The Republic of the Union of Myanmar Ministry of Electric Power Electricity Supply Enterprise Ayeyarwady Region Office Priorities and Detailed Description of Electrification Plan For Ayeyarwady Region Dated -21.Oct.2015
2
As Per DE Idea after discussion with Local government The Ayeyarwady Division is Located in the delta Region of lower Myanmar. Although there are many village in the Ayeyarwady Division, the villages which hare been electrifed are only (5.78 %). So we are strongly eager to be (100%) electrified villages in Ayeyarwady Division as quickly as passible. There are ( 11908 ) villages in the Ayeyarwady Division. Among them ( 689 ) Villages have been Electrified from the national grid. I would like to implement (689) Villages have been electrified from the national grid. I would like to Implement (719) villages which are located within 2 miles of existing electricity gird lines for the first phase electrification plan. This plan with be elective for ( 131925 ) households.And than, the remainder of village will be implement continuosly accroding to over National Electrification plan. Our MOEP also consents to this priority electrification project. During implementation of National Electrification plan, We are faced with same difficulties as there are so mony rivers, Streams,lakes and mountain ranges in the Ayeyarwady Division. In some places we can face with a little difficutly. The transportation and construction will be normlly easy it will not take time, So it can be implemented in short time. Our MOEP, DRD and consultants with foreign and local experts have to negotiate, coordinate and cooperate especially with local Government, Rural Development Depertment and other respective organizations to over come some perspective issues and challenges. 2
3
The additional electrification statement due to newly and upgrading 66/33/11kV substation and related power line for Ayeyarwady Region Sr No Township To Be Constructed The effective area (within 2 Miles) Estimated Cost (millon kyats) Substation 66kV Line (mile) 33kV Line (mile) Total Vill(ages (Nos) Total Househo ld (Nos) Total Populati on (Nos) Material cost Installati on cost Total cost 1Pathein 66/11kV, 5MVA (NEW) 1-313646160491590.58177.011767.59 2 Kangyidou nt 66/11 kV, 5 MVA(NEW) 0.218212974001526.49168.161694.65 3TharBound 33/11 kV, 5 MVA(NEW) -1014166768461005.65164.631170.28 4 Kyonepya w 33/11 kV, 5 MVA(NEW) -1817895367640.32111.61751.93 5 Maubin (YaLae) 33/11 kV, 5 MVA(NEW) -939419117880964.95157.851122.8 6 Maubin * Upgrade 33/11kV 5 MVA To 10 MVA -703.52514.7718.23 7Dedaye Upgrade 33/11kV 2MVA To 5 MVA -46082493599.73105.83705.56 8Danaphyu Upgrade 33/11kV 5MVA To 10 MVA -51438919617698.63127.47826.10 9 Nyaung Ton Upgrade 33/11kV 5MVA To 10 MVA -33438016576698.63127.47826.10 Total1.2201982279992228 8428.5051154.739583.24 REMARK – * For Maubin 33/11 kV, 10 MVA Substation, Only Installation & Service Charges are needed 3
4
