Download presentation
Published byAileen Fisher Modified over 9 years ago
1
Overall National Grid Development: Constraints & Options
2
Index Recent developments in Power Sector Future Outlook
Constraints and Options a
3
Recent Developments in Power Sector
Rate of Generation capacity addition gone up multifold Installed capacity 115 GW (in 2005) 276 GW (in 2015) i.e, 161 GW added in 10 years (138%)
4
Recent Developments in Power Sector
Increased private participation in capacity addition Installed capacity by Private Sector 12 GW (in 2005) 105 GW (in 2015) i.e, 93 GW added in 10 years (775%) Capacity mostly merchant in nature; very few PPA signed (10%) (38%)
5
Recent Developments in Power Sector
Increased penetration of renewable capacity Installed capacity 2.5 GW (in 2005) 36 GW (in 2015) i.e, 33.5 GW added in 10 years (14 times)
6
Recent Developments in Power Sector
765 kV Becoming backbone of Indian Power Grid About 15,000 ckm added in last 5 years More than 30 S/S added in last 5 years
7
Recent Developments in Power Sector
All India Grid Synchronised One Nation – One Grid One of the largest grids in the world Generation Capacity: 274 GW Demand: >1000 BU Transmission: ,09,116 ckm; 5,72,405 MVA (Transf. Capacity)
8
Recent Developments in Power Sector
Existing I-R Capacity 51,650MW One of the Largest Electricity Grids operating at single frequency in the world August 2006 North synchronized with Central Grid One Nation One Grid One Frequency NEW* Grid South Grid March 2003 West synchronized With East & North-East Dec’2013 South synchronized with NEW Grid Central Grid October 1991 East & North-East synchronized * North East West S W N E NE Five Regional Grids Five Frequencies 8
9
Recent Developments in Power Sector
500 MW HVDC interconnection with Bangladesh commissioned
10
Recent developments in Power Sector Vibrant Electricity Market
~ 8 p.u. ~ < 3 p.u. 10 Optimal Utilization of Resources through IR Exchanges and STOA Development of Vibrant Electricity Market Reduction in per unit energy charges
11
Recent Developments in Power Sector
Congestion being experienced in few corridors inspite of the fact, since 2005 34,000 ckm, 63 s/s & 1,19,055 MVA added by POWERGRID Inter regional capacity: increased from 24,000 MW to 51,650 MW
12
Future Outlook 24x7 Power for All
Increasing Per Capita Electricity Consumption Increasing penetration of renewable capacity: 175 GW by 2022 Seamless SAARC Power Grid
13
Transmission Addition
Future Outlook Transmission Addition 12th Plan 1,07,000 ckm 2,88,000 MVA Green Energy Corridors 11 high capacity corridors 2 nos of 800 kV HVDC Rs. 1,80,000 crore 13th Plan 1,30,000 ckm 3,00,000 MVA Green Energy Corridor-II Rs. 2,00,000 crore
14
National Grid – Present and Envisaged
NR Present IR Capacity: 51,650 MW Figures do not include 600MW (in aggregate) pertaining to various 132kV 15,830MW NER ER SR 5,720MW 3,630MW 10,690MW 2,860MW 12,920MW WR Planned IR Capacity by XII Plan end: 72,250 MW 17,930MW 16,920MW 12,790MW 7,920 MW 7,830MW Envisaged (Cumulative) by Mar’17 Existing 6,000 MW Present & Targeted IR Capacity include Pvt. Sector lines also
15
High Capacity Transmission Corridors
16
Constraints and Options
17
Major Constraints & Options
Right of Way Increasing voltage level EHVAC : 765kV 1200kV HVDC : 500kV 800kV (Multi-terminal) Multi Circuit lines High capacity lines Application of FACTS Compact tower, narrow base tower, pole structure Cable & VSC based HVDC Technology
18
Major Constraints & Options
Substation Land Acquisition Gas Insulated Switchgear (GIS) - Make in India Automation of substation
19
Integration of RE capacity-Options
Strong interconnections to sustain variability Development of Green Energy Corridors – I & II Transmission to precede generation Dynamic control system – STATCOM, SVC Renewable Generation Forecasting, Renewable Energy Management Centre (REMC) Provision of balancing reserves Availability of quick ramping capacities like, Pumped storage, hydro, gas based generation, etc.
20
Uncoordinated Development of Capacity Addition
Uncertainty in generation addition Eastern Region: 14,000 MW delayed Southern Region: 10,000 MW delayed No firm beneficiaries – lack of PPAs Increased share of merchant power Skewed power flow due to market forces
21
Options Co-ordinated National Effort for development of Transmission, Generation & Load Assessment of load by each state , Co-ordinated planning and implementation in a collaborative Manner – General Network Access (GNA) Transmission to Lead Generation Creation of Energy Highways, according to load growth envisaged for each state 3 high capacity HVDC lines (6000 MW each) under construction
22
Constraints & Options Options Very large grid
Real time monitoring with self healing feature Smart Grid application - Wide Area Measurement System (WAMS) : 1740 PMU, Robust communication Controlled features like SVC, STATCOM, FACTS, Phase shifters, etc. Grid Management Very large grid 2nd largest in the world 4 lac ckm upto 220 kV All types of technology – 400kV, 765kV, HVDC Increased penetration of renewable: 14% -> 30%
23
Thank You
24
Southern Region Inter Regional Capacity
Raigarh 6000MW Wardha 4200MW Talcher 2500MW Chandrapur Angul 4200MW Balimela Kolhapur Sholapur 130MW 4200MW 1000MW Gazuwaka 1000MW 260MW Upper Sileru Nizamabad Ponda 2200MW Srikakulam Raichur 260MW Belgaum Southern Region Inter Regional Capacity Nagajhari Narendra Kolar Pugalur
Similar presentations
© 2025 SlidePlayer.com. Inc.
All rights reserved.