Update on Chesapeake Bay Program Developments Briefing to the Water Resources Technical Committee October 9, 2009 (revised) Briefing to the Water Resources Technical Committee October 9, 2009 (revised)
2
WRTC Meeting (10/9/09)2 General CBP Updates Watershed Model Watershed Model –5.3 - Not ready yet (Final by Dec. 2009?) –5.2 – Used for initial targets/allocations Water Quality Model (significant changes) Water Quality Model (significant changes) –Change in Critical Period ’93 – ‘95 (1 in 10 years) –Change Reference Curves Scenario Builder Scenario Builder –Tool for developing local options/scenarios (vs. CBPO model runs) –Status – Not ready for ‘Local use’ for another 2 years
3
WRTC Meeting (10/9/09)3 General CBP Updates Load Allocations Load Allocations “Preliminary Basin-wide Target Loads” –200 M lb TN (vs. 175) –15 M lb TP (vs. 12) –Deemed sufficient to start WIP planning process SIPS - Now WIPs SIPS - Now WIPs –More Q’s than A’s – COG working to address these –State public process to start – Nov. 2009
4
WRTC Meeting (10/9/09)4 General CBP Updates Bay TMDLs - Schedule Bay TMDLs - Schedule –To be issued by EPA –Drafts – Due August 2010 –Finals - Still scheduled to be done by Dec. 2010 Deadline now embedded in: Deadline now embedded in: –Draft Executive Order 202a Water Quality Report –Draft EPA Guidance Document –Draft CWA Reauthorization Bill
5
WRTC Meeting (10/9/09)5 General CBP Updates WIPs – Schedule WIPs – Schedule –Delays - Updating info. & producing model runs for review/analysis to produce targets & allocations –Reduces available time to develop WIPs –Options being considered: Reduce public review period to 60 days Reduce public review period to 60 days Delay date for preliminary WIPs to Aug. 1 st Delay date for preliminary WIPs to Aug. 1 st Shorten response to comments turn-around time Shorten response to comments turn-around time
6
WRTC Meeting (10/9/09)6 General CBP Updates WIPs – Schedule WIPs – Schedule –Oct. 23 – PSC agrees on ‘working’ target loads –Nov. 1 – States/DC start development of WIPs, sub-sector target loads, etc. –Nov. 1 – EPA starts first round of public meetings Nov. 16 th – District’s proposed TMDL meeting Nov. 16 th – District’s proposed TMDL meeting –June 1 – States/DC submit preliminary WIPs –August 1 – States/DC submit draft WIPs –Nov. 1 – States/DC submit final WIPs TMDLs TMDLs –Dec. 21, 2010 - EPA publishes final Bay TMDL
7
WRTC Meeting (10/9/09)7 Key Issues WIPs WIPs –Insufficient time to develop robust/viable plans –Cost/Sufficient funding? –Achievability? –Accelerated implementation (2-3x current – realistic? TMDL requirements (WLAs vs. LAs) TMDL requirements (WLAs vs. LAs) –Potential constraints on local flexibility? –Legal constrains on changes? –Legal implications to locals of ‘consequences’?
8
WRTC Meeting (10/9/09)8 Next Steps Parallel Tracks Technical (i.e., COG staff review/analysis) Technical (i.e., COG staff review/analysis) –WIPs – Getting Answers to Questions –TMDL and Allocation Methodology – Identify implications to COG region & potential policy recommendations –TMDL Guidance Document – Review to ensure maximum flexibility for local governments/utilities –Executive Order Draft 202 Reports – Prepare formal comments Policy Policy –COG Board presentation by Chuck Fox (July 31 Retreat) & to CBPC (Nov. 20 th ) –Testimony by CBPC Chair on proposed CWA legislation (Sept. 22 nd ) –COG Board presentation by Senator Cardin (Oct. 14) on proposed CWA legislation –COG staff to develop formal comments on draft legislation