ISPA Measure 2002 BG 16 P PE 016 Varna Integrated Water Project Transformationof Transformation of WWTP Asparuhovo Reconstruction of WWTP Varna ReconstructionofWS& S Network Reconstruction of WS & S Network
2
PROJECT OVERVIEW FM Budget25,432,000.00 € FM Budget25,432,000.00 € Total contracted26,725,049.00 € Total contracted26,725,049.00 € –ISPA22,438,740.50 € –National Co-financing16,829,055.38 € –Additional National Funding4,286,308.50 € Total paid20,564,663.23 € Total paid20,564,663.23 € Financial Implementation 77,00% Financial Implementation 77,00% (Total paid/Total contracted) (Total paid/Total contracted) Financial Implementation 88,23% Financial Implementation 88,23% (Total paid of contracted FM budget/Total FM budget) (Total paid of contracted FM budget/Total FM budget) ISPA Measure 2002 BG 16 P PE 016 Varna Integrated Water Project
3
Works Contract 1 Transformation of WWTP Asparuhovo into pumping station and construction of transfer pipeline Commencement Date: 14 th February 2008 Commencement Date: 14 th February 2008 Taking Over Certificate: 6 th December 2011 Taking Over Certificate: 6 th December 2011 Physical Execution:100 % Physical Execution:100 % Financial Execution: 72 % Financial Execution: 72 %
4
Transformation of WWTP Asparuhovo into pumping station and construction of transfer pipeline into pumping station and construction of transfer pipeline Technologicalscheme Technological scheme
5
Transformation of WWTP Asparuhovo into pumping station and construction of transfer pipeline Balancing Tanks
6
Transformation of WWTP Asparuhovo into pumping station and construction of transfer pipeline Fine Screens Equipment Screeningbuilding Screening building
7
Transformation of WWTP Asparuhovo into pumping station and construction of transfer pipeline Gridtank Grid tank Pumpingstation Pumping station
8
Transformation of WWTP Asparuhovo into pumping station and construction of transfer pipeline into pumping station and construction of transfer pipelinePublicity Commemorativeplaque Commemorative plaque
9
Transformation of WWTP Asparuhovo into pumping station and construction of transfer pipeline Inaugurationceremony Inauguration ceremony
10
Transformation of WWTP Asparuhovo Contract 1- closed Commencement Date: 17 th January 2008 Commencement Date: 17 th January 2008 Completion Date: 15 th February 2011 Completion Date: 15 th February 2011 Contract 2- closed Commencement Date: 16 th February 2011 Commencement Date: 16 th February 2011 Completion Date: 15 th August 2012 Completion Date: 15 th August 2012 Contract 3 – under implementation Commencement Date: 16 th August 2012Commencement Date: 16 th August 2012 Completion Date: 15 th April 2013 Completion Date: 15 th April 2013 Financial Execution: 40 % Financial Execution: 40 % SupervisionContracts Supervision Contracts
11
Commencement Date:17 th January 2009Commencement Date:17 th January 2009 Taking Over Certificate: 4 th November 2011Taking Over Certificate: 4 th November 2011 Physical Execution:100 %Physical Execution:100 % Financial Execution: 97 %Financial Execution: 97 % The DNP is expected to expire on 20 th February 2013The DNP is expected to expire on 20 th February 2013 Works Contract 2 Reconstruction and modernization of WWTP Varna
12
Reconstruction and modernization of WWTP Varna Aerationtanks Aeration tanks
13
Reconstruction and modernization of WWTP Varna Blowers Building MCC
14
Reconstruction and modernization of WWTP Varna Methane Tanks
15
Reconstruction and modernization of WWTP Varna Utilizationofbiogas Utilization of biogas Gasholder
16
Reconstruction and modernization of WWTP Varna Commemorativeplaque Commemorative plaque
17
Reconstruction and modernization of WWTP Varna Publicity Inaugurationceremony Inauguration ceremony
18
Supervision Contracts Contract 1 - closed Commencement Date:10 th January 2009 Commencement Date:10 th January 2009 Completion Date:9 th February 2012 Completion Date:9 th February 2012 Financial Execution:99,7 % Financial Execution:99,7 % Contract 2 – under implementation Commencement Date:15 th May 2012 Commencement Date:15 th May 2012 Completion Date:15 th June 2013 Completion Date:15 th June 2013 Financial Execution:30 % Financial Execution:30 % Reconstruction of WWTP Varna
19
Commencement Date:25 th May 2009 Commencement Date:25 th May 2009 Taking Over certificate:21 st September 2010 Taking Over certificate:21 st September 2010 Performance Certificate: 21 st September 2011 Performance Certificate: 21 st September 2011 Contract is closed Contract is closed Works Contract 3 Reconstruction of WS & S Network
20
Commemorativeplaque Commemorative plaque
21
Supervision Contract Commencement Date:27 th April 2009 Commencement Date:27 th April 2009 Completion Date:26 th October 2011 Completion Date:26 th October 2011 Contract is closed Contract is closed Reconstruction of WS & S Network
22
Compliance with Article 8 of the Financing Memorandum Art. 8.4. a) The condition in the article is considered fulfilled- DG REGIO letter Ares 822987/28.07.2011 The condition in the article is considered fulfilled- DG REGIO letter Ares 822987/28.07.2011. Art. 8.4. b) Art. 8.4. b) The condition in the article is considered fulfilled- DG REGIO letter 08874/21.09.2006 The condition in the article is considered fulfilled- DG REGIO letter 08874/21.09.2006. Art. 8.4. c) The Master Plan is prepared. The Report to be submitted to the EC for approval. All other conditions under Article 8 of the FM are considered fulfilled.