggregate planning Master scheduling Material requirements planning (MRP) Capacity requirements planning (CRP) Process Industry Linear programming EOQ with non-instantaneous replenishment Mass Production Assembly line balancing Project Project -scheduling techniques (PERT, CPM)
25
Objectives in Scheduling
Meet customer due dates Minimize job lateness Minimize response time Minimize completion time Minimize time in the system Minimize overtime Maximize machine or labor utilization Minimize idle time Minimize work-in-process inventory
26
Shop Floor Control (SFC)
Schedule and monitor day-to-day job shop production Also called production control and production activity control (PAC) Performed by production control department Loading - check availability of material, machines, and labor Sequencing - release work orders to shop and issue dispatch lists for individual machines Monitoring - maintain progress reports on each job until it is complete
27
Loading Process of assigning work to limited resources
Perform work with most efficient resources Use assignment method of linear programming to determine allocation
28
Assignment Method Perform row reductions Perform column reductions
subtract minimum value in each row from all other row values Perform column reductions subtract minimum value in each column from all other column values Cross out all zeros in matrix use minimum number of horizontal and vertical lines If number of lines equals number of rows in matrix, then optimum solution has been found. Make assignments where zeros appear Else modify matrix: subtract minimum uncrossed value from all uncrossed values add it to all cells where two lines intersect other values in matrix remain unchanged Repeat steps 3 and 4 until optimum solution is reached
29
Assignment Method Initial PROJECT Matrix 1 2 3 4 Bryan 10 5 6 10
Kari Noah Chris Row reduction Column reduction Cover all zeros Number lines number of rows so modify matrix 12
30
Assignment Method Modify matrix Cover all zeros 1 0 1 2 1 0 1 2
Number of lines = number of rows so at optimal solution Bryan Kari Noah Chris PROJECT Bryan Kari Noah Chris Project Cost = ( ) X $100 = $2,100 12
31
Assignment Method - Setup
Solution goes here Only 1 leader can be assigned to each project Click “Solve” for solution Sum of all rows and columns = 1
32
Assignment Method - Solution
Assignments indicated by 1 Cost of solution
33
Sequencing Prioritize jobs assigned to a resource
If no order specified use first-come first-served (FCFS) Other Sequencing Rules FCFS - first-come, first-served LCFS - last come, first served DDATE - earliest due date CUSTPR - highest customer priority SETUP - similar required setups SLACK - smallest slack CR - smallest critical ratio SPT - shortest processing time LPT - longest processing time
34
Minimum Slack & Smallest Critical Ratio
SLACK considers both work and time remaining CR recalculates sequence as processing continues and arranges information in ratio form SLACK = (due date – today’s date) – (processing time) time remaining due date - today’s date work remaining remaining processing time CR = = If CR > 1, job ahead of schedule If CR < 1, job behind schedule If CR = 1, job on schedule
35
Sequencing Jobs Through One Process
Flow time (completion time) Time for a job to flow through system Makespan Time for a group of jobs to be completed Tardiness Difference between a late job’s due date and its completion time
36
Simple Sequencing Rules
PROCESSING DUE JOB TIME DATE A 5 10 B 10 15 C 2 5 D 8 12 E 6 8
37
Simple Sequencing Rules: FCFS
A B C D E Total Average /5 = /5 = 9.6 FCFS START PROCESSING COMPLETION DUE SEQUENCE TIME TIME TIME DATE TARDINESS
38
Simple Sequencing Rules: DDATE
B Total Average 75/5 = /5 = 5.6 DDATE START PROCESSING COMPLETION DUE SEQUENCE TIME TIME TIME DATE TARDINESS
39
Simple Sequencing Rules: SLACK
B (15-0) – 10 = 5 C (5-0) – 2 = 3 D (12-0) – 8 = 4 E (8-0) – 6 = 2 SLACK START PROCESSING COMPLETION DUE SEQUENCE TIME TIME TIME DATE TARDINESS E C D A B Total Average 82/5 = /5 = 6.8
40
Simple Sequencing Rules: SPT
SPT START PROCESSING COMPLETION DUE SEQUENCE TIME TIME TIME DATE TARDINESS C A E D B Total Average 74/5 = /5 = 6
41
Simple Sequencing Rules: Summary
AVERAGE AVERAGE NO. OF MAXIMUM RULE COMPLETION TIME TARDINESS JOBS TARDY TARDINESS FCFS DDATE SLACK SPT Best values
42
Sequencing Jobs Through Two Serial Process
Johnson’s Rule List time required to process each job at each process. Set up a one-dimensional matrix to represent desired sequence with # of slots equal to # of jobs. Select smallest processing time at either process. If that time is on process 1, put the job as near to beginning of sequence as possible. If smallest time occurs on process 2, put the job as near to the end of the sequence as possible. Remove job from list. Repeat steps 2-4 until all slots in matrix are filled and all jobs are sequenced.
