Download presentation
Presentation is loading. Please wait.
Published byMadeleine Mathews Modified over 8 years ago
1
Place your chosen image here. The four corners must just cover the arrow tips. For covers, the three pictures should be the same size and in a straight line. Update on Review of Embedded Generation Benefits Andy Wainwright
2
2 Background Standard Licence Condition C13 Introduced at BETTA (2005) Addressed different treatment of 132kV connected small generation in Scotland (transmission) with that in England and Wales (embedded) Time limited: due to expire 1 st April 2016 Embedded review needs to consider overall implications on GB generation Informal industry focus group established Spring 2013
3
3 Objectives of transmission charges Cost reflectivity Facilitate competition Developments in transmission businesses Recover transmission costs Non-discrimination Affected transmission ‘charges’ TNUoS BSUoS Losses Focus Group agreement to consider TNUoS first
4
4 TNUoS Charges - Locational Element TNUoS Locational Elements only Charging Zones Tariffs Net approach Embedded generation nets with demand Therefore subject to a negative demand locational signal Based on output at Triad Equivalent to generation signal: zoning limitations Gross approach Embedded generation receives same generation signal as transmission connected All demand receives locational signal
5
5 The effect of the generation residual element -10 -5 0 5 10 15 20 25 30 ABCDE Gen Dmd Avoidance of generation residual charge Embedded generator avoids paying generation residual element
6
6 The effect of the demand residual element -10 -5 0 5 10 15 20 25 30 ABCDE Gen Dmd Netting of positive demand Positive demand can avoid paying the demand residual element if able to net with embedded generation Embedded generation therefore has a value equal to the demand residual element
7
7 Combination of both residual elements In summary, embedded generation can receive TNUoS ‘benefit’ through two effects on residual elements; netting of positive demand (i.e. reducing demand charge) avoidance of generation residual charge Avoidance of generation residual charge Netting of positive demand 2 x Residual uplift
8
8 YearCostResidual 2012/13£1.41/kW£27.07/kW 2009/10£1.30/kW (equates to £1.47/kW in 2012/13) 1 £20.74/kW (equates to £23.53/kW in 2012/13) 1 1 RPI factor for 2009/10 to 2012/13 = 1.132992 How much benefit should be paid for offsetting +ve demand? NGET GSP infrastructure reinforcement costs
9
9 Average TNUoS charge: £7.57/kW (2013/14) Transmission Function (Use)Transmission connected G Embedded G Net transfers inject Net Access to Market (s) GB & wider EU Security / Quality of Supply Should embedded generation pay for transmission? How does embedded generation use transmission? Comparing transmission and distribution charges Note 2013/14 average TNUoS charge: £7.75/kW
10
10 Other areas under consideration Impact on >100MW generatorsExporting GSPsOffshore Transmission Implications
11
11 Next steps National Grid report to be published October Include Focus group & bi-lateral discussions Three week open letter Formal CUSC modification proposal potentially later in Autumn
Similar presentations
© 2024 SlidePlayer.com. Inc.
All rights reserved.