1 New Building Construction Plan Neighborhood Briefing November 19, 2015 1

2 Agenda Construction phases Logistics Noise and Dust Communications 2

3 Construction Plan The New Building Construction Plan will be posted online. Meant to be used as a reference. Provides the details: Construction phases Logistics Noise and Dust Mitigation plans Chemical Treatment of Rock Schematics of Campus 3

4 New Building Construction Schedule Swing Space Construction:June 2015 – December 2015 Magnolia Move:November 17-19, 2015 Move to LeFrak CenterDecember 28 – January 18 Lehman Closure/Fencing:December 2015 – January 2016 Abatement and Demolition:January 2016 – May 2016 Excavation and Foundations:May 2016 – October 2016 Rock Excavation:June 2016 – September 2016 Steel Erection/Superstructure:November 2016 – March 2017 Exterior Wall:February 2017 – August 2017 Building Watertight:September 2017 Interior Finishes:May 2017 – April 2018 Temporary Certificate of Occupancy:May 2018 Furniture and Equipment:May 2018 – August 2018 Occupancy:August 2018 4

5 Key Construction Phases Abatement and Demolition: January 2016 – May 2016 Excavation and Foundation: May 2016 – October 2016 Structure: November 2016 – August 2017 Interior Fit Out: August 2017 – March 2018 5

6

7

8

9

10 Logistics Work Hours 8:00am – 4:00pm Monday through Friday May occasionally extend to 6:00pm to stay on schedule No deliveries after 10:00pm – consistent with current practice No construction during reading and finals periods Claremont Avenue Logistics hub – worker/truck/equipment entrance and exit One lane will be closed for pedestrian and vehicle access – loss of parking Continued access through 119 th Street entrance Campus Access Above ground, lit, covered, pedestrian walkway from Barnard to Altschul Hall Wheelchair accessible 10

11 Noise and Dust Mitigation Turner is doing everything it can to mitigate impact of noise and dust – beyond what is required by code. Noise will be at its worst during demolition and excavation between February and August. Rock excavation is scheduled for the summer months. No construction will take place during reading periods and finals. Third-party assessments underway: Assessment construction/mitigation plan; Evaluation of ambient conditions and recommendations for additional mitigation steps. Collaboration with Columbia’s Environmental Health and Safety experts. 11

12 Noise and Dust Mitigation Noise MitigationDust Mitigation Use of sound deadening blankets along construction fence and higher fence than required Sound mufflers on vehicles No truck idling on Claremont Pre-treated rock to help ease excavation Effort to move class times No construction during reading period and finals Barnard studying noise impacts for potential other mitigation efforts Fine mesh fencing around Lehman hall Covered windows during demolition Wetting – hose operation during demolition Truck wash-down stations during excavation/foundation period Gravel and stone gateways limit dust 12

13 Communications Ways to Stay Informed Opt in to receive email updates by sending name and building number to newbuilding@barnard.edu News and look-aheads of construction activities, updated regularly New building website available at www.barnard.edu/tlc @MillieBuilds twitter account for up to date information Signage posted on construction fence and distributed in affected apartment lobbies, as permitted Troubleshooting For urgent issues during regular work hours, email constructionteam@barnard.edu or call Barnard Facilities at 212/854-2041.constructionteam@barnard.edu For urgent issues during off hours, call Barnard Public Safety at 212-854-3362 For all other inquiries, email newbuilding@barnard.edu. You will receive a response promptly, often within 24 hours 13

14 Email updates 14

15 @MillieBuilds Twitter handle 15

16 Expanded construction website 16