Wisler Pierre-Louis, P.E., LEED AP BD+C, CFM, PMP Public Works Director Public Works Department
2
Mission Statement Enhance the quality of life, health and safety of all residents by rendering proper and efficient sanitation, street, water, sewer, stormwater, fleet management, facilities maintenance and right-of-way maintenance services.
3
Organization North Miami 10 sq. mi., NE Miami-Dade 60,000 residents Service Area 90,000 residents 22,000 connections Staffing 500 employees city-wide 150 employees in PWD
4
City Limits and Service Area
6
Winson Water Treatment Plant
7
Winson WTP Upgrades Well Rehabilitation Filter Rehabilitation WTP Improvements Accelator Sludge Basin Clearwell New Administration Building Transfer and High Service Pumps New Storage Tanks
8
Well Rehabilitation Winson WTP Upgrades
9
Awards
10
FSAWWA Region VII – Best Tasting Drinking Water 2014 – 1 st Place 2013 – 1 st Place 2009 – 1 st Place FSAWWA State Drop Savers Poster Contest 2014, Division 5 – 3 rd Place Awards
11
Miami-Dade County Consent Decree Sewer Overflow Response Plan Information Management System Program Sewer System Asset Management Plan Gravity Sewer System O&M Program Pump Station Operations & Preventative Maintenance Program Force Main Operations & Preventative Maintenance and Assessment/Rehabilitation Program
12
Recently Completed Projects Biscayne Blvd. Force Main Project NE 131 st ST Force Main Project NW 2 nd AVE Force Main Project
13
Biscayne Blvd. Force Main Project 7,000 LF of 12-inch DIP Contractor: JVA Engineering Contractor, Inc. Engineer: EAC Consulting, Inc. Cost: $1,586,000 Start: 8/2014 End: 3/2015
14
Biscayne Blvd. Force Main Project
15
NE 131 ST Force Main Project 3,100 LF of 16-inch DIP Contractor: Roadway Construction, LLC. Engineer: Kimley-Horn and Associates Cost: $694,000 Start: 9/2014 End: 6/2015
16
NE 131 ST Force Main Project
17
NW 2 AVE Force Main Project 1,600 LF of 10-inch DIP Contractor: Roadway Construction, LLC. Engineer: Kimley-Horn and Associates Cost: $375,000 Start: 10/2014 End: 6/2015
18
NW 2 AVE Force Main Project
19
Projects in Design NE 6 AVE Water Main NE 16 AVE Water Main Hospital Pump Station San Souci 1 Pump Station San Souci 3 Pump Station
20
Sanitary Sewer Lining and Rehabilitation Upcoming Projects
21
THANK YOU!