Presentation is loading. Please wait.

Presentation is loading. Please wait.

Fermilab 1 SNUMI Civil Issues September 18, 2006Dixon Bogert SNUMI Civil Design & Site Considerations; Issues and FESS work Dixon Bogert SNUMI Meeting,

Similar presentations


Presentation on theme: "Fermilab 1 SNUMI Civil Issues September 18, 2006Dixon Bogert SNUMI Civil Design & Site Considerations; Issues and FESS work Dixon Bogert SNUMI Meeting,"— Presentation transcript:

1 Fermilab 1 SNUMI Civil Issues September 18, 2006Dixon Bogert SNUMI Civil Design & Site Considerations; Issues and FESS work Dixon Bogert SNUMI Meeting, Fermilab September 18 th, 2006 Reporting Work by FESS – Elaine McCluskey And Chuck Federowicz, Paul Lahn Last week’s work shown in red headers and text. (9/11) This week’s work shown in magenta headers and text. (9/18)

2 Fermilab 2 SNUMI Civil Issues September 18, 2006Dixon Bogert Phase 1 Elements of Construction SNUMI is planned to occur in two phases. The first phase, for which the items are identified with φ1 in the left margin, is required for the use of the Recycler Ring to slip stack 12 Booster batches of protons into six slots and then single turn transfer them into the Main Injector. The Main Injector will then spend minimal time at 8 GeV and the Main Injector cycle is reduced to about 1.33 seconds. The power on the NuMI Target is then about 700 kilowatts. A discussion of the development of civil definitions and preliminary cost and schedule estimates was held between Elaine McCluskey and Dixon Bogert on August 11, 2006.The basic outline was written down by Dixon on the Engineering Note shown below.

3 Fermilab 3 SNUMI Civil Issues September 18, 2006Dixon Bogert MI-14(?) Kicker Building at MI-10

4 Fermilab 4 SNUMI Civil Issues September 18, 2006Dixon Bogert MI-14(?) Location Near MI-10 MI-14(?) MI-10 MI-11

5 Fermilab 5 SNUMI Civil Issues September 18, 2006Dixon Bogert Proposed MI-14 Site Near MI-10 During the week FESS developed a detailed site plan for the MI-14 kicker building, based upon discussions with staff from AD/Electrical Support. To avoid setting the MI-14 building in the Indian Creek flood plain, the proposed building was turned around with entrance from the top of the FMI shielding berm. Discussions included the power required for the kickers, and the power required if an addition to house beamline power supplies is required. In this orientation, the kicker ducts cross under the proposed building. Shielding sections (not shown) were also made.

6 Fermilab 6 SNUMI Civil Issues September 18, 2006Dixon Bogert Proposed MI-14 Site Near MI-10

7 Fermilab 7 SNUMI Civil Issues September 18, 2006Dixon Bogert Proposed MI-14 Site Near MI-10

8 Fermilab 8 SNUMI Civil Issues September 18, 2006Dixon Bogert Proposed MI-14 Site Near MI-10 As of 9/18/06

9 Fermilab 9 SNUMI Civil Issues September 18, 2006Dixon Bogert Section thru MI-14 Site Near MI-10 MI-14 As of 9/18/06

10 Fermilab 10 SNUMI Civil Issues September 18, 2006Dixon Bogert MI-39(?) Kicker Building at MI-40

11 Fermilab 11 SNUMI Civil Issues September 18, 2006Dixon Bogert MI-39(?) Location Near MI-40 This location was suggested in the original memo. It is in wetlands, and access is poor. A possibly better choice is shown next, but the cable runs will be longer, although acceptable (<200’).

12 Fermilab 12 SNUMI Civil Issues September 18, 2006Dixon Bogert MI-39(?) Alternate Location Near MI-40

13 Fermilab 13 SNUMI Civil Issues September 18, 2006Dixon Bogert Proposed MI-39 Site Near MI-40 During the week FESS developed a detailed site plan for the MI-39 kicker building, based upon discussions with staff from AD/Electrical Support. The proposed building was set as shown last week outside of the FMI shielding berm. Discussions included the power required for the kickers. In this orientation, the kicker ducts enter the FMI berm directly from the back of the building.

