Presentation is loading. Please wait.

Presentation is loading. Please wait.

Elliptical cryomodules

Similar presentations


Presentation on theme: "Elliptical cryomodules"— Presentation transcript:

1 Elliptical cryomodules
Annual audit for WP5 Elliptical cryomodules P. Bosland 1st prototype cryomodule M-ECCTD 2nd prototype cryomodule H-ECCTD 9 medium beta serial CM cavities 21 high beta serial CM cavities

2 Two prototype cryomodules
M-ECCTD with medium beta cavities – 2016 FR-SW agreement Collaboration IPNO and IRFU H-ECCTD with high beta cavities – 2017 French In-kind contribution

3 FR – SW agreement + amendment
Collaboration IRFU – IPNO P. Bosland WPL5 - G. Olivier Christine Darve FR – SW agreement + amendment IPNO in charge of the cryostat – design and fabrication Vacuum vessel Space frame – cavity supports Thermal screen Superinsulation Internal cryogenic pipes Instrumentation IRFU in charge of the “cavity package”, the cryomodule assembly and RF power tests: Cavities + helium tank Power coupler design, manufacturing, RF tests Piezo tuner Magnetic shield Tooling: field flatness, cavity preparation, cryomodule assembling, … Cryomodule assembly Tests stand for cryogenic and RF power tests Tests of the ECCTD cryomodule

4 Cryomodule Design Similar to CEBAF/SNS cryomodule with 4 cavities per cryomodule Common design for medium (6 cells) and high beta (5 cells) cavity cryomodules Accelerating gradient: for b=0.67 (Medium Beta): Eacc=16.7 MV/m Qo> 5E9 at 2 K for b=0.86 (High Beta): Eacc=19.9 MV/m Qo> 5E9 at 2 K Maximum operating helium pressure: bar total length: 6.6 m Beam height: 1.5 m

5 Medium / High beta cavity
Tank (Ti) Magnetic shielding Cold tuning system Medium High Geometrical beta 0.67 0.86 Frequency (MHz) 704.42 Operating temperature (K) 2 Maximum surface field in operation (MV/m) 45 Nominal Accelerating gradient (MV/m) 16.7 19.9 Nominal Accelerating Voltage (MV) 14,3 18,2 Q0 at nominal gradient > 5e9 Cavity dynamic heat load (W) 4,9 6,5 Qext High beta (0,86): 5 cells Length 1316,91mm Medium beta (0,67): 6 cells Length 1259,40mm 57,5 mm Medium High Iris diameter (mm) 94 120 Cell to cell coupling k (%) 1.22 1.8 p and 5p/6 (or 4p/5) mode separation (MHz) 0.54 1.2 Epk/Eacc 2.36 2.2 Bpk/Eacc (mT/(MV/m)) 4.79 4.3 Maximum. r/Q (W) 394 477 Optimum b 0.705 0.92 G (W) 196.63 241 No HOM couplers HOM frequencies must be carefully controlled

6 HOMs This HOMs have been found at and MHz (P01) and and MHZ (P02) => 3D measurements of the ½ cells and end groups required for the production of next medium beta cavities Stiffening ring on the external ½ cell ?

7 Experience of the HIPPI power coupler at Saclay
HIPPI power coupler (KEK-type window) tested to 1.2 MW, 10% Duty factor at Saclay Test of the HIPPI power coupler on the HIPPI cavity at 1.8 K, full reflection

8 The ESS power coupler Pmax = 1.2 MW peak at 4 % duty cycle → critical component RF disc ceramic window Inner conductor Conical tip for stronger coupling Water cooling Outer conductor Cooled with Liquid He in the vac. Vessel Coax to rectangular RF transition (Door Knob) HV bias with RF trap CM integration Large diameter flange with below on vacuum vessel 3 diagnostic ports New design of the doorknob waveguide transition including a HV bias capacitor with RF trap Coupler conditioning set-up

9 Cold tuning system Type V for SPL beta = 1 5-cell prototype
Saclay V type adapted for ESS cavities +/- 3 mm range 1+1 piezo Cold motor and planetary gearbox (1/100e) Piezo support has a stiffness 10 times higher than the cavity  piezo preload at 2K is independant of the cavity springback force Type V for SPL beta = 1 5-cell prototype CTS linearity at 4.2K of type V-HIPPI

10 Magnetic shield Limit contribution of the trapped flux to the surface resistance to 4nW Limit the external static field to Bext = 14 mG. → required shielding efficiency equal to 35. Requirements achievable with a 2 mm in thickness and mr=15000 shielding material

