PACS IIDR 01/02 Mar 2001 EGSE1 Otto H. Bauer MPE
2
PACS IIDR 01/02 Mar 2001 EGSE2 Herschel Common Science System for ILT Consists of HCSS v0.1 and EGSE set-up –Based on a staggered development HCSS is a common development of HSCDT and ICC´s –HCSS v0.1 PDR successfully completed (end Feb.) EGSE is a common development of instrument teams –Organized through EGSE Working Group –Work packages defined in Statements of Work –Commitment through Letter of Understanding –Based on re-use and adaptation of available packets (SCOS 2000, Integral MIB Editor, Test Control –Supported by Project (ESTEC, ESOC)
3
PACS IIDR 01/02 Mar 2001 EGSE3 Distribution of Work Packages CDMS (1553B + Tranfer Layer Protocol)SPIRE Test Equipment Interface (TEI)HIFI TM/TC InterfaceHIFI SCOS 2000all On-board S/W Maintenance FacilityIFSI MIB Editor evaluation (-> Integral)HIFI Test ControlPACS SCOS 2000 On-board S/W ManagementPACS
4
PACS IIDR 01/02 Mar 2001 EGSE4 Deliveries and Schedule Status DateSupplierCustomerDelivered Item Feb 5ESTECHIFISCOS 2000/Router ICD Feb 15HIFIallRouter prototype Feb 27ESOCallMIB Editor prototype Feb 28ESTECHIFI, PACSSCOS 2000 v2.0 EGSE extension including TOPE oMar 1HIFIallRouter (SCOS 2000 – TEI) oMar 1ESOCallMIB Editor oApr 15PACSallTest Control (IFSI DPU test) oMay 8SPIREallCDMS Simulator oMay 18Everything is at MPEIntegration for IFSI tests oMay 31Shipment to IFSI oJune 30ESTECallSCOS v2.1e (Sol. 8, dif. COTS) oOct 1PACSallOBSM (SCOS 2000) oOct 1HSCDTallHCSS v0.1 (first release) oOct 1Everything is at MPEIntegration (HCSDT + ICC´s)
Similar presentations
© 2025 SlidePlayer.com. Inc.
All rights reserved.