14 Fermilab 14 SNUMI Civil Issues September 18, 2006Dixon Bogert Proposed MI-39 Site Near MI-40

15 Fermilab 15 SNUMI Civil Issues September 18, 2006Dixon Bogert Proposed MI-39 Site Near MI-40

16 Fermilab 16 SNUMI Civil Issues September 18, 2006Dixon Bogert Proposed MI-39 Site Near MI-40 As of 9/18/06

17 Fermilab 17 SNUMI Civil Issues September 18, 2006Dixon Bogert Section thru MI-39 Site Near MI-40 MI-39 As of 9/18/06

18 Fermilab 18 SNUMI Civil Issues September 18, 2006Dixon Bogert F17 is a model for these Buildings These drawings are taken from Project 6-6-8A

19 Fermilab 19 SNUMI Civil Issues September 18, 2006Dixon Bogert 4 th Anode Supply Room at MI-60

20 Fermilab 20 SNUMI Civil Issues September 18, 2006Dixon Bogert 4 th Anode Supply Room Location at MI-60 Possible blast/fire wall is required here. Additional 4-bay switch almost certainly required MI-60 Hi-Bay MI-60 Lo-Bay

21 Fermilab 21 SNUMI Civil Issues September 18, 2006Dixon Bogert 4 th Anode Supply Room Location at MI-60 FESS further developed the concept of locating the additional anode supply room in the area immediately north of the MI-60 high bay. A blast/fire wall was developed that could be placed immediately north of the high bay wall and made part of the MI-60 high bay wall.

22 Fermilab 22 SNUMI Civil Issues September 18, 2006Dixon Bogert 4 th Anode Supply Room Location at MI-60

23 Fermilab 23 SNUMI Civil Issues September 18, 2006Dixon Bogert 4 th Anode Supply Room Location at MI-60

24 Fermilab 24 SNUMI Civil Issues September 18, 2006Dixon Bogert Buss Bar Insertion at MI-60

25 Fermilab 25 SNUMI Civil Issues September 18, 2006Dixon Bogert Buss Bar Insertion at MI-60 Note interference with roof purlin beam

26 Fermilab 26 SNUMI Civil Issues September 18, 2006Dixon Bogert Additional Cooling Pond at MI-60 Ponds A/B

27 Fermilab 27 SNUMI Civil Issues September 18, 2006Dixon Bogert Additional Cooling Pond Location at MI-60 Pond A Pond B Pond “X” MI-60

28 Fermilab 28 SNUMI Civil Issues September 18, 2006Dixon Bogert Phase 2 – Accumulator Connections

29 Fermilab 29 SNUMI Civil Issues September 18, 2006Dixon Bogert Phase 2 – Accumulator Connections (Cont.)

30 Fermilab 30 SNUMI Civil Issues September 18, 2006Dixon Bogert Phase 2 – Accumulator Connections (Sketch)

31 Fermilab 31 SNUMI Civil Issues September 18, 2006Dixon Bogert Phase 2 – Accumulator Connections (Utilities)

32 Fermilab 32 SNUMI Civil Issues September 18, 2006Dixon Bogert Phase 2 – AP-4 Connection - 8 GeV Exit Point

33 Fermilab 33 SNUMI Civil Issues September 18, 2006Dixon Bogert Phase 2 – AP-4 Connection - 8 GeV Exit Point

34 Fermilab 34 SNUMI Civil Issues September 18, 2006Dixon Bogert FESS Deliverables

35 Fermilab 35 SNUMI Civil Issues September 18, 2006Dixon Bogert Remaining FESS Phase 1 work is only for the recycler

36 Fermilab 36 SNUMI Civil Issues September 18, 2006Dixon Bogert FESS forwarded to SNUMI Management comments on DOE Space Offsets


Download ppt "Fermilab 1 SNUMI Civil Issues September 18, 2006Dixon Bogert SNUMI Civil Design & Site Considerations; Issues and FESS work Dixon Bogert SNUMI Meeting,"

Similar presentations


Ads by Google