VC117 February 2009Jean-Sébastien GraulichSlide 1 MOM Report o Yagmur Torun ( June 15 - July 14) o J.S. Graulich ( July 13 - August 7) Jean-Sebastien Graulich,

Similar presentations


Presentation on theme: "VC117 February 2009Jean-Sébastien GraulichSlide 1 MOM Report o Yagmur Torun ( June 15 - July 14) o J.S. Graulich ( July 13 - August 7) Jean-Sebastien Graulich,"— Presentation transcript:

1 VC117 February 2009Jean-Sébastien GraulichSlide 1 MOM Report o Yagmur Torun ( June 15 - July 14) o J.S. Graulich ( July 13 - August 7) Jean-Sebastien Graulich, Geneva

2 Summary  Encouraging and visible progress in the hall Air conditioning operational DK Solenoid cool down started Electrical Installation Painting Magnet cooling water on. Soak test scheduled for next week TOF1, KL and BPM back in place  One Big Question Will the target be ready in time  One focus point ISIS shut down: August 13 to September 15 Not much more to say So I have included many pictures… VC117 February 2009Jean-Sébastien GraulichSlide 2

3 R78  I have tried to tidy up  Please Cooperate No more tools stored in the office Individual paper trays VC117 February 2009Jean-Sébastien GraulichSlide 3

4 Hall Progress  Electrical installation (see Andy’s talk) Nearly finished Fiat Lux VC117 February 2009Jean-Sébastien GraulichSlide 4

5 Hall Progress  Painting Mainly finished Hall clean and shiny VC117 February 2009Jean-Sébastien GraulichSlide 5

6 DK Solenoid  Cool down in progress (See Mike’s talk) VC117 February 2009Jean-Sébastien GraulichSlide 6 Transfer line repaired Cooling faster than in April Pierrick provided an EPICS app to ease the readings

7 Detectors  Back in place Still have to be aligned KL offset by 20 cm due to the moving platform VC117 February 2009Jean-Sébastien GraulichSlide 7 TOF1 KL BPM1 BPM2

8 Magnets  Water to the downstream magnets ON One leak on Q9 had to be fixed (pressure regulator valve)  Chillers tend to go on Alarm Just because we are not enough demanding (no heat load)  Marco Apollonio is preparing for soak test VC117 February 2009Jean-Sébastien GraulichSlide 8 Water flow is stable Hall Probe Re-discovered in R76

9 Target  Shafts manufactured To be welded and coated  Power electronics upgraded New fibers pulled to MLCR  The decision to install it or not will be taken on Aug 20 VC117 February 2009Jean-Sébastien GraulichSlide 9

10 Controls  Pierrick is working hard to include the CAEN HV power supplies in EPICS VC117 February 2009Jean-Sébastien GraulichSlide 10

11 Conclusion VC117 February 2009Jean-Sébastien GraulichSlide 11  We are approaching the end Don’t stop now…


Download ppt "VC117 February 2009Jean-Sébastien GraulichSlide 1 MOM Report o Yagmur Torun ( June 15 - July 14) o J.S. Graulich ( July 13 - August 7) Jean-Sebastien Graulich,"