Detailed Electrification Plan for Ayeyarwady Region (Within 2 miles from Existing 11 kV Distribution Line) NoNo Town ship Name of village To be Electri fi- ed No of Hous e Hou se hold Popu lation To be constructed Estim a tedcos t (Mil Kyate s) Task by regional cost for 11 kV line11/0.4 Transformer 400 V Line s (Mile s) Estim a tedCo st (Mil Kyate s) mile Materi- al Cost Trans Port Cost Const ructio n Cost TotalKVANo Mater ial Cost Trans Port Cost Con st ruct ion Cos t Total 1 Pathei n 21921400 2175 0 8793 6 194. 2 4628.6 290.7 8 793.8 9 5713. 2 194 00 18 9 2270. 44 68.88 158. 2 2512. 14 8214.1 2 150. 5 6492.3 88 2 Hinthat a 23437023 3849 8 1481 97 474. 5 11344. 2 708194314077 336 40 37 7 2524. 71 88.9 187. 2 2894. 1 4876.4 74 361. 2 9403.4 1 3 Ma U Bin 13514408 1441 6 6038 1 110. 8 2642.3 6 165.7 9 456.1 9 326.1 1 153 90 13 5 1625. 48 49.4 108. 8 1783. 38 5044.7 6 117.1 5251.9 18 4 Pyapo n 3662576458 2198 6 51.71235.677.6 211.9 7 1525. 8 420 0 38 462.4 18 13.5328.8 513.8 3 2039.0 2 56.3 2527.2 5 5 Myaun g Mya 6091299420 4093 7 57.7 1378.4 3 86 236.0 8 1721. 9 822 0 65 838.2 3 24.752 914.9 37 2636.8 66.8 5 2280.8 7 6 Laputt a 3566755822 2474 9 28.6683.542.9117.3843.7 348 0 35400.213.928.7442.9128732.3 1278.6 9 Total 71994892 9636 4 3841 86 917. 5 21912. 69 1371. 07 3758. 43 24207.7 847 30 83 9 8121. 48 259.3 1 563. 7 9061. 29 24098. 17 784. 25 27234. 5 4
5
To be Constructed 11 kV Distribution Line 917.5 miles 400 V Distribution Line 784.25 miles 11/0.4 kV Distribution Transformer 839 Nos No. of Villages - 719 Nos No. of house hold - 96364 Pathein District No. of Villages - 219 Nos Household - 21750 Estimated Cost - 8214.12 (mil kyats) Myaung Mya District No. of Villages - 60 Nos Household - 9420 Estimated Cost - 2636.8 (mil kyats) Laputta District No. of Villages - 35Nos Household - 5822 Estimated Cost - 1289 (mil kyats) Pyar Pon District No. of Villages - 36 Nos Household - 6458 Estimated Cost - 2039.02 (mil kyats) Maubin District No. of Villages - 135 Nos Household - 14416 Estimated Cost - 5044.7 (mil kyats) Hinthata District No. of Villages - 234 Nos Household - 38498 Estimated Cost - 4876.47 (mil kyats) Electrification Plan for Villages of Ayeyarwady Region (Within 2 miles from Existing 11 kV Distribution Line) 5
6
Detailed Electrification Plan for Pathein District (Within 2 miles from Existing 11 kV Distribution Line) NoNo Townshi p Name of village To be Electri fi- ed No of Hou se Hou se hold Pop u latio n To be constructed Estim a Ted cost (Mil Kyate s) Task by regional cost for 11 kV line11/0.4 Transformer 400 V Line s (Mile s) Estim a- tedCo st (Mil Kyate s) mil e Mater ial Cost Tran s Port Cost Cons t ructi on Cost Total KV A No Mater ial Cost Tra ns Port Cos t Cons t ructi on Cost Total 1Pathein313646 1604 9 36865.4754.3148.4 1068. 2 400 0 36 456.36 9 1329 498.2 7 1566.4 6 38 1711.1 7 2 Kan Gyi Dout 1820512129740024561.8435.2596.35 693.4 4 195 0 18 211.80 9 6.314 232.5 1 925.94 7 16695.78 3Thapaung14 16671687684614 334.7 1 2157.4 413.1 1 101 0 15 158.2 3 5.412 175.5 8 589.8 48 21699.46 4 Nga Pu Taw 5436 17199.5227.0514.338.95280.3500556.7651.9462.67342.923.1139.16 5Ye Kyi914462 1920 5 28662.2541.55113.6 817.3 7 353 0 52 575.58 4 2042 636.7 3 1454.1 1 4.7 210.97 8 6 Ngathaing Chaung 815921676807610.525115.7543.05309.8110010100.33.046.4109.7419.68.25370.33 7Athoke8 1048109141337.4 177.4 2 11.1330.43 218. 97 9508 123.1 0 2.86.4 132.3 0 351.2 83 9.5426.45 8Kyaunggon5 49854023188 191.2 6 1232.8 236. 06 6805 70.50 8 1.8476.26 312.3 22 5224.45 9 Kyone Pyaw 8 1789 536711262.916.545.1 324. 5 135 0 8 113.4 8 3.046.4 122.9 2 447.4 2 14.4644.16 10A Htaung1723352418921127.7662.0341.6113.6817.2 240 0 17 218.59 6 6.4613.6 254.0 4 1058.817764.46 11 NgaYote kaung 8 828 30548.1 193.5 9 12.433.21 239. 2 8508 93.30 9 3.0415.6 111.9 4 351.19404.00 12 Hing Gyi Kyun 6 1048 455810239.081541 295.0 8 108 0 7 92.38 8 2.14.899.23 394.3 08 4.5202.00 Total 21921400 2175 0 8793 6 194. 2 4628.6 290.7 8 793.89 5713. 2 194 00 189 2270.4 4 68.8 8 158.2 2512. 14 8214.1 2 150.5 6492.3 9 6
