Inland Navigation - A National Perspective Jim Walker USACE, Headquarters November 8, 2007
2
Navigation Program Almost 1100 Congressionally authorized and constructed navigation projects 27 inland navigation systems 237 Navigation locks Aging infrastructure Funding — Annual Operation and Maintenance — Non-routine Maintenance
3
Navigation Program Reliable Inland River Systems Lock Availability — Scheduled and Unscheduled Lock Closures Channel Availability — Depth and Width
4
Reliability – Navigation Locks Navigation Lock Unavailability, 1991-2005 Total Hours Scheduled vs. Unscheduled without Ice
5
Lock Reliability Corps wide Navigation Lock condition assessment Prioritized list of maintenance needs Reliability Goal — Unscheduled lock closures — Five Year Development Plan: less than 20,000 hours of unscheduled closures — FY09 pursue first year of incremental improvement
6
Channel Availability - Coastal Initial effort: Projects with greater than 10M tons per year Establish Performance Standard Determine channel availability trend — FY 2005, 2006, 2007 — Five Year Development Plans — FY 2009 Improvement Increment
7
Channel Availability - Coastal Channel Cross Section Depth at Centerline (CL) Depth at Channel Toe Depth at Quarter Points CL Toe Qtr Pt Advanced Maintenance Allowable Overdepth Qtr Pt Toe
8
Channel Availability - Coastal Level of Service Standard — Full project depth — Half project width, 95% of the time Channel availability trend — FY 2005: 38% — FY 2006: 35% — FY 2009 – 2013: get to 95% — FY 2009 Improvement Increment
9
Future Direction RAMP Risk Informed Asset Management Performance
10
RAMP RISK Categories Structural Operational Life Safety Economic Environmental Security
11
RAMP ASSET MANAGEMENT Maintenance Management Use for Repair, Rehab, Replace, Retire decision FEM is the Corps system Deploying in 2008-09
12
RAMP PERFORMANCE Tonnage Performance Standard Funding — Achieve appropriate levels of risk — Achieve level of performance Report what we are able to accomplish with the funds provided Transparent process – stakeholders, public, Congress
13
Future Direction Method needs to be easy to explain and understand Administration – OMB Economists Congress American Public America’s Infrastructure must become a National priority
14
RAMP OMB Feedback Concur with the approach Performance measure agreement Data collection and reporting underway Improve OMB PART rating from current ‘Results Not Demonstrated’
15
Where We Are Nav Lock High Performing Operation (HPO) 85% of Inland Navigation expended on annual operation and maintenance HPO to evaluate effectiveness and efficiency Performance Work Statement to be released for public review and comment in Nov/Dec www.navlocks- hpo.usace.army.mil/HPO_System.htm
16
Conclusion The Bottom Lines Investing in the Navigation system is investing in economic development America’s Infrastructure must become a National priority