1
Community Development Department Royal Palms Parkway City Council Workshop July 29, 2014
2
Community Development Department Scope of Work Project Length: 2.2 Miles Roadway resurfacing with new four foot paved shoulders New Eastbound Left Turn Lane at Royal Palms Pkwy and Rickenbacker Drive – Improves safety and intersection capacity New Eastbound Right Turn Lane at Royal Palms Pkwy and Belle Terre Pkwy – Improves safety and intersection capacity Safety improvements for path to Lehigh Trail at the intersection of Royal Palms Pkwy and Rymfire Drive –Three Rectangular Rapid Flashing Beacons (RRFB) –Median Refuge
3
Community Development Department Pedestrian Improvements Royal Palms Pkwy & Rymfire Drive
4
Community Development Department Map Area Project Start Project End US 1 Royal Palms Pkwy Belle Terre Pkwy
5
Community Development Department Original Estimated Construction Budget – $900k Proposed FY 2015 Budget - $1.33 Million Actual Cost –Construction Bid – $1.18 million –Contingency, CEI & Misc Expenses – $150k –Total – $1.33 million Project Budget