7
Ahtoung No. of Villages - 17 Nos Household - 2418 Estimated Cost - 1058.8 (mil kyats) To be Constructed 11 kV Distribution Line 194.2 miles 400 V Distribution Line 150.5miles 11/0.4 kV Distribution Transformer 189 Nos No. of village - 219 Nos No. of house hold – 21750 Yekyi District No. of Villages - 91 Nos Household - 4462 Estimated Cost - 1454.11 (mil kyats)0 Kyone Pyaw Township No. of Villages - 8 Nos Household - 1789 Estimated Cost - 447.42 (mil kyats) Nga Thaing Chaung No. of Villages - 8Nos Household - 1676 Estimated Cost - 419.6 (mil kyats) Thar Bound Township No. of Villages - 14 Nos Household - 1687 Estimated Cost - 589.8 (mil kyats) Nga Yote Kount Township No. of Villages - 8 Nos Household - 828 Estimated Cost - 351.1 (mil kyats) Hing Kyi Kyun District No. of Villages - 6 Nos Household - 1048 Estimated Cost - 394.308 (mil kyats) Nga Pu Taw District No. of Villages - 5 Nos Household - 463 Estimated Cost - 342.92 (mil kyats) Pathein District No. of Villages - 31 Nos Household - 3646 Estimated Cost - 1566.46 (mil kyats) Kan Gye Dount Township No. of Villages - 18 Nos Household - 2129 Estimated Cost - 925.947 (mil kyats) Kyaung Kone Township No. of Villages - 5 Nos Household - 540 Estimated Cost - 312.322 (mil kyats) Electrification Plan for Villages of Pathein District (Within 2 miles from Existing 11 kV Distribution Line) 7
8
Detailed Electrification Plan for Hinthata District (Within 2 miles from Existing 11 kV Distribution Line) NoNo Town ship Name of village To be Electrifi ed No of Hous e Hous e hold Popu latio n To be constructed Esti ma ted cost (Mil Kyat es) Task by regional cost for 11 kV line11/0.4 Transformer 400 V Line s (Mile s) Esti ma Ted Cost (Mil Kyat es) mile Mate rial Cost Tran s Port Cost Con st ruc tion Cost Tota l KVANo Mater ial Cost Tran s Port Cost Cons t ructi on Cost Total 1Hinthata12112327 4847 9 166 3968. 4 249680.84898 1023 0 12 1 1315. 99 45.9 8 96.8 1458.8 69.98 3 106 4758. 23 2 Kyan Khin 171058 390119454.128.577.96461200171786.4613.6198 789.5 61 14.1 481.0 92 3 Myaung Aung 3434524351 1588 0 37884.355.5151.71088476034442 12.9 2 27.2482 1570. 34 54.2 1849. 30 4Ingupu4118644 1876 9 7129 8 231 5509. 9 346945.26801 1589 0 18 4 460.4 5 15.5 8 32.8 508. 83 1556. 1 170 1556. 08 5Zalun9683110449296.51696.526 201. 5 650913.427.2 105. 05 306.5 5 4.5 201.9 6 6 LayMya t Nar 12859889371015358.522.561.5 442. 5 91012 127.2 77 4.569.6 141. 44 583.9 4 12.4 556.7 48 Total 2343702338498 14819 7 474. 5 11344.2 7081943 1407 7 3364 0 377 2524.7 17 88.9187.2 2894. 1 4876.4 74 361.2 9403.4 1 8
9
9
10