11 Supports of the different cold components
Blocking nut Cross rods fixed on 2 titanium half rings fastened to the helium tank on one side and on the spaceframe on the other side 3000N pre-stress applied on the rods, maximum force 8500N per rod after cooling down Pre-stress nut Rods (TA6V, Diam. 6mm) Magnetic shield Half rings linked to the tank (under the magnetic shield) Rod Thermal shield 3 jacks at 120° supporting the spaceframe after insertion 2 wheels fixed to the spaceframe at each extremity Guiding ensured by two rails welded to the vacuum vessel Supporting rods Special boxes allowing the axial moving and the thermalization of the thermal shield

12 Inter-cavities bellows
Mechanical cavity misalignment on the cavity strings Longitudinal shrinkage of the cavities Thermal isolation at the two extremities of the cryomodule Cold to warm transition MEDIUM BETA Number of corrugations: 10 Overall length 240,5mm Axial stiffness for 10 corrugations 21N/mm Radial stroke for 10 corrugations +/-0.80mm Radial stiffness for 10 corrugations 4450N/mm HIGH BETA Number of corrugations: 6 Overall length 183mm (at rest) Axial stiffness for 6 corrugations 35N/mm Radial stroke for 6 corrugations +/-0.48mm Radial stiffness for 6 corrugations 7417N/mm Distribution of the RF HOM modes

13 Spaceframe Spaceframe: Aluminium alloy
Forces on Rods: 3000 to 9000N Mass spaceframe: Kg Total mass of cavities + thermal shielding: 1200Kg Blocking by 3 jacks on two levels Tuning (3 positions) Spaceframe: Aluminium alloy Lower part can be disassembled to insert the couplers Depl. Total (mm) Depl. Struct. Depl. Blocs Contrainte max (Mpa) 1,32 1,24 (Z: -1,21 à +0,50) 0,12 à 1,08 (Z: -0,89 à +0,18) 30

14 Access traps blocking of the cavities and spaceframe during transport
Access in the tunnel Maintenance of cold tuning system (change motor and piezo)

15 Alignement of the cavities Alignment made by laser tracker
Beam axis reported to reflector bracket on beam flanges 1 2 Alignment of the cavity string within 1,5 mm of the beam axis 3 Vessel alignment with respect to cavity string 4 Alignment made by laser tracker Reflector brackets (vessel alignment) Alignment of the cryomodule in the tunnel (source ESS) Reflector brackets (coupler flange) Reflector brackets (cavity flange) 1,5" Corner cube reflector Additional fiducials will be set up inside the ECCTD cryomodule to check the alignment after cooling down.

16 Heat loads Values in Watts

17 PID for the elliptical cryomodules

18 Instrumentation list for the M-ECCTD
……

19 Compliance with the PED
97/23/EC Relative pressure Vessels Pipes 50 L Elliptical cavity 1 bar PS<0,5bar: The equipment is not on the scope of the 97/23/CE directive Article 3.3 The equipment must be designed and manufactured according to workmanlike way Category I The manufacturing must be more documented, especially with internal production control Objective: stay within « Article 3.3 » area

20 Helium Pressure relief devices
Cavity pressure test 1,43 PS Working pressure = nominal pressure WP PSET Set Pressure PS Maximum allowable overpressure PS + 10% Safety devices Safety devices 2,72 bar 2,09 bar Bursting disks +/- 10% Absolute pressure Max. allowable press. PSET + 10% 1,9 bar 1,891 bar Bursting disk 1,81 bar Bursting area PSET – 10% European rules compliance Article 3.3 1,729 bar Safety margin PSET POPENING = + 5 % PSET (overpressure when opening) PMAX APERTURE = + 10 % POPENING PCLOSING = - 5 % PSET PMIN CLOSING = - 10 % PCLOSING (hysteresis before closing) 59mbar 1,670 bar 1,609 bar Relief valve MAWP 1,58bar Opening area 1,551 bar 1,496 bar Safety margin 1,431 bar (1,3 +10%) 65mbar WP upper limit 1,301 bar ESS Helium factory, circuits and operating modes

21 Helium low pressure circuit
2 bursting disk at each tip + upstream safety relief valve (with he guard) To valve box A 36° angle is set up for the tank nozzle in order to allow the insertion of the cavity string and the cooling circuit inside the spaceframe Heat exchanger 36° The circuit is designed to reduce as low as possible the overpressure in case of beam vacuum failure by using a continuous DN100 diameter for the diphasic pipe, large curvatures and 2 DN100 bursting disks at each extremity. Worst scenario: beam vacuum failure 38KW/m2 heat load on the cavity wall Accidental overpressure: 230mbar after rupture of the disks