43
Sequencing With Excel
44
Johnson’s Rule C E A B D JOB PROCESS 1 PROCESS 2 A 6 8 B 11 6 C 7 3
45
Johnson’s Rule A B C D E Completion time = 41 Idle time = 5+1+1+3=10 E
Process 1 (sanding) 5 11 20 31 38 Process 2 (painting) 15 23 30 37 41 Idle time Completion time = 41 Idle time = =10
46
Excel for Johnson’s Rule
User inputs processing times and sequence Excel calculates completion times and makespan When the set of jobs is completed
47
Guidelines for Selecting a Sequencing Rule
SPT most useful when shop is highly congested Use SLACK for periods of normal activity Use DDATE when only small tardiness values can be tolerated Use LPT if subcontracting is anticipated Use FCFS when operating at low-capacity levels Do not use SPT to sequence jobs that have to be assembled with other jobs at a later date
48
Monitoring Work package Shop paperwork that travels with a job
Gantt Chart Shows both planned and completed activities against a time scale Input/Output Control Monitors the input and output from each work center
49
Gantt Chart 1 2 3 4 5 6 8 9 10 11 12 Days Today’s Date Job 32B Job 23C
Job 12A Facility Key: Planned activity Completed activity Behind schedule Ahead of schedule On schedule
50
Input/Output Control PERIOD 1 2 3 4 TOTAL
Planned input Actual input Deviation Planned output Actual output Backlog 30 PERIOD TOTAL
51
Input/Output Control PERIOD 1 2 3 4 TOTAL
Planned input Actual input Deviation Planned output Actual output Deviation Backlog PERIOD TOTAL
52
Excel for Input/Output Control
User inputs planned and actual values Excel calculates deviations and backlog
53
Advanced Planning and Scheduling Systems
Infinite scheduling - assumes infinite capacity Loads without regard to capacity Then levels the load and sequences jobs Finite scheduling - assumes finite (limited) capacity Sequences jobs as part of the loading decision Resources are never loaded beyond capacity
54
Advanced Planning and Scheduling Systems
Advanced planning and scheduling (APS) Add-ins to ERP systems Constraint-based programming (CBP) identifies a solution space and evaluates alternatives Genetic algorithms based on natural selection properties of genetics Manufacturing execution system (MES) monitors status, usage, availability, quality
55
Advanced Planning and Scheduling
56
Theory of Constraints Not all resources are used evenly
Finite scheduling approach Concentrate on the” bottleneck” resource Synchronize flow through the bottleneck Use process and transfer batch sizes to move product through facility
57
Drum-Buffer-Rope Drum Buffer Rope
Bottleneck, beating to set the pace of production for the rest of the system Buffer Inventory placed in front of the bottleneck to ensure it is always kept busy Determines output or throughput of the system Rope Communication signal; tells processes upstream when they should begin production
58
Synchronous Manufacturing
B A C D B B B C C C D D D Item i Key: i Ij k l Operation j of item i performed at machine center k takes l minutes to process
59
Synchronous Manufacturing
Demand = 100 A’s Machine setup time = 60 minutes MACHINE 1 MACHINE 2 MACHINE 3 B1 5 B2 3 C1 2 B3 7 C3 15 D3 5 C2 10 D2 8 D1 10 Sum * 17 * Bottleneck
60
Synchronous Manufacturing
Machine 1 Machine 3 Setup Completion time 1002 2322 12 2732 200 1260 1940 2737 C2 B1 B3 C3 B2 D2 C1 D1 D3 Idle 1562 1512 1872 Machine 2 2
61
Employee Scheduling Labor is very flexible resource
Scheduling workforce is complicated, repetitive task Assignment method can be used Heuristics are commonly used
62
Employee Scheduling Heuristic
Let N = no. of workers available Di = demand for workers on day i X = day working O = day off Assign the first N - D1 workers day 1 off. Assign the next N - D2 workers day 2 off. Continue in a similar manner until all days are have been scheduled If number of workdays for full time employee < 5, assign remaining workdays so consecutive days off are possible Assign any remaining work to part-time employees If consecutive days off are desired, consider switching schedules among days with the same demand requirements
63
Employee Scheduling DAY OF WEEK M T W TH F SA SU MIN NO. OF
WORKERS REQUIRED Taylor Smith Simpson Allen Dickerson
64
Employee Scheduling DAY OF WEEK M T W TH F SA SU MIN NO. OF WORKERS REQUIRED Taylor O X X O X X X Smith O X X O X X X Simpson X O X X O X X Allen X O X X X X O Dickerson X X O X X X O Completed schedule satisfies requirements but has no consecutive days off
65
Employee Scheduling DAY OF WEEK M T W TH F SA SU MIN NO. OF WORKERS REQUIRED Taylor O O X X X X X Smith O O X X X X X Simpson X X O O X X X Allen X X X O X X O Dickerson X X X X O X O Revised schedule satisfies requirements with consecutive days off for most employees
66
End of Lecture 20
Similar presentations
© 2024 SlidePlayer.com. Inc.
All rights reserved.