Presentation is loading. Please wait.

Presentation is loading. Please wait.

IBL Kick-off Meeting – Summary & Issues G. Darbo – INFN / Genova UPO, 21 July 2009 o IBL kick off meeting summary and issues ATLAS Upgrade Project Office.

Similar presentations


Presentation on theme: "IBL Kick-off Meeting – Summary & Issues G. Darbo – INFN / Genova UPO, 21 July 2009 o IBL kick off meeting summary and issues ATLAS Upgrade Project Office."— Presentation transcript:

1 IBL Kick-off Meeting – Summary & Issues G. Darbo – INFN / Genova UPO, 21 July 2009 o IBL kick off meeting summary and issues ATLAS Upgrade Project Office CERN, July 21 th 2009 G. Darbo - INFN / Genova Indico AGENDA page: http://indico.cern.ch/conferenceDisplay.py?confId=64379

2 IBL Kick-off Meeting – Summary & Issues G. Darbo – INFN / Genova UPO, 21 July 2009 2 IBL kick-off – July 8 th IBL kick-off meeting Venue: July 8 th, at Holliday Inn (Thoiry). 55 Registrants, 31 Institutes represented, 35÷40 Institutes shown interest

3 IBL Kick-off Meeting – Summary & Issues G. Darbo – INFN / Genova UPO, 21 July 2009 3 IBL kick-off Agenda http://indico.cern.ch/conferenceOtherViews.py?view=standard&confId=56905

4 IBL Kick-off Meeting – Summary & Issues G. Darbo – INFN / Genova UPO, 21 July 2009 4 Cost What in prototype costs: Sensors: Planar, 3D, Diamond (1) Electronics: FE-I4 Hybridisation: bump-bonding Local supports: stave Beam-pipe: mock-up External cooling: Thermal management What not: All other electronics / mechanical prototypes Irradiation and test beam (1) Diamond prototype added to cost - if diamond are the IBL sensors, the IBL cost will increase by > 1MCH.

5 IBL Kick-off Meeting – Summary & Issues G. Darbo – INFN / Genova UPO, 21 July 2009 5 Some Comments on Cost The IBL project is not uniformly developed on all its part Revisit cost when TDR will be mature Contingency not included – how to deal extra cost? Include contingency? Extra cost of deliverable has to be covered by the share assigned to the Institute? Funding scenario: 4.0 MCHF (M&O-A) + {4.4 MCHF (M&O-B) + 1.2 MCHF (fresh project money from new institutes)} – What next: 1.within this funding model, "old" M&O-B FA’s need to confirm their share of 4.4M (anything removed goes into +1.2M for general "bidding”); 2.establish the "money matrix” – tentative ; 3.collect firm pledges; 4.draft (i)MoU – it appears clear that we need to match financial with “visibility” of the contribution.

6 IBL Kick-off Meeting – Summary & Issues G. Darbo – INFN / Genova UPO, 21 July 2009 6 Interest in the Project 35÷40 Institutes (some present themselves in partnership with two or more Institutes). They are represented by a total of 16 Funding Agencies Strong interest in sensors across the 3 technology options (planar/3D/diamond) – 22 institutes interested in a sensor technology – for some of them the contribution to the project is conditional to the sensor option. First round of “serious” expression of interest: 120 ÷ 150 FTE (Engineers, Physicist, PhD) 8÷9 MCHF could be available to cover the 6.6 MCHF – some dependency of funding on chosen technology options (sensor/cooling/stave) and on distribution of deliverables amongst Institutes (Institutes will contribute to the project with money if their role/visibility is corresponding).

7 IBL Kick-off Meeting – Summary & Issues G. Darbo – INFN / Genova UPO, 21 July 2009 7 What (over)-Subscribed & What not WBS 1 - Sensors: 3 sensor technologies in the prototype phase: many groups (22) interested in sensors. Sensor production/test sites: we need two or max three sites for testing sensors after production – no more than one per Country. The past Pixel sensor tests were made in Germany/Italy/US for a much larger number of sensors. Sensor production cost divided amongst many FA’s – no “majority share” If diamond will be the chosen sensor technology – revisit project cost. WBS 2 – Electronics: The package is quite well covered Over subscription on ROD – need coordinated discussion between opto- board/BOC/ROD WBS 3 – Hybridisation Bump-bonding prototype is oversubscribed – we need more than one bump technology for prototyping and only one for production (cost and quantity are not an issue) Over subscription (not strong) on flex hybrid technology interconnect technology.

