® FSS Vehicle Shelving Systems Managers Delivery Programs Support May 7, 2008
2
® 2 Requirements FSS Vehicle Shelving Systems Total system weight: 275 pounds or less. Tray/Parcel Volume: 7 mail trays, 2 residual trays, 2 saturation trays, 7 FSS street trays, 12 parcels. Increase mail tray and stowage capacity Provide improved efficiency for loading and access of the mail and for disposition of the empty trays Improve tray and parcel organization Improve efficiency of moving mail from the cargo area to the front work area Operation intuitive for carriers Meet ergonomic requirements
3
® 3 FSS Shelving Background FSS Vehicle Shelving Systems Supplier Conference on FSS shelving systemsJan. 2007 Solicitation Issued Mar. 2007 Proposals Evaluated Apr. 2007 Prototype BuildJun. 2007 Unit Cost ReassessedAug. 2007 2 nd Prototype EvaluatedOct. 2007 Prototype Contract AwardNov. 2007 100 Field Eval Unit InstallationFeb. 2008
4
® 4 No System FSS Vehicle Shelving Systems
5
® 5 System A FSS Vehicle Shelving Systems
6
® 6 System B FSS Vehicle Shelving Systems
7
® 7 System C FSS Vehicle Shelving Systems
8
® 8 Field Carrier Evaluation – Reston and Fairfax POs FSS Vehicle Shelving Systems Approx. 60 carriers used the three systems from March 10- April 19 Each carrier utilizes one system for two weeks. Survey and interviewed follow at the end of each usage Unofficial Official Results System A: Some carriers did like the system, some did not. System B: Almost all of carriers did not like the system System C: Majority of carriers like the system.
9
® 9 System Evaluation The final system will be selected based on: FSS Vehicle Shelving Systems Carrier Survey Durability Test System Interaction Study Repair/Maintenance Time and Ease of Installation
10
® 10 Next Steps FSS Vehicle Shelving Systems Cycle Durability Test Mar. 8 – Apr.30 Road Durability Test Mar.10 – Apr.15 Production Cost Submission Apr. 15 Selection for Crash Test May 15 Crash Test Completed Jun. 15 Contract Award for 18,000 units Jul. 15 First Article Inspection Sep. 1 Delivery Oct. 1/08 – Oct. 1/10