22 Cryomodule assembly

23 M-ECCTD Two objectives: To qualify the technology
To prepare the assembly procedures, the tools and the documentation for the serial elliptical cavity cryomodules Assembly procedure Assembly procedure Integration tools Integration tools Items manufacturing ECCTD integration Ready for the serial cryomodules Documentation Documentation Others Others Preliminary Version Final Version

24 Analyse of the assembling sequence
Student: Amaury Martin 09/2013 – 01/2014 Study of the assembling sequence and needs of toolings Assembling in clean room Assembling outside clean room Pre-study of the toolings: compatible with both types of cavities medium and high beta

25 Coupler / cavity assembly
State of the art: interface coupler / cavity parallel to the laminar air flow Horizontal coupler Rotation needed after assembly to get to the final vertical position of the coupler in the cryomodule Complex tooling First rough analysis of the air flow around the flange: the air flow may be pertubated because of the reinforcement sheets of the helium tank Choice: vertical assembly Tooling compatible for both types types of cavities Adjustment of the coupler position relative to the cavity flange Coupler vertical Coupler horizontal Air speed Whirlwind

26 Frame and supports for the assembly in clean room

27 Cavity string assembly in clean room
Design still in progress Beam axis height: 1150 mm from the clean room ground Individual position adjustment system of each cavity and bellow Supports of the cold to warm transition bellows to be designed

28 Assembly outside clean room
Thermal screen installed but not shown Wheels on the spaceframe Guiding rail on the vacuum tank

29 Courtesy of Catherine MADEC - XFEL
. The implementation of the assembling process at Saclay will be based on the SPIRAL2 and XFEL experience Courtesy of Spiral 2 CEA team Courtesy of Catherine MADEC - XFEL

30 Short status of the M-ECCTD
Cavities: Medium beta: fabrication started ‘6 cavities ordered to ZANON) Couplers: RF window and antenna ordered (8 ceramic windows ordered to Toshiba) Call for tender for outer conductor (double wall) and door-knob Tuners, magnetic shielding: Design 95% finalized Fabrication to be launched Spaceframe, vacuum vessel: Design finalized. Preparation of the procurement procedures in progress (goal: launch the procurement before the end of January 2015) Test stand: modification of the cryogenic line and HV modulator in progress Clean room assembly toolings: studies started - still in progress

31 Two high beta prototype cavities manufactured
Results of the first tests in vertical cryostat P01 ESS Prototype high beta cavity manufactured by ZANON P02 ESS Prototype high beta cavity manufactured by RI Heat treatment to remove hydrogen performed at CERN last week Next tests in VC mid of November

32 Planning of the M-ECCTD and H-ECCTD
Goal: qualification of the cavities/coupler And launch of the cavities and couplers production in Sept 2016

33 Schedule of the WP5 activities

34 Recommendations of the last audit at Orsay the 28 10 2014
Appendix B – Recommendations 1) Review decision and resulting design for limiting pressure for PED Cat 0 The auditors recommend WP4,WP5 review its decision to design to 0.5 bar gauge for avoiding PED Cat I+ certification requirements. WP4/WP5 should: Seek an independent peer review of the pressure safety design. Consider the possibility of 2 phase helium flow at the relief valves Start early discussions with a certifying organization for all implications such as raw material certification, traceability, safety analysis, etc. Review decision regarding 0.5 bar gauge and design resulting from this decision. Review operational implications of such a design Include in the time schedule activities for certification of crymodule pressure vessels. Includes QA traceability of materials. Ps = 0.9 bar article 3.3 of PED 2) Amend requirement: ESS-SYR-ACC-SPKL-EMR 190 Cavity RF instrument sensitivity – change from 1 V to ? - ESS – S. Molloy 3)Determine who the appropriate pressure certifying agency shall be for these cryomodules Responsible: ESS – J. Weisend II 4) Review design for active cooling for magnetic shielding: Solution for elliptical cryomodules is different and simpler. A single solution for all cryomodules shall be sought - IPNO 5) Develop requirements for cryomodule mounting and interface with ground ESS – S. Molloy and C.Darve

