TC meeting P2 planning wks 9&10 A.Tauro 28-2-2012
2
Planning wk9 DSO test: no access UX25 on Thu 1 st Mar (and on 2 nd, as a reserve) PH-DT (gas-group): upgrade of the PLC and PVSS codes. The intervention will last about 8 hours Mon 27th TPC laser (start on Wed PM) SPD cooling drill SR7 on Mon Transport + P2tech: PX24 plug (small blocks, Mon) Close hole in MNF shielding (Tue) Restart L3 and Dipole cooling (test on Tue between 10:00 and 12:00) Removal A.C. from CR2 (Thu) MTG: restart isobuthane (Tue) HMP: restart methane (Tue) Muon TRK: –Repair slats on ST3-ST4-ST5 BE-ABP-SU: survey ST3-4-5 and network measurement with new instrument. Scan L3+MNF from low-beta (if possible) EN-CV: install and commissioning new PMD ventilator unit EN-CV-DC: finalize TPC-RR filters installation and SSD-SDD ramp-up 28/2/12TC meeting - A.Tauro
3
Planning wk10 SPD cooling P2tech: reinstall green fences C-side Muon TRK: –Repair slats on ST3-ST4-ST5 Move PMD to final position (Mon) Reinstall ADA BE-ABP-SU: PMD survey (Tue) EN-HE: removal crane electronics (Fri) EN-CV-BE: start-up and commissioning new ITS dehumidifier (5 th Mar) TE-VSC: open manual valve in MNF (Fri) T0: check electronics (9 to 12/3) ONET: cleaning UX25 cavern INEO: install 220V sockets in backframe (Tue) and miniframe (Wed) 28/2/12TC meeting - A.Tauro
4
AOB Confined training course tomorrow, Wednesday, at 9:00 at P2 –See with Fernando if you are interested to follow the course 28/2/12TC meeting - A.Tauro
Similar presentations
© 2025 SlidePlayer.com. Inc.
All rights reserved.