Detailed Electrification Plan for Ma U Bin District (Within 2 miles from Existing 11 kV Distribution Line) NoNo Town ship Name of village To be Electrifi ed No of Hou se Hou se hold Pop u latio n To be constructed Estim a tedco st (Mil Kyate s) Task by regional cost for 11 kV line11/0.4 Transformer 400 V Line s (Mile s) Estim a tedCo st (Mil Kyate s) mil e Mate rial Cost Tran s Port Cost Con st ruc tion Cost Tota l KVA NoNo Mate rial Cost Tra ns Port Cos t Cons t ructi on Cost Total 1Ma U Bin394191 1788 0 48114471.78196.2 1411. 9 433039 462.7 35 1431 507.5 9 1919.5 4 24 1095.2 9 2 Nyaung Ton 334380 1657 6 19 461.4 2 28.9579.13 569.5 0 503033 443.3 32 1226 481.2 8 1050.7 9 411858.4 3Danu Phyu514389 1961 7 31.8760.847.73130.5938.9428051559.317.940.8617.9155739.1 1755.1 6 4 Pan Ta Naw 1214481456630812 276.1 4 17.3347.36 340.8 1 175012 160.1 2 5.511 176.6 2 517.43 7 13 579.06 8 Total135 1440 8 1441 6 6038 1 110. 8 2642. 36 165.7 9 453.1 9 3261. 1 1539 0 13 5 1625. 48 49.4108.8 1783. 38 5044.7 6 117.1 5251.9 18 10
11
Electrification Plan for Villages of Ma U Bin District (Within 2 miles from Existing 11 kV Distribution Line) Dya Nu Phyu Township No. of Villages - 51 Nos Household - 4389 Estimated Cost - 1557 (mil kyats) Nyaung Ton Township No. of Villages - 33 Nos Household - 4380 Estimated Cost - 1050.79 (mil kyats) Pan Ta Naw Township No. of Villages - 12 Nos Household - 1456 Estimated Cost - 517.43 (mil kyats) Me U Bin District No. of Villages - 39 Nos Household - 4191 Estimated Cost - 1919.54 (mil kyats) To be Constructed 11 kV Distribution Line 110.8 miles 400 V Distribution Line 117.1miles 11/0.4 kV Distribution Transformer 135 Nos No.of village -135 Nos No.of house hold - 14416 11
12
Detailed Electrification Plan for Pyapon District (Within 2 miles from Existing 11 kV Distribution Line) NoNo Town ship Name of village To be Electrifi ed No of Hous e Hous e hold Popu latio n To be constructed Estim a ted cost (Mil Kyate ) Task by regional cost for 11 kV line11/0.4 Transformer 400 V Line s (Mile s) Estim a tedCo st (Mil Kyate s) mil e Mate rial Cost Tran s Port Cost Con st ruc tion Cost Tota l KVA NoNo Mate rial Cost Tra ns Port Cos t Cons t ructi on Cost Total 1Pyapon3 9209793448371.74.512.388.54003 38.09 4 1.142.451.5 140 3.8 170.57 8 2 Kyaikla tt 71190124931029.5 227.0 5 14.2538.95 280.2 5 7008 80.40 6 2.515.6 87.73 1 367.98 1 8359.11 3Dedaye4 52560824934.2 100.3 8 6.317.22 123. 9 7004 57.51 7 1.523.2 62.23 7 186.146 269.33 4 4 Bokala y 223622 1294335836.552.5143.51033240023 286.4 01 8.3617.6 312.3 61 1344.938.5 1728.2 3 Total36625764582198651.7 1235. 63 77.55 211.9 7 1525. 7 420038 462.4 18 13.5 3 28.8 513.8 29 2039.0 2 56.3 2527.2 5 12
13
Dadaye No. of Villages - 4 Nos Household - 608 Estimated Cost - 86.14 (mil kyats) Kyiaklatt Township No. of Villages - 7 Nos Household - 1249 Estimated Cost - 384.12 (mil kyats) Pyapon Township No. of Villages - 3 Nos Household - 979 Estimated Cost - 140 (mil kyats) Bogalay District No. of Villages - 23 Nos Household - 3622 Estimated Cost - 1344.9 (mil kyats) To be Constructed 11 kV Distribution Line 51.7 miles 400 V Distribution Line 56.3 miles 11/0.4 kV Distribution Transformer 41 Nos No. ot village – 36 Nos No.of house hold - 6458 Electrification Plan for Villages of Pyapon District (Within 2 miles from Existing 11 kV Distribution Line) 13
14
