Presented by: Russell M. Arnold Jr., PE Director/Town Engineer Public Works Department Christopher N. Pierce, PE Wright-Pierce
2
WPCF Background Need for Current Project Recommended Plan Project Cost Estimate Schedule Farmington WPCF Upgrade2 Agenda
3
Originally Constructed 1960s Expanded in 1970 Additional Capacity Upgrade & Expansion 1994 Additional Capacity Effluent Ammonia Limits Continuous operation Farmington WPCF Upgrade3
4
WPCA Goals Capacity for projected flows and loads Upgrade aging infrastructure More stringent permit limits Nitrogen (Protect Long Island Sound) Phosphorus (Protect Farmington River) BOD 5 /TSS Improve Energy Efficiency Provide additional odor control 4Farmington WPCF Upgrade
5
5
6
PROJECT COMPONENTCOST CONSTRUCTION$47,460,000 CONSTRUCTION CONTINGENCY (5%)$2,370,000 TECHNICAL SERVICES (13.0%)$6,170,000 MATERIAL TESTING (0.5%)$240,000 ASBESTOS & LEAD PAINT ABATEMENT-$50,000 LEGAL / ADMINISTRATIVE / FINANCING$950,000 ENGINEERS ESTIMATE OF COST$57,240,000 6 Farmington WPCF Upgrade
7
CWF eligible funding $57,240,000 Anticipated grant (21.5%)-$12,306,600 Design (WPCA) -$ 2,893,000 Local share$42,040,400 Anticipated Assessments Farmington @ 78.1%$ 32,833,552 Avon @ 9.5%$ 3,993,838 UCHC @ 6.8%$ 2,858,747 Burlington @ 4.8%$ 2,017,939 Canton @ 0.8%$ 336,552 7Farmington WPCF Upgrade
8
Annual Debt Service $1,991,100 (net of Assessments) Increase to Tax Rate.57 Mills Average Assessment $ 232,074 Tax Impact $132.58/Year 8
9
9Farmington WPCF Upgrade July 8 th Council Agenda – Set Public Hearing August 12 th Council Agenda Public Hearing Section 8-24 Referral Bond Resolution Set Special Town Meeting August through October – Project Information to Public Special Town Meeting – Oct. 25 th Referendum – Nov. 4 th