Central Valley Flood Protection Board Meeting – Enforcement Report 1
2
Enforcement Activity – January thru March: 427 Encroachments identified in USACE Inspections entered into DB 5 Fact Finding Letters were Issued 2 – Reached full compliance 2 – Have agreed to comply after flood season or farming activities 1 – Requested a meeting with staff 8 Notices of Violation Issued 2 – Reached full compliance 1 – Incorrectly complied 1 – No response has been received 4 – Issued in late March 2
3
Central Valley Flood Protection Board Meeting – Enforcement Report Enforcement Activity – January thru March: 2 – Cease and Desist Orders were adopted by CVFPB 1 – Cease and Desist Hearing 2 – Compliance Letters issued 13 – Encroachment cases closed USACE Inspection Compliance: 69 Systems are Active for PL 84-99 RIP Assistance 41 Systems are Inactive 8 Systems are Partially Inactive 3
4
Central Valley Flood Protection Board Meeting – Enforcement Report 4
5
Letter of Intent (LOI) for System Wide Improvement Framework (SWIF) Update: Reclamation District 1000’s LOI was submitted to USACE March 11, 2013 SBFCA’s LOI was submitted to USACE on March 26, 2013 Reclamation District 1001’s LOI will be submitted to USACE once finalized 5
6
Central Valley Flood Protection Board Meeting – Enforcement Report Questions? 6
7
Central Valley Flood Protection Board Meeting – Enforcement Report Partially Inactive: In the past, USACE inspected portions of levee systems, and would give ratings to portions of levee systems. If 3 LMA’s were responsible for a system, 1 LMA may have been rated inactive, while the other two were rated active, giving the levee system a partially inactive rating. 7
8
Central Valley Flood Protection Board Meeting – Enforcement Report Enforcement Database Update: 778 - Encroachments 460 - Recently Entered from USACE Inspection Reports 320 – Before USACE Inspection Reports Of the 778 122 – Closed 481 – Categorized as “Investigate” 175 – Categorized as “Active” New Tools in the DB 8
9
Central Valley Flood Protection Board Meeting – Enforcement Report Status ID Order Status/Activity Month Year Total 18100Encroachment Project Entered into DB12013207 3180Fact Finding Letter Sent120134 7820Public Hearing by Board120131 17 2000Encroachment Closed120132 18100Encroachment Project Entered into DB220138 5200Notice of Violation Sent220135 28930Compliance Letter Issued220131 17 2000Encroachment Closed220139 18100Encroachment Project Entered into DB32013212 3180Fact Finding Letter Sent320131 5200Notice of Violation Sent320134 28930Compliance Letter Issued320131 17 2000Encroachment Closed320132 9