Injectors & LHC report S. Baird and M. Bernardini on behalf of OSS members 20/09/2013LSC - EN-MEF-OSS1.

Similar presentations


Presentation on theme: "Injectors & LHC report S. Baird and M. Bernardini on behalf of OSS members 20/09/2013LSC - EN-MEF-OSS1."— Presentation transcript:

1 Injectors & LHC report S. Baird and M. Bernardini on behalf of OSS members 20/09/2013LSC - EN-MEF-OSS1

2 AD & LEIR 20/09/2013 LSC - EN-MEF-OSS 2 AD – Girder line 7000, procurement of material in progress, but some delay due to change of material (361 LN instead of 316L for a few chambers). – BHN06: official decision circulated – UHM3107 and UVM3207 tanks : Pumping and leak test in progress – KFI tanks reinstallation expected mid Oct.- final leak tests in progress – Installation of a railing for OD in progress LEIR – Successful brief opening vacuum sector 5 (removal IMP’s) last week. Sectors 1, 2 and 5 in preparation in view of coming bake-out campaign (1/10 until 15/11). – Cleaning campaign - 2 nd phase form next week – Access system - general tests OK Some mechanical issues to fix and then the access point will be officially be put into service (soon).

3 PS In Progress – CV Consolidation program: Cabling work is in progress Ventilation ducts installation – Septum 16 External Shielding program: Pilling work is completed – Cabling campaign Septa and vacuum teams are starting to connect and to test new cables – General equipment maintenance: Instrumentation, vacuum,, Beam Stoppers, (EN/STI) consolidation/maintenance program – PS PSS Safety and Access System installed – Successful test of assembly blocks for the dummy septum (ECR 1307208) – LEIR injection beam line MTV intervention 20/09/2013 LSC - EN-MEF-OSS3

4 PSB In progress – PSB beam dump replacement project on schedule. Survey of the beam dump cavity revealed a downward slope of 1cm over 2 M. The beam dump cavity is not continuous and is made up of 2 cylinders of 3 and 2 meter lengths respectively. At the junction of the 2 cylinders, a slight descent of the 2 nd downstream cylinder explains the discontinuity of the rail profile. Civil engineering are to drill and extract samples from the dump foundations in order to analise the composition of the base materials (soil or concrete). Depending on the outcome, Civil engineering may have to inject a stabilising resin into the beam dump foundations possibly delaying the beam dump installation by ~ 3 weeks. – CV consolidation and maintenance of CV, kickers, Septa, vacuum beam instrumentation, Magnet and Beam stopper, cabling campaign. – Replacement of PSB ring 32A electrical power sockets. Completed. – Decontamination of the beam dump cavity. – HV power testing & validation of the repaired Technix BI.DIS power supply. Forecast – Installation of the public address cables & infrastructure – Replacement of the BI.SMH. Work package analysis meeting 02/10/2013. Work to start wk 42 (14/10/2013) – Terminate and reception the access control MAD. – Survey & alignment of the BI and BT line magnets. 28/08/2013LSC - S. Baird4

5 SPS BA1: – Installation of new fibre optic systems in progress (foreseen to finish ahead of schedule) – Replacement of safety valves in progress (almost complete) – A few cables still remain to be identified (ongoing) – [Irradiated cabling campaign – beginning of October] TT10: – Installation of the new support beams is postponed to next week (Has now started. See photo) – BA3 and outside the CCC: These 2 areas are currently being cleared and tidied in preparation for the CERN open days at the end of this month. (ongoing) Other works: – EN/CV have begun to refill the main SPS ring-main (Complete) – TE/VSC have started this week to pump down and leak detect all the long sectors of SPS ( started in BA3) – All other works are proceeding on schedule 20/09/2013LSC - EN-MEF-OSS5

6 LHC - P1 R2E – Pt1: – Left: Cabling progressing well – Right: Piping finished Cabling in progress LSS1: – Survey HLS maintenance in progress – DFBX: consolidation of current leads in progress – Upgrade and maintenance of collimator control systems in progress – TCLP installed – Roman Pots removed – BPMCW being installed 20/09/2013LSC - EN-MEF-OSS6

7 LHC – P1  P2 Arc 12 : – UPS replacement in RE 18 and 22 – QRL pumped – Cryo-magnets reconnection being finalized – Electrical tests next week; – SMACC: W bellows opened M openings finished (4 wks ahead of schedule) Point 2 – SU maintenance in progress (no cooled air) – Cryogenic maintenance in progress LSS2 – Preparation for open days – RB24 opening in progress – Maintenance of motorized jacks on ITs finished 20/09/2013LSC - EN-MEF-OSS7

