1 In Partnership with Palangoy Gospel Chapel ETWF Church and Training Centre

2 Contract Signing 31 AUG 2011 Insurance Bond / Building Permit Clearing of Site (Ground Breaking) Temporary Fence, Shelters and Stockroom 50% Building Structure 80% Building Structure 100% Building Structure 23 MAY 2012 Completion of Maintenance Period 50% Building = Second Storey + Roof Frame Structure 80% Building = Roof + Tiles + Painting Structure 100% Building = Fully Completed + TOP Structure

3 EXPENSES - TAYUMAN PROJECT (August 2011 - ) DateDetail Ph Pesos Balance 30-Aug-11Building Permit Fees43,572.2010,956,427.80 1-Sep-11Claim Form 1100,000.0010,856,427.80 7-Sep-11Claim Form 2300,000.0010,556,427.80 12-Sep-11Claim Form 3800,000.009,756,427.80 20-Sep-11Claim Form 4800,000.008,956,427.80 29-Sep-11Claim Form 5800,000.008,156,427.80 30-Sep-11Edgar's Salary - September 201111,000.008,145,427.80 7-Oct-11Claim Form 6800,000.007,345,427.80 20-Oct-11Claim Form 71,400,000.005,945,427.80 30-Oct-11Edgar's Salary - October 201113,750.005,931,677.80 30-Nov-11Edgar's Salary - November 201112,000.005,919,677.80 10-Dec-11Claim Form 81,000,000.004,919,677.80 2-Jan-12Edgar's Salary - December 201112,000.004,907,677.80 6-Jan-12Claim Form 91,000,000.003,907,677.80 1-Feb-12Edgar's Salary - January 201212,000.003,895,677.80 20-Feb-12Claim Form 101,000,000.002,895,677.80 1-Mar-12Edgar's Salary - February 201212,000.002,883,677.80 24-Mar-12Claim Form 111,000,000.001,883,677.80 1-Apr-12Edgar's Salary - March 201212,000.001,871,677.80 1-May-12Edgar's Salary - April 201210,500.001,861,177.80 18-May-12Viewtech Wall Screen6,160.001,855,017.80 23-May-12Claim Form 12643,197.001,211,820.80 26-May-12Import Permit for Chairs15,000.001,196,820.80 Total 9,803,179.20 1,196,820.80

4 BUILDING FUND (April 2012 ) DateDetail Sin $ Balance 14-Jan-12 Philippines Building Fund (Target: $350,000.00) 350,000.00 LESS REMITTANCES: 15-Aug-11(1) Building Cost85,964.89264,035.11 22-Aug-11(2) Building Cost86,087.90177,947.21 4-Nov-11(3) Building Cost88,893.8989,053.32 20-Mar-12(4) Building Cost59,612.5229,440.80 TBD(5) Furnishing Cost (PA System and Chairs)29,440.80 PA System $23,508.00 Chairs $ 5,932.80 Total $29,440.80

5

6 BAPTISMAL POOL - SIDE

7 BAPTISMAL POOL - FRONT

8 FIRST FLOOR LADIES TOILET

9 FIRST FLOOR KITCHEN

10 SECOND FLOOR KITCHEN

11 MASTER ROOM WARDROBE

12 CONFERENCE ROOM 1 WARDROBE

13 MAIN SPEAKER LEFT MAIN SPEAKER RIGHT CEILING MOUNT PROJECTOR PULL DWN SCREEN STAGE MONITOR LEFTSTAGE MONITOR RIGHT SUB-WOOFER SANCTUARY STAGE

14 RAVIVICTOR

15 ETWF MEMBERS WITH DEACON FRANCIS AND DEACONESS KATHY

16 CHECKING OUT THE AUDIO SYSTEM

17

18 PRAYER Items: 1. Thanksgiving for providing funds, 2. Salvation of Construction Workers, 3. Good Working Relationship, 4.Safe arrival of 300 Chairs, 5. Built Within Budget, 6.Smooth Handover, 7. Thanksgiving.