8 IBL Kick-off Meeting – Summary & Issues G. Darbo – INFN / Genova UPO, 21 July 2009 8 WBS 4 – Local Supports Bare stave is well covered – groups quite active Module loading on stave looks over-subscribed – need more discussions and better understanding. Cooling pipe fittings could have impact on the overall module loading plans WBS 5 – Internal Services Covered – no special issues WBS 6 – Beam-pipe & interfaces (global supports) This is centrally designed by PO – there are Institutes with mechanical engineering manpower that could take sub part as deliverables – not commitments taken (too early in the definition). WBS 7 – Surface Integration Little covered at moment – expression of interest available – need coordination

9 IBL Kick-off Meeting – Summary & Issues G. Darbo – INFN / Genova UPO, 21 July 2009 9 WBS 8 – External services Part of WBS on M&O-A not covered: Type 2, 3 and 4 cables and pipes WBS 9 – External Cooling & Gas In discussion the new organization of the cooling CO2 or C3F8 (mixture of C2F6 + C3F8) to be selected WBS 10 – Installation in the Pit Completely on M&O-A WBS 11 – DAQ, DCS & Interlock integration DCS hardware – Mainly Wuppertal HV/LV PS (M&O-A) – interested groups WBS 12 - Irradiation and Test Beam Many group interested. An upgrade/refurbishment of the strip telescope would be welcome – who interested?

10 IBL Kick-off Meeting – Summary & Issues G. Darbo – INFN / Genova UPO, 21 July 2009 10 Schedule – Fixed Date or sLHC I? Need to know: Design for sLHC phase I no matter what (follow machine schedule)? Design for a fixed installation date – install when ready (before Phase I) When to make it ready? The Upgrade Project Office (May 12 th ) suggests to use 2014/2015 as a guideline for the IBL installation date. We are now working with a schedule that foresees an installation date in 2014/2015 The FE-I4 and Sensor/Module are on the critical path, and installing earlier than 2014/2015 would require some compromises in the performance.

11 IBL Kick-off Meeting – Summary & Issues G. Darbo – INFN / Genova UPO, 21 July 2009 11 FE-I4 Review FE-I4 has gone through a “system & design issue” review on March, 2 nd 2009: http://indico.cern.ch/conferenceDisplay.py?confId=52403 A readiness review before chip closure is foreseen for late September/October: Kevin will chair the review committee Review organised by Philippe and Maurice Engineering run will be done in the IBM/CERN frame contract Cost will be in the IBL project - ~ 500kCH Do we need MoU for such a large commitment? It seems that money could be available by Institutes involved in the project, but will then need to be recognised as IBL contribution! Need to balance between risk of 2009 submission and that of adding a delay that will propagate to the whole IBL project…

12 IBL Kick-off Meeting – Summary & Issues G. Darbo – INFN / Genova UPO, 21 July 2009 12 TDR Kevin and Mar together with PL and TC proposed chapter editors: Waiting for response… Editors kick-off meeting July 22 nd Tight schedule if we want to have TDR published 1/4/2009 TDR as important document to FA’s release of money TDR Chapter Structure 1. Introduction 2. Overview 3. Modules 4. Staves 5. Integration 6. Installation 7. Off-detector 8. Prototyping, Testin g 9. Critical Integration 10. Commissioning 11. Management

13 IBL Kick-off Meeting – Summary & Issues G. Darbo – INFN / Genova UPO, 21 July 2009 13 TDR - Schedule ActionDeadline # Weeks from previous TDR Printout, submission to LHCCApril 1 st 20102 Final Draft Deadline for commentsMarch 15 th 20102 Sent to Collaboration for ApprovalMarch 1 st 20102 Draft 2 Deadline for commentsFeb 15 th 20103 Sent to CollaborationJan 25 th 20102 Draft 1 Deadline for commentsJan 11 th 20104 Sent to CollaborationDec 15 th 20092 Approval by TDR Editors and PO/USGDec 1 st 20092 Preparation TDR IntegrationNov 16 th 20093 Editors meeting 4 - final internal draftOctober 19 th 20093 Editors meeting 3September 28 th 20093 Editors meeting 2September 7 th 20093 Editors meeting - final chapter’s structureAugust 19 th 20093 Editors Kick off meetingJuly 22 nd 2009

14 IBL Kick-off Meeting – Summary & Issues G. Darbo – INFN / Genova UPO, 21 July 2009 14 Conclusion IBL kick-off meeting was quite successful Large interest in the project – many Institutes, many FTE’s Enough money looks available for the project Some over subscription and some little covered Financial side Funding model proposed Money matrix in development iMoU and firm pledges on the way TDR Proposed chapter editor names, waiting for some replies TDR editors kick-off meeting tomorrow FE-I4 Readiness review – funding - submission


Download ppt "IBL Kick-off Meeting – Summary & Issues G. Darbo – INFN / Genova UPO, 21 July 2009 o IBL kick off meeting summary and issues ATLAS Upgrade Project Office."

Similar presentations


Ads by Google