35 In progress Done Done Done
6) Amend ESS-SYR-ACC-SPKL-EMR 210 to include tolerances ( ?) Add requirement for yaw (rotation) ESS – S. Molloy and C.Darve 7) Develop Level 4 requirements for Vacuum for WP4 and WP5. This includes creating requirements for cryomodules interface to isolation vacuum system including: size of the port flange design pumping capacity define normal modes and maintenance mode and hence resulting configurations e.g. opened / closed valves vent requirements use of portable pump cart ESS – S. Molloy and C.Darve, with input from P.Ladd (WP12) In progress 8) Generate Heat Load requirements to WP11 for all cryomodule types. Requirements should be given by temperature level (2 K, 40 K and 4.5 K) and given for both static and dynamic cases. This is required by the end of 2013, to enable tendering for cryoplant during 2014. ESS – S. Molloy, C.Darve, and P.Arnold (WP11) 9) Generate Level 4 requirements between all accelerator types and WP11 Cryogenics. Examples of needed requirements include Definitions of cryomodule failure modes and expected responses Operation modes (reference existing document) Interfaces e.g. WP11 responsibility starts at vacuum barrier on cryosystem 10) Provide a tech note of calculations to ESS, to explain static and dynamic heat loading and to justify design choices for Spoke & Elliptical cryomodules. IPNO and CEA Saclay 11) Create Cryogenic Standards Document for ESS ESS –P.Arnold (WP11) Done Done Done

36 12) Determine and document the minimum wait time before entering tunnel after beam operations.
ESS - D. McGinnis 13) Develop a requirement for the warm-up time for both the Spoke and Elliptical cryomodules ESS – S. Molloy, C.Darve, and P.Arnold (WP11) 14) Review design of seals Reconsider use of VCR, swagelock connectors with metallic seals and replace with welds wherever possible IPNO and CEA Saclay 15) Review pressure relief system design to ensure that the burst disc reliefs are only used for catastrophic events and that the spring loaded relief valves are used in all other cases (power failure, cryoplant shut down, improperly operated controls valves etc) Done 16) Finalize P&ID’s for elliptical and spoke cryomodules. ESS – S. Molloy, C.Darve, P.Arnold (WP11) and agree interfaces with CEA Saclay 17) Ensure drop plate or other pressure relief devices in the cryomodule vacuum chamber is shown on the P&IDs IPNO and CEA Saclay 18) Review the planning of activities for the series –production elliptical cryomodules to ensure that it is not overly optimistic. Ensure that any updates are added to the ESS Integrated Project Schedule (P6) CEA Saclay and ESS (C.Darve) 19) Develop Level 3 or Level 4 requirements for the ICS interfaces for all resonators (RFQ, DTL, Spks, Ellipticals etc), in regards to PLCs, PLC programming, MPS (Machine Protection System) and PSS (Personnel Safety System). Ensure assignment of responsibilities are clear ESS – A. Ponton (WP3), S. Molloy, C. Darve and G.Trahern (ICS) Done Done Done

37 The transport has to be organized by ESS
20) Identify responsibilities for transportation of cryomodules between IPNO-Uppsala and between CEA Saclay- and ESS and document these in the WP descriptions, IKC agreements and contracts. Note that it may be necessary to develop transport-related performance requirements at Level 4 or 5 e.g. lifting eyes, vibration limits, drop test criteria, waterproofing, corrosion resistance etc. ESS - S. Molloy and C. Darve, IPNO and CEA – Saclay 21) Review the design and verify with the certifying organization the joints between Niobium and Tinanium without NiobiumTitanium alloy parts. Same investigation for the high temperature (600 °C for de-hydrogenation) treatment of cavities already welded in the titanium Helium tank and with already welded Ti Gr5 bellow (max temperature for Ti parts). The transport has to be organized by ESS Specification for the transport written by CEA with the agreement of ESS. Should not be an issue if the cryomodule stays in Article 3.3

38 Thank you for your attention

39 The team for the ECCTD changes New teams are being buit for the WPs
IRFU is preparing the new organization of the project for the CEA In Kind contribution The team for the ECCTD changes New teams are being buit for the WPs Example of the WP for the ECCTD WU Assemblage Intégration RWU C. Madec Coupleurs C. Arcambal Outillages N. Bazin J.P. Poupeau Blindages magnétiques, Expertise J. Plouin Tuners G. Devanz Cryostat G. Olivier CNRS/IPNO Cavités F Peauger Test F. Peauger Instrumentation interne Workpackage ECCTD RWP: F. Peauger Qualité A. Bruniquel Planning X. Hanus Responsable Scientifique Ingénieur Système Bunker test 704 MHz J.P. Charrier Cryomodules O. Piquet Système de Contrôle F. Gougnaud Source RF A Hamdi Cryogénie P. Sahuquet B. Renard Processing A. hamdi Suivi industriel V. Hennion N. Berton P. Contrepois Bureau d’études P. Hardy F. Leseigneur Infrastructure de test


Download ppt "Elliptical cryomodules"

Similar presentations


Ads by Google