Detailed Electrification Plan for Myaung Mya District (Within 2 miles from Existing 11 kV Distribution Line) NoNo Town ship Name of village To be Electrifi ed No of Hou se Hou se hold Pop u latio n To be constructed Estim a tedco st (Mil Kyate s) Task by regional cost for 11 kV line11/0.4 Transformer 400 V Line s (Mile s) Estim a tedCo st (Mil Kyate s) mil e Mate rial Cost Tran s Port Cost Con st ructi on Cost Tota l KVA NoNo Mate rial Cost Tra ns Port Cos t Cons t ructi on Cost Total 1 Myaung Mya 2130203152 1270 4 23.4 559.8 5 34.695.65690.1261021 258.9 3 7.9816.8 283.7 1 973.8125.4866.64 2Wakema6 169017287102 5.7 5 137.4 3 8.6323.58 169. 6 90010 137. 74 3.88 149. 54 319.179307.08 3 Kyonmang e 11 18411962 1001 5 7.1 169.6 9 10.729.11 209. 5 167012 162. 68 4.569.6 176. 84 386.2912.5426.5 4Ei Me222578 1111621.4 511.4 6 32.187.74652.7304022 278.8 9 8.3617.6 304.8 5 957.5520680.65 Total60 91299420 4093 7 57.7 1378. 43 86 236.0 8 1721. 9 822065 838.2 37 24.752 914.9 37 2636.866.85 2280.8 7 14
15
Ei Me Town ship No. of Villages - 22 Nos Household - 2578 Estimated Cost - 957.55 (mil kyats) To be Constructed 11 kV Distribution Line 57.7 miles 400 V Distribution Line 66.85 miles 11/0.4 kV Distribution Transformer 65 Nos No.of village – 36 Nos No.of house hold - 9420 Wakema Township No. of Villages - 6 Nos Household - 1728 Estimated Cost - 319.17 (mil kyats) Kyone ma nge Township No. of Villages - 11 Nos Household - 1962 Estimated Cost - 386.29 (mil kyats) Myaung Mya Township No. of Villages - 21 Nos Household - 3152 Estimated Cost - 973.81 (mil kyats) Electrification Plan for Villages of Myaung Mya District (Within 2 miles from Existing 11 kV Distribution Line) 15
16
Detailed Electrification Plan for Laputta District (Within 2 miles from Existing 11 kV Distribution Line) NoNo Township Name of village To be Electrif - ied No of Hou se Hou se hold Pop u latio n To be constructed Estim a tedco st (Mil Kyate s) Task by regional cost for 11 kV line11/0.4 Transformer 400 V Line s (Mile s) Estim a tedCo st (Mil Kyate s) mil e Mate - rial Cost Tran s Port Cost Cons t ructi on Cost Tota l KVA NoNo Mate rial Cost Tra ns Port Cos t Cons t ructi on Cost Total 1Laputta18 46673758 1520 7 14. 1 337 21.1 5 57.81416207018 216. 2 7.4615.1 238. 8 654.716.4736.18 2 MawLamyin g gung 17 200820649542 14. 5 346.6 21.7 5 59.45 427. 8 1410171846.4613.6 204. 1 631.915.9 542.50 8 Total35 66755822 2474 9 28. 6 683.542.9117.3 843. 7 348035 400. 2 13.928.7 442. 9 128732.3 1278.6 9 16
17
To be Constructed 11 kV Distribution Line 28.6 miles 400 V Distribution Line 32.3miles 11/0.4 kV Distribution Transformer 35 Nos No.of village – 35 Nos N0.of hhould hold- 5822 Mawlamyaing KyunTownship No. of Villages - 17 Nos Household - 2064 Estimated Cost - 631.9 (mil kyats) Laputta Township No. of Villages - 18 Nos Household - 3758 Estimated Cost - 654.7 (mil kyats) Electrification Plan for Villages of Laputta District (Within 2 miles from Existing 11 kV Distribution Line) 17
18
No Fiscal Year Ayeyarwaddy Region Capital Budget for ESE(mil kyats) Ayeyarwaddy Region Capital Budget for DRD (mil kyats) Electrified Connection ON GridOff Grid Total Cost for 11 kV Line & 11/0.4 kV Tr; Total Cost for 400 V line TotalOff Grid Village (Nos) Consum er (Nos) Villa ge (Nos) Consum er (Nos) 1 2014-2015 Estimate (BE+RE) 607.634257.03864.676043.3663650019632702 2 2015-2016 Estimate (BE+RE) 413.134197.877611.023054.151251310021215425 3 2016-2017 Budget Estimate (BE) 19395192458- 725 96364 -- Total2959.77973.91 3933.6 9 9097.5191311596440848127 The Statement of Fiscal Yearly Budget and Electrified Connection for Ayeyarwady Region 18
19