8 LHC - P2  P3 Arc 23 – QRL pumping in progress – Magnet reconnection in progress High voltage electrical tests phase1 performed! – DN200 installed – UPS replacement going on – W bellows openings finished – M opening just started LSS3 – Installation of the cable trays finished – cabling campaign started – BLM re-installed in completed vacuum sub-sectors 20/09/2013LSC - EN-MEF-OSS8

9 LHC - P3  P4 Arc 34 – Magnets reconnection in progress “Plaque de renfort” in place End in November – QRL pumping completed – IC consolidation: W bellows openings started – CRG services modules consolidation finished – New non conformity on nested bellow B13L3 --> to follow 20/09/2013LSC - EN-MEF-OSS9

10 LHC – P4  P5 LSS4 & P4 – Water cooled cables consolidation in progress Ducts are exchanged Work on power converter in progress Rescheduling – Short circuit tests from Oct. 21 st to Nov. 8 th –  UW maintenance postponed to March 2014 – RF maintenance and upgrade Flow meters being re-installed – New cooling tower installation in progress – 13kA & 600 A shall be finished – Thermoswitch installation just started – LSS4L: Works have to stop on Wed 25th for Open days preparation Arc 45 – QRL pumping in progress (50% of overall QRL pumped) – Magnet reconnection in progress (end Nov.) – DN200 started – DFBAI.5L – damaged bellow – Opening starts next week – [QRL compensator replacement in December] 20/09/2013LSC - EN-MEF-OSS10 WCC leak test

11 LHC – P5 LSS5: – Modification of the cabling for TOTEM ongoing – 600A upgrade in progress – Survey finished in 5L, in progress in 5R R2E – P5 – Safe room ventilation: studies being finalized; extension and new hole will be done in coming weeks; – Pipe being installed (ahead of schedule) – UPS replacement finalized – Cable trays installation in progress 20/09/2013LSC - EN-MEF-OSS11 Cable tray installation in UJ56

12 LHC – P5  P6 Arc 56 – New faulty PIM replaced-leak tested beginning Oct. – QRL compensator replacement started – SMACC 11/14 vacuum subsectors consolidation completed; Non conformities being solved W closure stopped (priority to sector 67) – DFBA consolidation in progress 5R ends week 39 DFBAK.6L – damaged bellow – repair to be scheduled 20/09/2013LSC - EN-MEF-OSS12

13 LHC – P6 LSS6 & P6 – MKD-MKB tests on beam1 finished – MKD-MKB upgrade on beam2 in progress – Cabling campaign ongoing – Water cooled cable campaign in progress – priority on DFBAK.6L – 3 TCDQ installed @6R – Lift PM65: Heavy maintenance performed. – LSS6: Works have to stop on Wed 25th for Open days preparation 20/09/2013LSC - EN-MEF-OSS13 No access by PM65 Access by PZ65

14 LHC – P6  P7 Arc 67 – SMACC in progress: Splices completed Shunt being finalized Diodes consolidation in progress W Closure activities in progress DFBA consolidation – 6R ends next week – 7L ends wk. 40 R2E – P7: – ODH and firedetection systems installed– tests done and ok – Fireproof racks tranported in TZ76 (storage) – Supports for fireproof racks installed 20/09/2013LSC - EN-MEF-OSS14 Fireproof racks and supports in TZ76 Insulation boxes; resin injection

15 LHC - P7  P8 Arc 78 – Magnet reconnection finished (except Q5L8) – Splice consolidation in progress Splices in progress (almost finished) Shunt installation in progress (~50% ) Diodes started DFBA consolidation shall end wks 43 – QRL X-rays in progress: only 1/301 inspected compensators found deformed on overall QRL LSS8 &P8 – Survey maintenance from next week – 1 st MKI re-installed R2E - P8 – Ventilation control scheduled in October – Cryo and cabling in progress 20/09/2013LSC - EN-MEF-OSS15

16 LHC – arc 81 Arc 81 - SMACC -DFBA consolidation (ends end Nov.) -Splices activities started (desolder) -QRL compensator being replaced -Vacuum consolidation from next week 20/09/2013LSC - EN-MEF-OSS16

17 Overall progress Injectors: – PSB: issue on dump line- to follow LHC – R2E – Ahead of schedule at P1- P5&P7&P8:On schedule – SMACC ~ 3 weeks of delay – QRL: no new deformed compensator; 50% pumped – Additional works QRL compensator exchange – scheduled – in progress DFBA bellow repair – to be scheduled – technical solution to be defined Open days – LHC6 and LHC4, work have to stop in LSS from Wed. night 20/09/2013LSC - EN-MEF-OSS17

18 LHC Overall Schedule – broken line 20/09/2013LSC - EN-MEF-OSS18


Download ppt "Injectors & LHC report S. Baird and M. Bernardini on behalf of OSS members 20/09/2013LSC - EN-MEF-OSS1."