F ACILITIES, P LANNING, AND C ONSTRUCTION November 16, 2015 – Monthly Construction Report Report
2
Facilities Under Construction: V.R. Eaton High School Outdoor Learning Center Facilities in Planning/Bidding Stage: Transportation Complex Steele HVAC and Roof Renovation Area Currently Under Construction/ Planning
3
Remaining Work at Eaton High School Landscape –Weather Pending Pond C is the last area to be finished (behind baseball and softball fields) 3 rd Floor Academic Wing –Finish up this area
4
Outdoor Learning Center Architect: Stantec Architects Contractor: Northstar Builders Const. Start Date: February 2015 Completion Date: August 2016 Status: Piers Completed: 100% completed excluding the Overlook B Geo wells 100% completed Large Pavilion Moisture Conditioning is 75% Complete (12’) Anticipation wall grade beams are poured Septic Demo is 80% Complete
5
Great Hall and Front Drive
6
Great Hall
7
Large Pavilion
9
Wetland Pavilion and Restroom Building
10
Wetland Pavilion
11
Restroom Building
12
Creekside Pavilion
14
Transportation Complex Contractor: Const. Start Date: January 2015 Completion Date: June 2015 Program: Central Bus Complex Update: o Advertising begins November 17 th o Presented Contractor with cost in December o Durham School Services, L.P. agrees to contribute $745,000 to the Paving Project
15
Steele HVAC and Roof Replacement Engineer: MetCo Roof Consultant: Amtech Const. Start Date: June 2016 Completion Date: August 2016 Status: Working with consultants on design Method of Delivery to the Board in December Drawings to be completed at the beginning of 2016 Bid out project beginning of 2016
17
F ACILITIES, P LANNING, AND C ONSTRUCTION November 16, 2015 – Monthly Construction Report Report