1
Stacy Hagenbucher
2
Process Improvements Clarification Trends Finals Tracking Trends Why Missing Dates Additional Resource Issues on sites
3
22 projects are in the process 8 have been completed Averaging 143 days overall on process Common Issues: All Work Complete Date Punch List Substantial Complete Planting Dates – ONLY ENTER ON PROJECTS WITH PLANTING CYCLES
4
Source Document Reference – Including Tickets Breakouts noted – EX: HMA Shoulders from Mainline Proper Checking ALL calculations - red ink and initialed Maintenance and Repair of Haul Roads – NEEDS TO BE PAID ON ALL PROJECTS
5
ASP 6 - Effective on January Lettings If temperature is 40 degrees or less for paving – to the point of cut off. Only if entire day is 40 degrees or less, otherwise hold off paving until within standard specifications. Once agree to it for a day – payment for entire day. Change Order into projects – should be about $3/Ton Required to submit a cold weather paving plan.
6
Place at 0.05 to 0.07 gallons per square yard. This is considerably more than previously placed. Use higher end on milled surfaces. Should no longer see “lines” Dilution Need confirmation from contractor that it is a 50% max dilution rate of the tack material.
7
Bad vs. Good
8
Focus this year Looking for more consistency throughout the region Three areas to focus on: Contract Language in Field Manager Proper Justification Backup Documentation
9
Contract Modification in Fieldmanager Reason Code Need two letter code – nothing else Contract Document Should read like one – Use Standard Spec and Special Provisions as a go by for setup and language Should not contain Justification. Us Spelchick
10
Contract Modification Justification This is where the explanation fits Less formal writing Needs to be JUSTIFICATION though On Price – Needs background information – stating Engineer reviewed is NOT enough. Add background information as attachments – emails, calculations, Bid Express...
11
Check Culvert Pipe Lengths and Sizes prior to Contractor Ordering Pipes Real Estate Check for any commitments made during design. Coordinate with Contractor to ensure enough ROW or TLE was acquired for work to be completed. Erosion Control Do not be afraid to use Orders, pay mobilizations, and verify that plan is correct in placement. Check what should be placed DURING construction.
12
Timely Decision Making – Pantry/Manuals Pre-Construction Meetings Weekly Meetings Minutes Project Records Line of Communication – In NCR Pre-con Shell Designated Materials Person 3 Week Rolling Schedule RFI Evaluation Forms
13
Traffic Control Inspections Inspection Sheet Utility Conflicts Still a concern, stay vigilant
15
In Region Pantry Folder A start to finish project guide References existing documents Contains some processes not covered elsewhere Erosion Control Release Work in progress – Comments appreciated – requests for further information, incorrect information Will be updated annually
16
As of Feb. 1 – Sign Shops no longer accepting sign drop offs. SPV changed. Current Contracts with old language – No Cost Change order to send signs to new locations. Signs can be dropped off at any of the Distributor County Shops – does not have to be the region shop the project is in.
18
Added example page to Wire Spreadsheet Added High Strength Structural Steel Sign Support sheet with example Signing spreadsheet updated to include new sign items and 6 columns Removed locks on project information cells Renamed to group like sheets together Removed Incentive Density Spreadsheet – no longer required
19
Concrete Pipe Length Sheet added to use for calculations.