Download presentation
Presentation is loading. Please wait.
Published byMarjorie Rice Modified over 9 years ago
1
Mod 0273: Governance of Feasibility Study Requests to Support Changes to Network Exit Agreements – National Grid NTS Response
2
Mod 0273 Overview Raised by E.ON UK Focuses on Feasibility Studies required to change max flow / ramp rate changes to NTS NExAs, NTS new connections & DN equivalent processes No published timescales for completion of Feasibility Study or associated Agreement No indicative costs published Proposes CUSC style formal timescales & costs to introduce: 3 month turnaround of Feasibility Study Fixed costs (with option for users to opt for later reconciliation) Proposed benefits are: Improved transparency Greater competition via increased flow rates
3
NG NTS Initial Views There is confusion over the electricity model deployed The 3 month Connection and Use of System Code (CUSC) Modification Application process employed in electricity does not include a feasibility/engineering study Feasibility Study fees are not published in electricity The gas process needs to be fully understood In comparison to electricity, the number of new connections and Network Exit Agreement (NExA) changes are relatively few. Receiving quite a few enquiries in a relatively short period can cause workload planning difficulties. The timescales in gas vary considerably depending on the complexity of the customer requirements/installation Feasibility and Conceptual Design Studies are important as they are undertaken to meet legislative obligations
4
Electricity New Connections & Modifications - CUSC Process A ‘Feasibility Study’ is typically undertaken to help determine the best location for a new connection - limited usage, unregulated service, costs are recovered, no delivery SLA Fees (fixed & indicative) published for New Connections & Modifications but Feasibility Study costs are not published Application process ‘clock starts’ when all documentation is received/approved & funds have been paid Offer timescales: 28 days – 3 months Feasibility Study Formal application & Payment cleared Clock StartOffer Made Design Stage Acceptance (Optional) 3 Months Up to 6 months but no SLA
5
Gas Exit Connection Processes For New Connections an indicative 20 week turn-around is published Flexibility – the studies undertaken are tailored to suit the particular customer requirements The costs/timescales of the analysis conducted is calculated accordingly Typical study timescales and costs: CharacteristicTimescaleCost Simple changes/minimum connections3-6 months£10k to £50K Semi complex changes/medium size connections6-12 months£50K+ Complex changes/large connections12 months+£100K+
6
Why is it important we conduct studies? Rapid load changes during start up and shutdown could affect the efficient and effective operation of the pipeline system Trigger safety devices and cut off supply at the installation Cause damage to National Grid equipment at installations such as pressure regulators, filters and orifice plate meters Adversely affect other Users of the system (entry and exit points) in the vicinity Legislation Health and Safety at Work Act etc. 1974 Pressure Systems Safety Regulations (PSSR) 2000 Pipeline Safety Regulations (PSR) 1996
7
What is involved in conducting a study? Influencing factors: Customers don’t always know what they want! Customers often experience difficulties in providing the information requested Difficulties in agreeing Contractual terms (between Customer and NG) Nature of the study Contractor Procurement process Workload planning – NG and Contractors
Similar presentations
© 2025 SlidePlayer.com. Inc.
All rights reserved.