On behalf on EN-EL October 1 st, 2015 YETS 2015-2016 Works EN-EL [ CF excluded ]
2
YETS 2015-2016 – Works EN-EL [CF excluded] On behalf on EN-EL October 1 st, 2015 Concerning the whole CERN : Annual test for the Safety networks 10’ power cut of « General Services » & « Safety » networks at 7:00 am in a working day Auto-transfer test PS – Booster impacted only a week-end on the Meyrin site All other sites (SPS – LHC – 513 – MEY hors PS – Prevessin –ZN…) repowered without power cut on degraded configuration during the week-end Meyrin - LHC1 – LHC18 - BA6 – BA7 Safety network not available only Saturday in working hours ! EL IMPACTS for the YETS 2015-2016
3
On LHC (1/3) : AUG tests 9 days, 1 day by site – Arcs affected 2 times N/S Automatism on LHC5 Circuit breaker Replacement on safety switchboard ESD1/5E and normal switchboard EBD1/5E : Works during X-Mas break ? Prohibited access in underground LHC5 - PM56 and CMS PX15 and demi-arcs 5-6 & 4-5 Automatic transfer switch on CV pressurisation switchboard on LHC5 : Works during X-Mas break ? Prohibited access in underground LHC5 PX54_CMS. USC55 : LV circuit breaker replacement for selectivity EL IMPACTS for the YETS 2015-2016 YETS 2015-2016 – Works EN-EL [CF excluded] On behalf on EN-EL October 1 st, 2015
4
On LHC (2/3) : Automatic transfer switch on CV pressurisation switchboard on LHC1 Works during X-Mas break ? Prohibited access in underground PX15_ATLAS Circuit breaker/contactor replacement on ATLAS LV switchboard in UX15 EXD1/15X and EXD2/15X 2 x 2 days EQD2/1H modification for the adjunction of a column for TE/CRG ATLAS Power cut of TE/CRG switchboard - 1 day (15-16 December proposed by TE/CRG) Feeders modifications on ATLAS switchboard EOD8/15A – EXD2/1DX – EXD4/15A – EBD1/15A 1 day by switchboard EL IMPACTS for the YETS 2015-2016 YETS 2015-2016 – Works EN-EL [CF excluded] On behalf on EN-EL October 1 st, 2015
5
On LHC (3/3) : Test of redundancy feeders QPS LHC machine to eliminate non-compliances Done on compliance logical blocking signals and 18 kV protections tests of the LHC loop points 1 -5 -6 -7 -8 Opening of LHC 18kV loop, without power cut, in coordination with AUG tests Done on compliance equipment on LV switchboard Limited LV power cuts Maintenances 48V, transformers, UPS, and more spécifically UPS Cryo LHC 48V PLC revamping LHC1 – USA15 - SDX5 – USC55 – SE18 Without power cut LHC18, Replacement of 5 I/O frames Supervision affected, without power cut EL IMPACTS for the YETS 2015-2016 YETS 2015-2016 – Works EN-EL [CF excluded] On behalf on EN-EL October 1 st, 2015
6
On SPS (1/2) : AUG tests 7 days on working days Oil treatment for 400/18 kV transformer EHT2/BE Pulsed network Replacement MN coil on WS-Net ORMAZABAL switchboard and supervision consolidation The day of the BA6 or LHC1 AUG test ? Logipam update for BB6 18 kV protection relay and PLC update for WS-net 18 kV N/S automatism WS-SPS & WS-LHC power cuts, with AUG tests ? EL IMPACTS for the YETS 2015-2016 YETS 2015-2016 – Works EN-EL [CF excluded] On behalf on EN-EL October 1 st, 2015
7
On SPS (2/2) : Power cut of 18 kV circuit breaker EMD303/B3 for supervision update Pulsed network, RF power cur in BB3 Cabling and cable ways identification for BA’s SPS Maintenance UPS, 48V, transformers… 48V PLC revamping BB4 –BA7 –BE9 Without power cut BAF3 Preparation Disconnections, cables and ways dismantling Area creation for RF & CV EL IMPACTS for the YETS 2015-2016 YETS 2015-2016 – Works EN-EL [CF excluded] On behalf on EN-EL October 1 st, 2015
8
On the North Area and the Prevessin site : AUG tests 4 days – 1 day by site – Working days except for Prevessin Obsolete 48V chargers replacement for BA82 N/S automatism replacement (PLC+HMI) for BB81 diesel generator No Safety network on EHN1-BA81-BA85 during 3 days UPS maintenance in BE91 substation, for CCC CCC protected by the UPS redundancy in BE91 Maintenance UPS, 48V, transformers… EL IMPACTS for the YETS 2015-2016 YETS 2015-2016 – Works EN-EL [CF excluded] On behalf on EN-EL October 1 st, 2015
9
On Meyrin (1/2) : Replacement of 48V chargers for ME25-ME23-ME11-ME6-ME16-ME9 Installation of a new 48V system for ME50 & ME64 Update of logic protection for the 66kV incomer in ME59 18 kV reconfiguration on Meyrin site, without power cut Extension of the 18 kV switchboard in ME50 Power cut of demineralised water production b.378 during 1 day – LHC Impact Replacement MN coil on ORMAZABAL switchboard in ME13 & ME15 The day of the AUG test ? Modification Auto-transfer 18 kV coupling circuit breaker EMD301*9 and update of the auto-transfer PLC in ME9 JURA No Auto-transfer during 3 days EL IMPACTS for the YETS 2015-2016 YETS 2015-2016 – Works EN-EL [CF excluded] On behalf on EN-EL October 1 st, 2015
10
On Meyrin (2/2) : AUG tests 5 days … during week-ends ! Displacement of the EBD14*80 in b.179 1 day power cut Replacement of the LV switchboard in ME15 (if not finished before) Limited power cuts of General Services 48V PLC revamping ME6 – ME9 – ME11 –ME23 –ME43 Without power cut Installation 18 kV circuits breakers in ME25 for b.245 POPS-B Installation new LV switchboard and mechanicals supports for PSB area Replacement AUG rack in ME62 Maintenance UPS, 48V, transformers … EL IMPACTS for the YETS 2015-2016 YETS 2015-2016 – Works EN-EL [CF excluded] On behalf on EN-EL October 1 st, 2015
11
Thank you for your attention !