October 4-5, 2010 1 Status of ARRA funded AIPs Stochastic Cooling Alex Zaltsman October 4, 2010 Stochastic Cooling cost and schedule.

Similar presentations


Presentation on theme: "October 4-5, 2010 1 Status of ARRA funded AIPs Stochastic Cooling Alex Zaltsman October 4, 2010 Stochastic Cooling cost and schedule."— Presentation transcript:

1 October 4-5, 2010 1 Status of ARRA funded AIPs Stochastic Cooling Alex Zaltsman October 4, 2010 Stochastic Cooling cost and schedule

2 October 4-5, 2010 2 Outline Scope Funding and Costs Major Milestones Management and Reporting Bumps in the Road Safety From here to completion

3 October 4-5, 2010 3 Scope Engineer, procure and install a horizontal Stochastic Cooler and associated equipment in the RHIC Blue and Yellow rings. –The major procurements include amplifiers, electronics and vacuum vessel assemblies. Each ring contains: –2 vacuum vessels with 8 cavities per vessel –1 pickup

4 October 4-5, 2010 4 Funding and Costs

5 October 4-5, 2010 5 Major Milestones Currently ahead of planned schedule The possibility still exists for installation of one pickup before RHIC start-up.

6 October 4-5, 2010 6 Management and Reporting Internally Weekly and Monthly Budget and Expense reports Monthly labor reports (hours charged by individuals) Open purchase orders/purchase requisitions report (available daily) Reporting to DOE Execution Plan Monthly ARRA milestone progress reports Monthly teleconferences Quarterly reports Quarterly teleconferences

7 October 4-5, 2010 7 Bumps in the road… Our design requires a large rectangular vacuum seal for the kicker tanks which we were trying to develop with outside vendors but were unsuccessful. This delayed us by 3-4 months, and the final resolution was to weld the tanks.

8 October 4-5, 2010 8 Safety ARRA AIPs are fully integrated into the C-AD Safety organization and subject to the same standards as RHIC –ESSH&Q Division and Safety Committees –Procedures and safe practices –Trained supervisors and employees –All work has been done safely. No safety occurrences on the project.

9 October 4-5, 2010 9 Safety Completed Safety milestones (on Indico) –NEPA review –Design Review questionnaire –Preliminary Hazard Screening Report Planned Safety milestones/reviews: –Accelerator Systems Safety Review Committee (ASSRC) –Radiation Safety Committee (RSC)

10 October 4-5, 2010 10 from here to completion… Current and ongoing –Finish assembly –Testing –Installation Planning Installation –No major risks are foreseen for the installation during the summer shutdown 2011.


Download ppt "October 4-5, 2010 1 Status of ARRA funded AIPs Stochastic Cooling Alex Zaltsman October 4, 2010 Stochastic Cooling cost and schedule."