Jason J. Siwula, PE – Safety Engineer HSIP HORIZONTAL ALIGNMENT SIGNING
2
Horizontal Alignment Signing Initiative Systemic Approach to installing Horizontal Alignment Signage (HAS) Install HAS utilizing fluorescent yellow sheeting along the entire corridor where one RD Plan “enhanced” curve is located for consistency and uniformity Target approximately 25% of the state maintained system over the five year implementation schedule
3
HSIP Signage Corridors Phase 1 (mi)Phase 2 (mi)Phase 3 (mi)Phase 4 (mi)Phase 5 (mi)Totals (mi) District 185.59888.40686.02190.357106.058456.440 District 2101.510105.830107.518105.608114.239534.705 District 3106.779102.47499.990102.915101.938514.096 District 4116.392118.597121.106143.884123.153623.132 District 587.80783.49683.60586.37384.213425.494 District 6154.051158.707151.167151.63894.673710.236 District 7188.805168.010173.733180.506201.535912.589 District 885.89490.88293.97193.85498.987463.588 District 993.97091.55197.08399.39382.237464.234 District 10111.431112.999118.094115.83795.508553.869 District 1194.70499.324127.069119.111104.197544.405 District 12127.136139.618132.801140.867137.102677.524 Grand Total:6880.312
4
Why Horizontal Alignment Signs? Reduction in Lane Departure crashes 2009 MUTCD Signing Changes 2009 MUTCD Compliance Date Driver expectation Benefit / Cost
5
Source: http://cmfclearinghouse.orghttp://cmfclearinghouse.org Crash Modification Factors for Fluorescent Curve Signs
6
Examples of Signage Updates Previously Existing Signing2009 MUTCD Signing Update
7
Many of the 2009 MUTCD Compliance Dates have been revised or eliminated, however, the compliance date for Horizontal Alignment Signing remains in place. MUTCD Compliance Date – December 31, 2019
8
Driver Expectations Along a Corridor
15
Bottom line – Many sites can be implemented with a relatively low cost for a significant benefit! *B/C Source: FHWA-HRT-09-045 Benefit / Cost Ratio between 8.6-102.3
16
A New Approach Contract with a consultant to supplement Traffic Engineering functions Ball Bank Indications Setting of advisory speeds Approximate sign placement Quantities for letting projects
17
Selected Consultants
18
Example Signing Layouts Non-Enhanced Curves or Turns Enhanced Curves or Turns
19
Current Status Contracts with all consultants have been authorized 11/26/2012 Horizontal Alignment Signing / Ball Bank Training Class (1 st scheduled for December 18, 2012) “Boots on the ground” starting near the first of the year
20
Next Steps Review initial corridor submissions from each consultant Meet with the Districts to discuss implementation through the Construction Procurement process (inspection, quality control, etc.) Let construction contract(s) for several corridors to ensure the quality of the end product Adjust the process as necessary for implementation and complete Phase 1 and Phase 2.
21
Questions?