Sr No Description Quantitie s Transported Site 1 11/0.4 kV Distribution Transformer 182 Nos Pathein sub-ststion 1,2 2.10 meter Concrete Pole8504 Nos Pathein sub-ststion 1,2 3.ACSR 95mm 2 712.5 Ton Pathein sub-ststion 1,2 4.11kV Disc Insulators6660 Set Pathein sub-ststion 1,2 4.11kV Pin Insulators24420 Set Pathein sub-ststion 1,2 5. Surge arresters, Disconnectors, Fuses 212 Set Pathein sub-ststion 1,2 6.Other Material1 Lot Pathein sub-ststion 1,2 Main Materials List Transported to Pathein District Office 19
20
Sr No Description Quantitie s Transported Site 1 11/0.4 kV Distribution Transformer 377 Nos Hinthada sub-station & Myaung Aung Gas Tarbine 2.10 meter Concrete Pole 21654 Nos Hinthada sub-station & Myaung Aung Gas Tarbine 3.ACSR 95mm 2 1187.5 Ton Hinthada sub-station & Myaung Aung Gas Tarbine 4.11kV Disc Insulators17100 Set Hinthada sub-station & Myaung Aung Gas Tarbine 4.11kV Pin Insulators62700 Set Hinthada sub-station & Myaung Aung Gas Tarbine 5. Surge arresters, Disconnectors, Fuses 407 Set Hinthada sub-station & Myaung Aung Gas Tarbine 6.Other Material1 Lot Hinthada sub-station & Myaung Aung Gas Tarbine Main Materials List Transported to Hinthada District Office 20
21
Sr No Description Quantitie s Transported Site 1 11/0.4 kV Distribution Transformer 135 Nos Ma U Bin District,PMO Office 2.10 meter Concrete Pole5154 Nos Ma U Bin District,PMO Office 3.ACSR 95mm 2 275 Ton Ma U Bin District,PMO Office 4.11kV Disc Insulators3960 Set Ma U Bin District,PMO Office 4.11kV Pin Insulators 14652 Set Ma U Bin District,PMO Office 5. Surge arresters, Disconnectors, Fuses 165 Set Ma U Bin District,PMO Office 6.Other Material1 Lot Ma U Bin District,PMO Office Main Materials List Transported to Ma U Bin District Office 21
22
Sr No Description Quantitie s Transported Site 1 11/0.4 kV Distribution Transformer 41 Nos Pyapon sub-station & Kyaiklatt sub- station 2.10 meter Concrete Pole2370 Nos Pyapon sub-station & Kyaiklatt sub- station 3.ACSR 95mm 2 130 Ton Pyapon sub-station & Kyaiklatt sub- station 4.11kV Disc Insulators1872 Set Pyapon sub-station & Kyaiklatt sub- station 4.11kV Pin Insulators6864 Set Pyapon sub-station & Kyaiklatt sub- station 5. Surge arresters, Disconnectors, Fuses 71 Set Pyapon sub-station & Kyaiklatt sub- station 6.Other Material1 Lot Pyapon sub-station & Kyaiklatt sub- station Main Materials List Transported to Pyapon District Office 22
23
Sr No Description Quantitie s Transported Site 1 11/0.4 kV Distribution Transformer 65 Nos Myaung Mya sub-station 2.10 meter Concrete Pole2682 Nos Myaung Mya sub-station 3.ACSR 95mm 2 145 Ton Myaung Mya sub-station 4.11kV Disc Insulators2088 Set Myaung Mya sub-station 4.11kV Pin Insulators7656 Set Myaung Mya sub-station 5. Surge arresters, Disconnectors, Fuses 85 Set Myaung Mya sub-station 6.Other Material1 Lot Myaung Mya sub-station Main Materials List Transported to Myaung Mya Office 23
24
Sr No Description Quantitie s Transported Site 1 11/0.4 kV Distribution Transformer 35 Nos Laputta sub-station 2.10 meter Concrete Pole1346 Nos Laputta sub-station 3.ACSR 95mm 2 72.5 Nos Laputta sub-station 4.11kV Disc Insulators1044 Set Laputta sub-station 4.11kV Pin Insulators3828 Set Laputta sub-station 5. Surge arresters, Disconnectors, Fuses 45 Set Laputta sub-station 6.Other Material1 Lot Laputta sub-station Main Materials List Transported to Laputta District Office 24
25
25