TB 18.5.06 Peter Glässel, Heidelberg1 TPC Status Report Project leader: Peter Braun-Munzinger, GSI Darmstadt Deputy project leader: Johanna Stachel, Heidelberg Technical coordinator: Peter Glässel, Heidelberg
2
TB 18.5.06 Peter Glässel, Heidelberg2 Outline Preparations for pre-commissioning Pre-commissioning has started Gas system Laser system First events Pre-commissioning objectives and plan
3
TB 18.5.06 Peter Glässel, Heidelberg3 FE Cards Installation 2/2 FEE testing, round 2 ‘Dry’ sector tests completed (FEE only, no HV)
4
TB 18.5.06 Peter Glässel, Heidelberg4 Completion of installation Lots of details: LV bus bars Water cooling ROC bodies Water cooling FEC’s (about 10.000 pieces) Grounding bars, ground connections Gas manifold Distribution panels and boxes (15 cables/sector) ongoing, C-side nearly done Pt1000 (about 400) …. Temporary installations for pre-commissioning LV for 2 sectors Cooling DAQ DCS Fire alarm ….
5
TB 18.5.06 Peter Glässel, Heidelberg5 Work at C-Side, now with scaffolds
6
TB 18.5.06 Peter Glässel, Heidelberg6 Gas system Software upgrade Re-commissioning with new gas lines (via plug) with dummy volumes Connected to TPC since 24.4.06, flushing with CO 2 Filling with Ne since 28.4. Final mixture since last weekend O 2 150 ppm purification not yet operational Control Backup Mixer Purifier CO2 Distr Analys Pump
7
TB 18.5.06 Peter Glässel, Heidelberg7 Pressure history
8
TB 18.5.06 Peter Glässel, Heidelberg8 Laser system Laser arrived 27.4.06, works Partial alignment of A-side optics (2 laser rods of 6) done last weekend Laser in clean room Laser optics box and cable channel
9
TB 18.5.06 Peter Glässel, Heidelberg9 100 kV Drift Voltage System UPS Interlocks and DCS functionality tested 100 kV test 10.5.06: ok 60 kV long term (10h) ok
10
TB 18.5.06 Peter Glässel, Heidelberg10 Pre-Commissioning plans Goal was to start with FEE/ROC mid May Commissioning of Field cage, FEE and ROCs (i) study 2 sectors thoroughly, about 2 weeks (ii) commission sector by sector @ 2 days/sector shift schedule Move to UX25: 4.9.06 Delphi frame is ‘moving cradle’ Detailed planning and preparations ongoing
11
TB 18.5.06 Peter Glässel, Heidelberg11 Sector 13 wired up RCU’s
12
TB 18.5.06 Peter Glässel, Heidelberg12 Cosmic tracks in OROC 13 Moderate gain: about 2 to 3000
13
TB 18.5.06 Peter Glässel, Heidelberg13 First Laser tracks in OROC 13
14
TB 18.5.06 Peter Glässel, Heidelberg14 The Team
15
TB 18.5.06 Peter Glässel, Heidelberg15 TPC Summary Gas system working, final gas mixture Pre-commissioning of FC, ROC, FEE started Move to UX2 Sep 06(?)
16
TB 18.5.06 Peter Glässel, Heidelberg16 -- Spares --
17
TB 18.5.06 Peter Glässel, Heidelberg17 Commissioning Objectives I Field cage gas tightness of all volumes VHV system ramp-up and down up to 100+ kV connection to DCS and DCS functionality test of UPS system ROC's turn on HV with gain 5000 (from database) evaluate gating grid functionality pulses with laser pulses with cosmics for 1st configuration (sector 4 and 13, i.e. top/bottom): measure gain and noise characteristics as function of HV evaluate dE/dx resolution characterization of drift volume: Efield, T,p dep. with tracks for 1 sector only: Kr gain calibration (establish procedures) full Kr calibration (if needed) when TPC is in the pit
18
TB 18.5.06 Peter Glässel, Heidelberg18 Commissioning Objectives I For all sectors: turn on HV until nominal gain 5000 measure gain and noise characteristics as fct of HV characterization of drift volume: E-field, T,p dep. with laser tracks Cooling system evaluate mechanical integrity (leak tightness) Gas system evaluate full functionality, connection to DCS, stability of pressure and mixture Goofy evaluate functionality and drift velocity (dT, dP corrections, mixture dependence Temperature sensors integration into DCS system correlation of temperature profile with measured FC characteristics Laser evaluate general functionality, stability, monitoring integration into DCS
19
TB 18.5.06 Peter Glässel, Heidelberg19 Commissioning Objectives II Front End Electronics Verification of the connection between FECs and ROC’s pad plane done during installation of the FECs by pulsing ROC’s cathode wires table with FEC identifier ↔ Detector location correspondence list of pads that are not connected to the FECs Measurement of electronic gain, width, noise and baseline of all channels (all sectors) done one sector at a time by pulsing ROC’s cathode wires database of gain, pedestals, pulse width, noise (4 values per channel) distributions of gain, pedestal and noise determine thresholds for zero suppression Global effects (characterization of few sectors) stability of pedestals (requires controlled cooling) characterization of the baseline oscillation induced by the gating grid
20
TB 18.5.06 Peter Glässel, Heidelberg20 Commissioning Objectives II Measurement of temperature, voltages and currents of all FECs (all sectors) determination of the threshods for the generation of the interlock signal (turning off the FEC) Characterization of the temperature, voltages and currents (few sectors) different running conditions (power on, with and w/o cooling, high trigger rate, various ALTRO settings)
21
TB 18.5.06 Peter Glässel, Heidelberg21 Commissioning Objectives III Readout Electronics and Backend Systems FEE Configuration Creation of a set of basic Configuration Files (black events, zero suppressionevents, readout path test, etc.) FEE Command Coder Configuration of FEE via DCS development of the supervisory layer completion of the field layer (DCS board) application integration of field layer, intercom layer and supervisory layer Configuration of FEE via DDL FEE monitoring via DCS development of the supervisory layer completion and test of the intercom layer and field layer application
22
TB 18.5.06 Peter Glässel, Heidelberg22 Commissioning Objectives III TPC Data Monitor review and integration of the various visual monitoring packages (MOOD, HLT, Expert Monitor, Offline) development of automated data quality monitor (what and where) Integration of FEE, ECS, DAQ, HLT, Trigger, Offline define standard run and calibration procedures and operations verify procedures for detection and recovery from errors (e.g. illegal trigger sequence)